APPENDIX “A”
Response
to Issues Raised at the Finance and Administrative Committee
March
22, 2004 Meeting
In regard to the 10 specific points raised at the meeting of the Finance and Administrative Committee on March 22, using Option #4:
1. Enhancement of Hwy. # 7 and Markham Road/ Main Street
Moving the structure north fufills the enhancements of the Markham Village Gateway.
2. Integration of the two facilities
Option 4 fully provides for the possible future integration of the Library with the Arena, and permits a phased approach.
3. Cost of new parkette in front of the building
The cost of upgrading the parkette will be between $150,000 and $300,000. The timing of the work is not necessarily related to the Library expansion, except for $75,000 related to Library entrances, and exits and approach paths, and included in the costs. The maximum cost of providing a shade garden between the Library and the Arena will be $150,000.
Part of the Terms of Reference for the Library expansion include the production of a Master Plan for the site, and further issues in regard to the parkette will be incorporated in this.
4. Possible deterioration of the south wall, and costs involved
This is covered in the Library renovations budget.
5. Funding sources/options for financing. (DCs, reserve, other); impact on community
Addressed in Financial Considerations of Report.
6. Building to the north and all costs involved
Addressed in Financial Considerations of Report.
7. Atrium in front of building
An atrium effect will be provided on the west side of the extension, through the use of glass to bring transparency.
8. Feasibility of a multi-stage project
APPENDIX “A” (continued)
This Option maximizes the possibilities for a multi-stage project comprised of separate freestanding projects.
9. Impact on green space
The extension increases the prominence and attractiveness of the corner. The Library has a far stronger presence. This option also protects the heavily used park areas to the south and west.
10. Options for financing, including: commercial/partnership options available
More options will become available in the future, should the Arena become linked to the Library and available for other community purposes.
APPENDIX
“B”
Annual Expenses of Current Lease
Annual
Items
|
Administration Centre Lease Costs in 2004$ (Incl.
Taxes) |
Estimated Ongoing Costs of Shared Facility with
Markham Village Library in 2004$ (Incl. Taxes) |
Potential Savings in 2004$ (Incl. Taxes) |
Total Lease Cost
|
$256,631 |
$25,450 |
$231,181 |
Auxiliary
maintenance (incl. taxes) |
$8,647 |
$4,407 |
$4,240 |
Courier/delivery
(incl. taxes) |
$1,980 |
$0 |
$1,980 |
Telephone--data
and voice (incl. taxes) |
$24,359 |
$24,359 |
$0 |
Security
(incl. taxes) |
$2,544 |
$2,544 |
$0 |
TOTAL
COST IN 2004$ |
$294,161.00 |
$56,760.00 |
$237,401.00 |
APPENDIX “C”
Estimated One-time
Expenses Associated with Relocating the AC to the Markham Village Library
One-time Items |
Estimated Costs In 2004 $ (Including Taxes) |
Moving of F & E, configuration of IT network, staff travel, overtime, and contingencies |
$80,000 |
Construction of new public meeting rooms to replace public meeting rooms in existing basement (5,250 sq. ft.) |
$1,507,397 |
Total Cost In 2004
$ |
$1,587,397.00 |
|
|
|
|
|
|
|
|
|
|
|
Appendix D |
||||||||||||
Town
of Markham |
|||||||||||||||||||||
Markham
Village Library Expansion and Renovation |
|||||||||||||||||||||
Project
Cost Estimate |
|||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||||||||
|
Total Project |
|
New Construction |
|
Replacement |
|
Renovation |
||||||||||||||
|
|
|
Total Cost |
$/sq ft |
|
Total Cost |
$/sq ft |
|
Total Cost |
$/sq ft |
|||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||||||||
Construction |
6,492,084
|
|
3,095,850
|
294.84 |
|
1,294,309
|
246.54 |
|
2,101,925
|
107.46 |
|||||||||||
Internal Costs |
867,115
|
|
475,952
|
45.33 |
|
293,088
|
55.83 |
|
98,075
|
5.01 |
|||||||||||
Construction
Total |
$7,359,199 |
|
$3,571,802 |
$340.17 |
|
$1,587,397 |
$302.36 |
|
$2,200,000 |
$112.47 |
|||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||||||||
FF& E / IT |
741,405
|
|
741,405
|
70.61 |
|
|
|
|
|
|
|||||||||||
Collections |
1,144,600
|
|
1,144,600
|
109.01 |
|
|
|
|
|
|
|||||||||||
Project Total |
$9,245,204 |
|
$5,457,807 |
$519.79 |
|
$1,587,397 |
$302.36 |
|
$2,200,000 |
$112.47 |
|||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||
I:\SENIOR\MV Expansion\Rpt to