|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan
Brown, Director of Engineering |
|
|
|
|
PREPARED BY: |
Alan Brown, Director of Engineering Allan Arbuckle, Manage of
Infrastructure and Capital Works |
|
|
|
|
DATE OF MEETING: |
April 4, 2005 |
|
|
|
|
SUBJECT: |
Tender Award - Contract 018-T-05 Construction of Cachet
Estates/Glenbourne Park Water Distribution System |
|
|
|
RECOMMENDATION:
THAT Contract Tender No. 018-T-05
for the Construction of Water Distribution System for Cachet Estates and
Glenbourne Park Subdivision be awarded to the low bidder, Memme
Excavating Co. Ltd. in their proposed amount of $6,156,025.92
excluding GST;
AND THAT the Mayor and Clerk be
authorized to execute a contract with Memme
Excavating Co. Ltd. for the construction of the
Cachet Estates and Glenbourne Park Subdivision water distribution systems.
AND THAT a contingency amount of $430,922 exclusive of GST be established to cover any additional construction costs
and that the Director of
AND THAT staff be authorized to undertake appropriate
measures as defined in the report to limit the overall project cost to a
maximum value of $6,666,000 exclusive of GST.
AND THAT staff be authorized to obtain 3
proposals from qualified consulting engineering firms and select a firm in
accordance with the Town’s purchasing bylaw to provide geotechnical, materials
and hydrogeological testing services during construction in the upset limit
amount of $65,000 exclusive of GST.
AND THAT the design budget for the project
be increased by a total of $14,600 to cover the cost of services not included
in the design consultant’s original terms of reference including the
preparation of designs for the servicing to the Cachet Estates lots fronting
onto Woodbine Avenue, peer review and water system modelling services prepared
for the project.
AND THAT a contingency of $ 50,000 excluding GST be established to
retain a qualified consulting firm or firms as a preferred
supplier to provide specialized technical services during construction of the
project and that
the Director of
AND THAT the consulting engineering firm of Masongsong
Associates
AND THAT subject
to receipt of the Region of York’s financial contribution and the property
owner’s signed release, the Town Treasurer be authorized to issue payment to
the registered owner of the lot in an amount equal to the Region’s contribution
of approximately $5,790 per lot.
AND THAT funds
for Contract No. 018-T-05, Construction of Water Distribution System for Cachet
Estates and Glenbourne Park Subdivision be provided from
the
AND THAT funds be borrowed to
finance this project from the Life Cycle Replacement and Capital Reserve Fund,
to be fully repaid with interest from the benefiting property owners assessed
under Section 391 of the Municipal Act.
AND THAT upon payment of all
invoices, any remaining funds in the
AND THAT upon completion of the project, staff report back
to Council with the Fee Bylaw under Section 391 of the Municipal Act to assess
the final cost and repayment terms to each of the benefiting property owners.
AND THAT the Director of
AND THAT staff be authorized to issue a purchase order to
Masongsong Associates Limited in the upset limit of $10,000 to prepare sanitary
servicing concepts and costs for
AND THAT Kees Schipper, Commissioner, Transportation and
Works, for the Region of York be advised accordingly
PURPOSE:
The purpose of this report is to award the
contract for the construction of the water
distribution system for Cachet Estates and
BACKGROUND:
Well Impacts
The Region of York is undertaking an extensive dewatering program as a
part of the construction of Phase II of the
In June of 2003 Council authorized staff to
retain a consultant to undertake preliminary designs and cost estimates for the
construction of a municipal water system to service the area and in May of
2004, staff were authorized to proceed with the detailed design of the system
based on the support of residents for a construction of a municipal system
funded by all benefiting property owners in the area at a cost of $129,500. Specialized engineering services related to
geotechnical were also retained at a cost of $14,600 which brings the design
fee to $144,100. The detailed designs for the project have been completed and
tenders for the construction of the system have now been received.
Section
391 – Municipal Act
The construction of the watermain is to proceed under the provisions of
Section 391 of the Municipal Act which allows a Municipality to
impose a fee on property owners benefiting from the construction of a municipal
service such as a watermain. This fee
will be assessed on an equal basis per property and will include the total
project costs including construction costs, consultant fees, engineering fees
and permit costs. The preliminary cost for the construction of the water distribution
system was approximately $6.0 million resulting in a cost attributable to each
benefiting property owner of approximately $20,000 for the 303 lots in this
area. This estimated cost was provided to area residents in May of 2004 and was
supported by approximately 67% of the surveyed property owners. The residents were also advised that if the
project costs were more than 10% above the estimate ($22,000) than the
residents would be resurveyed for support of the increased cost.
Staff will report back upon completion of the project to finalize the
project cost, confirm payment terms (i.e. 10 year term with interest or lump
sum) and obtain Council’s approval of the fee by-law.
Region of
The Region has committed a total of $1,650,000 as a part of the
The Regional contribution of ±$5,790 per lot will be finalized and forwarded
from the Region directly to the Town together with the signed release document.
Upon receipt of this payment and documentation, the Town Treasurer will issue
payment to the property owner.
Resident
meetings
Meetings with area residents were held on
DISCUSSION:
The tender for the construction of the Cachet
Estates/Glenbourne Park water distribution system was issued in accordance with
Purchasing By-law #2004-341. Contractors
interested in constructing the project were prequalified and tenders were
issued to 5 prequalified contractors on
Contractor |
Inclusive of GST and of disbursements |
Mardave Construction Ltd |
$7,597,000.00 |
Comer Group Ltd 50 Fernstaff
Crt., Unit 8 |
$6,943,205.33 |
Kapp Contracting Inc. |
$6,596,770.42 |
Memme Construction |
$6,586,547.73 |
Clearway Construction Inc. |
$7,481,614.98 |
The bids were verified for accuracy and
compliance with the tender terms and conditions.
CONSULTANT SERVICES:
Construction Supervision and Contract Administration Services
In June 2003, proposals were submitted by 4 consulting firms for the
design and contract administration of this project. Of the four submissions, Masongsong
Associates
There are a number of areas within the project
where high ground water levels and poor soil conditions are expected to pose
significant technical challenges during the installation of the watermain.
Trenchless techniques will also be employed for the watermain installation in
some lo
For quality control purposes, a specialized
firm to provide geotechnical, materials and
hydrogeological must be retained for testing services during construction.
Staff will be soliciting proposals for this work from three qualified firms in
accordance with the purchasing bylaw and have included an allowance of $65,000
exclusive of GST to cover the cost of these services.
FINANCIAL CONSIDERATIONS:
Staff recommends that the tender for the Construction of
Water Distribution System for Cachet Estates and Glenbourne Park Subdivision be awarded to the lowest bidder, Memme
Excavating Co. Ltd. in the amount of $6,156,025.92 exclusive of 7%
GST. The total cost of constructing the project is as follows;
Item |
Cost excl. GST |
Construction Cost |
$6,156,025.92 |
Construction Contingency (7%) |
$
430,922 |
|
$
144,100 |
Contract Administration |
$ 138,510.58 |
Geotechnical, materials & hydrogeological testing allowance |
$ 65,000 |
Specialized technical services
allowance |
$ 50,000 |
|
$ 153,900.65 |
Total Project Cost |
$7,138,459.15 |
Funding for the project will be
provided by the benefiting property owners in accordance with Section 391 of
the Municipal Act. The total cost of the project will be shared equally among
the existing 290 property owners, and future 13 lots by Angus Glen on Cachet (303
total). In the interim funds to finance
this project will be borrowed from the Life Cycle Replacement and Capital
Reserve Fund. Following completion of
construction, a fee by-law authorized by Section 391 of the Municipal Act will
be prepared and repayment from the benefiting property owners (303 lots) will
commence.
Based on the current estimated total project cost,
the cost per lot to each benefiting homeowner is approximately $23,559
excluding GST or approximately $3,559 more than the original estimated cost per
lot provided to the property owners and $1559 more than the upset limit
committed to under the original survey.
Although Section 391 of the Municipal Act does not
require resident approval for the increased assessment, as previously mentioned
the Town of
As there is sufficient opportunity to realize the
$472,458.85 cost savings, staff therefore recommend the overall project cost be
limited to $6,666,000 and staff be authorized to reduce costs from any or all
of the above options.
CONSTRUCTION SCHEDULE
The current schedule for the
project, to be finalized with the contractor, is to have this contract
completed by late 2005/early 2006.
Angus Glen Development has filed a
draft plan application for their
In order to finalize this option
Engineering staff have to first review the overall sanitary servicing for the Glenbourne area and finalize the size and depth of the
Angus Glen sewer needed to service the area and not just their 13 lots. Staff therefore request approval to retain
our watermain consultant on a preferred supplier basis at an upset limit of
$10,000 to prepare servicing concepts, cost estimates for the sanitary
servicing of Glenbourne area.
Staff will report back to Committee
as to the overall sanitary concept for the Cachet/Glenbourne
area, sanitary servicing options, costs for the Glenbourne area residents and recommendations as to the
Angus Glen proposal.
BUSINESS UNITS CONSULTED AND AFFECTED:
The Finance and Legal Departments have reviewed
this report and their comments have been incorporated.
ATTACHMENTS:
Attachment A – Lo
|
|
|
Alan Brown, C.E.T. Director of |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Q:\Development\Engineering\REPORTS\2005\March\
Cachet wmTender Award doc