|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan Brown,
Director of Engineering |
|
|
|
|
PREPARED BY: |
same as above |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
Pomona Mills Creek ( |
|
|
|
RECOMMENDATION:
That the Engineering Department report entitled
“Pomona Mills Creek (Don River) Implementation Plan” be received;
And that the Terms of Reference for a Task
Force for the Pomona Mills Creek (
And that the Director of Engineering be
authorized to retain a consulting engineer to assist in the project management
of the proposed implementation plan to an upset limit of $25,000;
And that such costs be funded from Account #
083 5350 4726 005
And that staff report back to Committee with
updates as the work of the Task Force progresses.
And that the TRCA and Don Watershed Council be
advised accordingly.
PURPOSE:
The purpose of this report is to provide an
inventory of issues and priorities in the immediate vicinity of the Pomona
Creek within the Town of
BACKGROUND:
The Don watershed within the Town of
Pomona Creek is a tributary of the
The Don Watershed Planning document “Forty
Steps to a New Don, 1994” identified the Don River as one of the most degraded
urban rivers in the GTA and recommended a number of strategies to revitalize
and regenerate the Don watershed. The
future Don is envisioned as a revitalized urban river, flowing with
life-sustaining water through regenerated natural habitats and human
communities¹. The document emphasizes
three general principles:
As a partner to the Don Watershed Council, the
Town is committed to protect and regenerate Pomona Creek within the
APPROACH
A number of important environmental
issues that are in need of short and long term attention are identified through
examination of prior studies, TRCA’s priorities, local community complaints and
preliminary field assessment. They
include:
These issues with Pomona Creek can
be grouped into three categories:
typical issues of the Don watershed, local watershed issues within
Pomona Creek and future development issues.
Some of the issues such as fish barrier mitigation, stream bank erosion
and water quality, are typical problems of the
In order to address all these
environmental issues and verify the issues and priorities, a detailed
Management Plan will be required. The Plan should adopt an integrated approach
which includes the involvement of the TRCA, stakeholders, community interest
group, staff and Council. The plan
should provide management guidelines to improve water quality in the Don,
environmental amenity and ecological integrity commensurate with the overall Don
Watershed Regeneration Plan. Prior to
the development of the management plan, some of the issues need to be further
investigated to ensure the watershed’s long-term health and sustainability.
The implementation of the
management plan will commence following approval by Markham Council in
consultation with any community group and/or stakeholders who express interest
in the plan, and subject to funding availability.
_______________________________
¹Executive Summary,
Forty Steps to a New Don, TRCA
The TRCA, Don Watershed Council,
MOE and community consultation will occur during the development of this plan
to ensure that all community and landowner’s values are adequately considered
in the long-term management objectives of the Don watershed within the
Town. The implementation of this
management plan and major works scheduled for the Don will occur in stages and
in accordance with priority rating and fund availability.
A conceptual structure of the
management plan is outlined in Figure 2 and illustrates the key steps and
issues.
DON RIVER ISSUES
Fish Barrier Mitigation
A number of weir structures are
located in Pomona Creek within the Town boundaries. These structures have been acting as barriers
to movement of fish and other animal and plant life of the region and also
interfere with the normal transport of stream substrate. Figure 3 illustrates a fish barrier. Barriers to fish movement have been a problem
in the
Figure 3:
Typical Fish Barrier
The Forty Steps to a New Don recommends that the fish barriers within
the Don should be replaced with fish friendly alternatives. As an example of barrier rehabilitation, the
weir structure at
Prior to the development of the
fish barrier mitigation strategy, an inventory of barriers within the Don is
required. This was recommended by TRCA
during the preliminary field assessment visit.
The inventory would include spatial and topographic survey of each
structure including relevant details, and upstream and downstream
conditions. Such an assessment would be
helpful in determining the cost and re-grading of the river during the development
of management plan.
Stream Bank Erosion Control and Retaining
wall/Culvert Rehabilitation
The preliminary field survey
identified a number of eroding bank conditions along Pomona Creek (See Figure
4). In some stretches, erosion is
significant, which poses risks to the existing culvers and the recreational
trail. As part of the update of the
Development Charges By-law (2004) an update of the background study for erosion
works was completed. It outlined areas
of the
Figure 4:
Stream Bank Erosion
Figure 5:
Retaining Wall Failure and Culvert Obstruction
Retrofit of Glynnwood Pond and Mitigation
of Storm Sewer Surcharges
The Glynnwood pond is located near
the northwest corner of
The Toronto Ladies Golf Course
(TLGC) is located south of
There may be opportunities to
divert stormwater runoff from adjacent urban areas into TLGC from the Bayview
storm sewer which otherwise outlets to the Glynnwood Pond. The runoff can be conveyed and stored within
the TLGC property as an irrigation source.
However, this alternative will require thorough analysis to assess
grading, water quality, and funding perspectives.
Implementation of Recreational Trail Link
The
Water Quality
One of the main sources of water
pollution in Pomona Creek and the Don within the Town is urban runoff. The quality of water within the Town depends
on the upstream conditions and on the quality of runoff discharged. The
preliminary visit identified potential locations for pond retrofit not
previously identified as well as the need to further assess, through an
inventory of storm sewer outlets, other locations. Furthermore, a drainage area
assessment should be undertaken to assess runoff quantity and quality from the
contributing watershed for input into the watershed regeneration plan.
Impacts from Upstream Development
The northern portions of Upper East
Don and German Mills Creek sub-watersheds are not fully developed and the
development is in progress. The impacts
of these upstream developments on the Don should be assessed for existing and
future conditions. Baseline water quality sampling and baseline flow monitoring
can be considered and prioritized to assess future changes caused by
development upstream.
PRELIMINARY PRIORITIZATION OF ISSUES
The following table has been
prepared as a preliminary prioritization of issues that will be included in the
Town of
Table
1: Prioritization of Issues
ISSUES and Objectives |
Tasks |
PRELIMINARY
PRIORITY |
· Inventory of fish barriers · Conduct survey of barriers · Develop suitable fish friendly alternatives to barriers · Replace barriers and implement best alternative |
High |
|
Stream Bank Erosion Control |
· Conduct survey to define stretches that need erosion control · Develop alternative erosion control measures · Stabilize retaining wall that need attention · Rehabilitate culverts |
High |
Cleaning Glynnwood Pond and Mitigation of Sewer Surcharge at Glynnwood site |
· Removal of accumulated sediments · Replace gabion retaining wall at the forebay · Stabilize eroded banks · Investigate contributing drainage areas · Installation of inlet control devices in storm sewer serviced areas ·
Stabilization of outlet channel between pond
and |
High |
|
· Assess demand · Develop water source alternatives · Plan recreational link within the golf course |
High |
Implementation of Recreational Trail Link |
· Assess implementation of recreational trail · Land owners assessment · Assess alternative routes |
Moderate |
· Create inventory of the storm sewer outlets · Assess potential pond retrofit locations · Evaluate stormwater management within the watershed · Evaluate downspout disconnection · Monitor water quality · Analyze runoff quality and quality |
Moderate |
|
Impact of Upstream Developments |
· Assess upstream development conditions ·
Monitor base condition of river at the
boundary of |
Moderate |
NEXT STEPS
As the above issues relate to
Development Services and Community Services Commissions, external agencies
(TRCA, MNR), property owners (Ladies Golf Club,
Terms of Reference for the task
force and suggestions for its membership are enclosed as Attachment ‘A’.
FINANCIAL CONSIDERATIONS:
Subject to the recommendations of the task
force funding requirements, possible funding sources and partners will be
identified in subsequent reports to Council.
In order to undertake the implementation plan, staff will require
assistance from consulting engineers.
Staff recommends that a consultant be retained at an upset limit of
$25,000 to be funded from the Engineering Department Capital Account 083 5350
4726 005.
Subsequent reports will be submitted to
Committee and Council outlining additional funding requirements for the
implementation plan.
ATTACHMENTS:
Attachment A – Terms of Reference
Q:\Development\Engineering\REPORTS\2004\September\Don
River Implementation Plan 090904 #2.doc
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |