FINANCE AND ADMINISTRATIVE COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Sales, Commissioner Community and Fire Services

 

 

 

 

PREPARED BY:

 Alan Wolfe, P.Eng., Project Consultant

 

 

 

 

DATE OF MEETING:

2004-Feb-16

 

 

 

 

SUBJECT:

Approval of the Museum Reception Centre Building

 

 

 


 

 

RECOMMENDATION:

That this report entitled “Approval of the Museum Reception Centre Building” be received;

 

And that Council accept the Ballantry Homes offer to contribute $250,000 in cash towards the Museum Reception Centre building;

 

And that estimated cost of construction of the Museum Reception Centre building is $600,000;

 

And that the sources of funding be as follows:

                Ballantry Contribution -  $250,000

                Closed Projects            -   $150,600

                2004 Capital Budget    -   $199,400 (to be considered with the 2004 Capital Budget).

                         Total Funding          $600,000

 

And that Council approve proceeding with the tendering process for the construction of the Museum Reception Centre building;

 

And further that staff report back to Council to award the contract for the construction of the Museum Reception Centre building.

PURPOSE:

The purpose of this report is to present to Council Ballantry Home’s offer of a $250,000 cash contribution towards the construction of the Museum Reception Centre (MRC) building.  The report is also to obtain Council authority to proceed with the construction of the building.

 

BACKGROUND:

On March 26, 2002, Council adopted Report No.15 – Finance and Administrative Committee:  Demolition of the Andrew Wideman House, 9462 Highway 48, Restitution Options, Ballantry Homes (Ballantry) with the following recommendations as amended:

 

“That Council accepts the offer by Ballantry Homes to provide services in kind in the amount of $250,000 to build a new, purpose-built, Reception Facility at the Markham Museum;

And that the Chief Administrative Officer and Town Solicitor bring forward a proposed agreement as well as proposed details of cost estimates and a methodology for measuring the cost of construction for consideration by Council;

And that Community Services staff be authorized to obtain the services of a museum architectural consultant to assist in the preparation of a functional requirements plan and design concept for the proposed museum facility;

And further that as a condition of the draft plan approval for the proposed Ballantry Homes plan of subdivision, Ballantry Homes be required to install at its cost a cairn and a 'Markham Remembered' interpretive plaque acknowledging and interpreting the former Andrew Wideman House.”

 

OPTIONS/DISCUSSION:

A Building Steering Committee (BSC) to oversee the design and construction of the Museum Reception Centre (MRC) was formed immediately after the Council decision.  The Committee consists of a representative from the Heritage, Finance, Capital Assets, Legal, and Property Departments, as well as the Museum Manager and Board Chair.  The Chief Administrative Officer (CAO) chairs the Committee and Alan Wolfe is the Project Consultant.

 

The Committee has been meeting on a regular basis and work on the project has been proceeding accordingly. The development and progress of the project is summarized below.

 

1.                  Sears and Russell Architects Limited (SRA) were engaged to complete the schematic and conceptual design, including cost estimates.

 

2.         The Schematic Design and building location was presented to Community Services Committee on September 16, 2002. The Committee adopted the following resolution:

 

“That the presentations by Alan Wolfe, Project Consultant, Linda Irvine, Manager, Parks and Open Space Development, and Jeff Weatherston, Sears and Russell Architects regarding the proposed location and preliminary building design of the Museum Reception Centre, be received;

 

And that the direction being taken by the Building Steering Committee for the proposed Museum Reception Centre be endorsed, in principle.”

 

This resolution was confirmed by Council at its meeting of October 1, 2002.

 

3.         Work on finalizing the design development proceeded over the fall 2002 and winter/spring of 2003.

 

·                    The final internal layout of the building was established. It consists of a 1000 square foot orientation room including a kitchenette and storage room, a reception area, washrooms, and an electrical room to serve the east zone of the Museum. The total size of the facility is approximately 2900 square feet.

 

·                    A detailed site plan including servicing, landscaping, site circulation, and parking requirements for the building was completed.

 

·                    Arrangements were also made to obtain the required soil information and a site survey.

 

·                    The sanitary sewer, storm sewer and the watermain were designed.

 

·                    The hydro service was designed in conjunction with other site hydro improvements.

 

The site plan design was completed and approved by the BSC. The Site Plan Application was presented to the Development Services Committee (DSC) on April 8, 2003.

 

4.                  The Site Plan was presented to the Development Services Committee.

 

·                    SRA presented the proposed site plan to the Development Services Committee (DSC) on April 8, 2003.

 

·                    At the April 8, 2003 meeting, the DSC requested the exterior design of the building be enhanced with additional heritage features to improve the compatibility of the building with the Museum and other structures along Markham Main Street.

 

·                    The revised design was presented to DSC on the May 8, 2003.

 

The revised design included the following enhancements:

·                    Dormer

·                    Upgraded heritage style asphalt shingles

·                    Heritage style windows

·                    Double wooden columns for the porch

·                    Prefinished wood exterior trim instead of aluminium

 

5.                  Over the summer of 2003 the design development and working drawings were finalized. An application for a building permit was submitted on September 5, 2003.

 

6.                  The finalized drawings and specifications were provided to Ballantry for pricing in early September 2003.

 

During negotiations with Ballantry regarding the cost of facility, it was evident that Ballantry was not equipped to construct the MRC for a competitive cost.  Given the public use requirements of the MRC building, it had to be designed to meet all the requirements of a quality public assembly building including accessibility features, mechanical, electrical and plumbing upgrades, and commercial grade windows and doors.  Ballantry’s suppliers and sub-trades were not experienced in this type of construction and were not able to provide competitive pricing for the facility.

 

On this basis, Ballantry offered to contribute $250,000 in cash instead of providing the $250,000 of in-kind services towards the construction of the building. A copy of a letter of understanding documenting this offer is included as Appendix “A” of this report.

 

It is recommended that Council accept this offer and approve proceeding with the construction of the Museum Reception Centre building.

 

FINANCIAL CONSIDERATIONS:

The cost consultant’s estimate for the construction of the building was $600,000. This amount includes providing a public assembly building and the DSC required enhancements to the building.

 

It should be noted that the final construction cost will be determined through the competitive tendering process.

There was no Town funding provided for the construction of the MRC building in the 2003 Capital Budget. However, there are some funds available from previous capital budget projects that are not proceeding in the near future as follows:

 

·                    The 2002 Capital Budget included an allowance for $85,600 for the roof replacement for the Ward Building. In May 2003, Council approved spending $50,000 to conduct a study of the overall condition of the Ward Building. Therefore, there is $85,600 - $50,000 = $35,600 remaining in this account. 

 

·                    The 2003 Museum Capital Budget also provided $115,000 for the Ward Building roof repair

 

These roof repair projects have been deferred pending the recommendations of the building assessment report. Therefore, the above funds can be reallocated to pay for the MRC building. The repairs required for the Ward Building recommended by the building assessment report   will be included in the future capital budgets for Council’s consideration.

 

Based on Council accepting the Ballantry contribution, the funds required to construct the facility would be:

 

Cost estimate for the building construction                                 $600,000

Ballantry Cash Contribution                                                      $250,000

Balance to be funded by the Town                                            $350,000

 

Less Funds reallocated from the following accounts:

 

Roof Maintenance Account 056-5350-4702-005                     $ 35,600

Ward Bldg Roof Repair Account 073-6150-5004-005 $115,000

Total Amount Available to be reallocated                                  $150,600

 

Balance of Funding to be included in the 2004 Capital Budget  $199,400.

 

This amount has been included in the Museum’s 2004 Capital Budget submission.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Staff from Markham Museum, Community Services and Financial Services have reviewed and concur with the contents of this report.

 

ATTACHMENTS:

Appendix “A” – Ballantry Letter of Understanding regarding $250,000 Cash Contribution to the   Museum Reception Centre building

 

 

 

 

Barb Roth,

Director of Recreation and Culture Services

 

 

Stan Bertoia,

General Manager of Construction and Utilities

 

 

 

 

Peter Loukes,

Director of Operations and Asset Management

 

 

Jim Sales,

Commissioner of Community and Fire Services

Q:\Recreation\REPORTS\Museum Reception Centre.doc