RECOMMENDATION:
THAT the staff report entitled 14th Avenue Sidewalk 2004 Capital Budget Allocation dated June 21, 2004,
be received;
AND THAT a sidewalk on 14th Avenue, between Boxwood
Crescent (east intersection)
and Legacy Drive not be constructed in 2004;
AND THAT the Engineering Department
report back this Fall with a 10-year sidewalk
implementation plan for the Town of Markham;
AND THAT the $140,000 allocation in
the 2004 Capital Budget be assigned to the highest
priority location as determined by the implementation plan for sidewalk construction
to be considered in Fall 2004.
PURPOSE:
To
report on the need for a sidewalk on 14th Avenue, from Boxwood
Crescent (east intersection)
to 9th Line to accommodate pedestrian traffic, in response to the
Council initiated 2004 budget allocation for this project.
EXECUTIVE SUMMARY
Councils
funding for the extension of a sidewalk on 14th Avenue was on the basis of a signalized pedestrian crossing on 14th Avenue west of Legacy Drive and a sidewalk on the south side of 14th Avenue. Based on pedestrian counts and
discussions with the Region of York a signalized pedestrian crossing will not
be approved. In order to safely permit
pedestrians to cross 14th
Avenue the sidewalk would
have to be extended to 9th Line at considerable cost to install
retaining walls. Staff
recommend the funds approved by Council be utilized for other sidewalk
projects which have greater pedestrian volumes and staff pursue with the Region
advancing improvements to 14th
Avenue west of
9th Line to accommodate sidewalk and future road widening.
BACKGROUND:
14th Avenue, between Boxwood
Crescent (east intersection)
and 9th Line, is a two-lane Regional arterial road of rural
characteristics (gravel shoulders, ditches, no sidewalk). Existing sidewalks and footpaths located in
this area are shown in Attachment 1, and include a footpath on the north side
of 14th Avenue
west of the Rouge River and
a section of sidewalk on the south side of the existing bridge crossing of the Rouge River. The existing pedestrian system is
discontinuous and requires improvement. This is intended to occur as 14th Avenue is widened and urbanized by the Region of York.
The Region has not included this
portion of 14th
Avenue in their
10-year Capital Roads Program and therefore there are no scheduled plans for
any road or bridge improvements. Because of the pedestrian safety concerns on 14th Avenue, Town Council has earmarked $140,000 in the 2004
Capital Budget for the installation of a sidewalk.
DISCUSSION:
2004 Capital Budget Discussion
In the course of the recent Budget discussions, members of Council
raised safety concerns for pedestrians along 14th Avenue at the Rouge River. Town Staff
were asked to provide a verbal cost estimate to install a sidewalk along this
section of 14th
Avenue and a
$140,000 estimate was provided on the basis of a sidewalk on the south side of 14th Avenue from Boxwood Cr. (East intersection) and Legacy Drive and a pedestrian signal at the intersection of Legacy Drive. This amount
was allocated in the approved 2004 Capital Budget. Staff indicated that they would report back
to Council with a review of options including an assessment of actual
pedestrian counts along this section of roadway.
Pedestrian Count
In response to the concern about
pedestrian safety, staff recorded the number of pedestrians walking along the
north and south sides of the 14th Avenue at the Rouge River between Boxwood Crescent (east intersection) and Legacy Drive. This study
was conducted on May 11, 2004 during the peak morning, lunch and afternoon school times. The south side of 14th Avenue does not have any pedestrian facilities, with the
exception of a short section across the bridge, while the north side has an
existing footpath through the valley lands.
Results of the pedestrian study showed that there were no children
observed walking to school via 14th Avenue or the adjacent footpath. In addition, only three adults were observed
walking along the footpath on the north side of 14th Avenue during the same time periods.
The lack of children walking along 14th Avenue to and from school between the Legacy and Boxwood
communities can be attributed to two key factors. First, the distance between the two
communities is such that walking is not convenient. Second, the school bus service transports the
children as per the school board bus policy.
Both Boxwood Public School and Sir Richard W. Scott Catholic Elementary School provide school bus service to the Legacy community, as they are outside
the minimum walking distances to the Legacy community. A public school is proposed for the Legacy
community and is tentatively scheduled to be open in 2006. This will likely accommodate most of the
children from the Legacy community that are currently being bused
to Boxwood Public School. Students attending Sir Richard W. Scott Catholic Elementary School will continue to be bused.
Design Challenges for a sidewalk
There are significant physical
challenges to provide a sidewalk between Boxwood Crescent (east intersection) and Legacy Drive. The following
two options outline several factors that would need to be addressed to build a
sidewalk in this area:
Option 1
Sidewalk on north side of 14th Avenue
Constructing a sidewalk on the
north side of 14th Avenue involves linking the existing footpath west of the Rouge River to Legacy Drive. The river, valley and limited
property on the north side results in a number of challenges as noted below
which do not make it feasible to build a sidewalk on the north side at this
time:
- A separate pedestrian bridge to cross the Rouge River
is needed.
- Significant grading of the slopes of the Rouge River
valley
- Property acquisition on the golf course (Town owned) and Church
lands
Option 2
South side of 14th Avenue
Constructing a sidewalk on the
south side of 14th Avenue is feasible to a point just east of the bridge. Beyond this location, the property to the
south rises significantly and introduces the following issues:
- A pedestrian crossing would be necessary on 14th Avenue near Legacy Drive. However, the Region does not support a
pedestrian crossing since minimum pedestrian volumes to meet the warrants
are not satisfied. Furthermore, a
pedestrian crossing at this location without a pedestrian crossing is not recommended
given the sightlines, vehicular speeds and road curvature of 14th Avenue.
- Grading the slopes of the Rouge River
valley
- Property acquisition of adjacent properties
- Tree removal/impact
- In order to extend the sidewalk east of Legacy Drive
it would entail a retaining wall at significant cost along the south limit
of the right-of-way
10 Year Sidewalk Program
As part of the development charges
study update to be presented to Council in July 2004, staff
have prepared a detailed list of outstanding sidewalks on arterial roads
and in new development. There is ± $15
million of sidewalk installation to be undertaken over the next 20 years.
Staff will submit a 10 year Capital
Program to Transportation Committee this Fall so the
projects can be prioritized. Staff recommends the $140,000 funds allocated by Council for
14th
Avenue sidewalk
be allocated to the highest ranked projects for implementation this Fall.
CONCLUSION:
There are very low pedestrian
demands that do not justify a need for a sidewalk between Boxwood Crescent (east intersection) and Legacy Drive at this time.
There are substantial physical challenges to cross the valley and the Rouge River. Given these
issues, it is recommended that the $140,000 funding allocated by Council for
this project be added to the overall sidewalk programme and be used for other
locations as recommended by staff in the Fall.
ATTACHMENTS:
Attachment
1 Sidewalk Feasibility Location Map
Attachment
2 14th Avenue Footpath Looking West From Rouge River
Attachment
3 14th Avenue Footpath at the Rouge River
Looking East
Attachment
4 14th Avenue Bridge Over the Rouge River
Looking East
Attachment
5 14th Avenue Bridge Over the Rouge River
Eastbound
Attachment
6 14th Avenue Bridge Over the Rouge River
Westbound
Attachment
7 14th Avenue
East of the Rouge River
Looking East
Attachment
8 South Side of 14th
Avenue East of
the Rouge River Looking East
Attachment
9 14th Avenue at Legacy Drive Looking East
Attachment
10 14th
Avenue at Legacy Drive
Looking West
Attachment
11 South Side of 14th
Avenue Eastbound
Approaching 9th Line
Attachment
12 North Side of 14th
Avenue Eastbound
Approaching 9th Line
|
|
|
Alan Brown, C.E.T.
Director of Engineering
|
|
Jim Baird, M.C.I.P., R.P.P.
Commissioner of Development Services
|