In regard to the 10 specific points raised at the meeting of the Finance and Administrative Committee on March 22, using Option #4:

 

1.                  Enhancement of Hwy. # 7 and Markham Road/ Main Street

                        Moving the structure north fufills the enhancements of the Markham Village Gateway. 

 

2.                  Integration of the two facilities

            Option 4 fully provides for the possible future integration of the Library with the Arena, and permits a phased approach.

 

3.                  Cost of new parkette in front of the building

The cost of upgrading the parkette will be between $150,000 and $300,000.  The timing of the work is not necessarily related to the Library expansion, except for $75,000 related to Library entrances, and exits and approach paths, and included in the costs.  The maximum cost of providing a shade garden between the Library and the Arena will be $150,000. 

 

Part of the Terms of Reference for the Library expansion include the production of a Master Plan for the site, and further issues in regard to the parkette will be incorporated in this.

 

4.                  Possible deterioration of the south wall, and costs involved

      This is covered in the Library renovations budget.

 

5.                  Funding sources/options for financing. (DCs, reserve, other); impact on community

Addressed in Financial Considerations of Report.

 

6.                  Building to the north and all costs involved

      Addressed in Financial Considerations of Report.

 

7.                  Atrium in front of building

An atrium effect will be provided on the west side of the extension,  through the use of glass to bring transparency.

 

8.                  Feasibility of a multi-stage project

 

                                                                                    APPENDIX “A” (continued)

 

This Option maximizes the possibilities for a multi-stage project comprised of separate freestanding projects.

 

9.                  Impact on green space

The extension increases the prominence and attractiveness of the corner.  The Library has a far stronger presence.  This option also protects the heavily used park areas to the south and west.

 

10.              Options for financing, including: commercial/partnership options available

More options will become available in the future, should the Arena become linked to the Library and available for other community purposes.

 

 

 

 

 


APPENDIX “B”

 

Annual Expenses of Current Lease

 

 

 

Annual Items

Administration Centre Lease Costs in 2004$ (Incl. Taxes)

Estimated Ongoing Costs of Shared Facility with Markham Village Library in 2004$ (Incl. Taxes)

Potential Savings in 2004$ (Incl. Taxes)

Total Lease Cost

$256,631

$25,450

$231,181

Auxiliary maintenance (incl. taxes)

$8,647

$4,407

$4,240

Courier/delivery (incl. taxes)

$1,980

$0

$1,980

Telephone--data and voice (incl. taxes)

$24,359

$24,359

$0

Security (incl. taxes)

$2,544

$2,544

$0

TOTAL COST IN 2004$

$294,161.00

$56,760.00

$237,401.00

 

 

 


                                                                                                                    APPENDIX “C”

 

Estimated One-time Expenses Associated with Relocating the AC to the Markham Village Library

 

 

One-time Items

 

 

Estimated Costs

In 2004 $

(Including Taxes)

 

Moving of F & E, configuration of IT network, staff travel, overtime, and contingencies

$80,000

Construction of new public meeting rooms to replace public meeting rooms in existing basement (5,250 sq. ft.)

$1,507,397

Total Cost In 2004 $

$1,587,397.00

 

 

 


 

 

 

 

 

 

 

 

 

 

Appendix D

Town of Markham

Markham Village Library Expansion and Renovation

Project Cost Estimate

 

 

 

 

 

 

 

 

 

 

 

 

Total Project
Cost Est.

 

New Construction
10,500 sq. ft

 

Replacement
5,250, sq ft

 

Renovation
19,560 sq ft

 

 

 

Total Cost

$/sq ft

 

Total Cost

$/sq ft

 

Total Cost

$/sq ft

 

 

 

 

 

 

 

 

 

 

 

Construction

6,492,084

 

3,095,850

294.84

 

1,294,309

246.54

 

2,101,925

107.46

Internal Costs

867,115

 

475,952

45.33

 

293,088

55.83

 

98,075

5.01

Construction Total

$7,359,199

 

$3,571,802

$340.17

 

$1,587,397

$302.36

 

$2,200,000

$112.47

 

 

 

 

 

 

 

 

 

 

 

FF& E / IT

741,405

 

741,405

70.61

 

 

 

 

 

 

Collections

1,144,600

 

1,144,600

109.01

 

 

 

 

 

 

Project Total

$9,245,204

 

$5,457,807

$519.79

 

$1,587,397

$302.36

 

$2,200,000

$112.47

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 