RECOMMENDATION:
That the Engineering Department be authorized
to be part of a multi-agency monitoring study of a
Stormwater Management Facility in the Greensborough Community.
And that
PURPOSE:
To seek Council’s
authorization to be part of a multi-agency study to review the effectiveness of
an existing Stormwater Management Facility.
EXECUTIVE SUMMARY:
BACKGROUND:
The TRCA is coordinating a review with other
environmental agencies of the effectiveness of stormwater management facilities
in protecting the downstream watercourses.
The Stormwater Management Facility in the Greensborough Community has
been selected as an ideal test case given the upstream development and
sensitivity of the downstream watercourse (Little Rouge Creek).
Work
Plan
A detailed work plan has been prepared by the
TRCA and is attached. This work plan
outlines the scope of work, budget, funding partnerships and deliverables.
FINANCIAL CONSIDERATIONS:
Funding is available in the Engineering
Department 2003 Capital Budget (account number 083-5350-4726-005) to finance
ENVIRONMENTAL CONSIDERATIONS:
The results of this study will be utilized by
environmental agencies and municipalities in determining the effectiveness of
our Stormwater Management Facilities and if subsequent revisions to our
standards are required.
ATTACHMENTS:
Attachment A – TRCA’s Work Plan
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |