TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan Brown, Director of
Engineering |
|
|
|
|
PREPARED BY: |
Frank Ierfino, Development
Engineer |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
|
|
|
|
RECOMMENDATION:
THAT the
Development Services Commission report titled “Berczy Village Community – Four-Party
Agreement for Stormwater Management Pond” dated
AND THAT the Mayor
and Clerk be authorized to execute an agreement with the Regional Municipality
of York, Berczy Developers Group, and B. McGregor Development Limited to the
satisfaction of the Chief Administrative Officer and the Town Solicitor.
PURPOSE:
To obtain Council
approval to enter into an agreement with the Region of York, The Berczy
Developers Group and B. McGregor Development Group to transfer outstanding obligations
for a stormwater management pond from the Berczy Developers Group and B. McGregor
Development Limited to the Region.
BACKGROUND:
McGregor
Plan of Subdivision Pond ’A’
B. McGregor
Development Limited plan of subdivision (65M-3168) as per attachment ‘A’ in the
Berczy Secondary Plan Area has been constructed including a stormwater management
pond located at
The
infrastructure and the stormwater management pond is now in a position to be
assumed by the Town as per the subdivision agreement dated
The
Region commenced discharging approximately 10 l/s of groundwater on
Agreement
In
order to transfer outstanding obligations for the Pond from Berczy Developers
Group and B. McGregor Development Ltd. to the Region of York an agreement is
required between the Berczy Developers Group, B. McGregor Development Limited, Region
of York and the Town, outlining the obligations of the four parties. These obligations include, but are not
limited to;
·
The Region agreeing to assume as of
· Berczy
Developers Group and B. McGregor Development Limited submitting sufficient payment
to the Region of their outstanding obligations to complete Pond A (silt removal,
planting etc.);
·
Transfer of indemnification for the stormwater
management pond from Berczy Developers Group/B. McGregor Development Limited to
the Region;
· Region to address any
outstanding obligations for
·
The Region to carry out any monitoring or
maintenance required by the Town in respect of Pond ‘A during the period of
dewatering;
·
Town to release B. McGregor Development
Limited from the outstanding obligations with the Pond under their October 8,
1997 agreement and release the Letter of Credit currently held by the Town for
the outstanding obligations; and
·
The Region indemnifies the Town in respect
of the dewatering and discharge operation and with respect to downstream claims
due to water quality.
It is recommended
that the Mayor and Clerk be authorized to execute an agreement with the Regional
Municipality of York, The Berczy Developers Group and B. McGregor Development
Limited to the satisfaction of the Town Solicitor and Chief Administrative
Officer. The conditions noted above will
form the basis of this agreement.
BUSINESS UNITS CONSULTED AND AFFECTED:
The Legal Services
Department has reviewed and commented on this report.
ATTACHMENTS:
Attachment A – Area
Map
|
|
|
|
|
Alan Brown,
C.E.T. Director of
Engineering |
|
Jim Baird,
M.C.I.P., R.P.P. Commissioner of
Development Services |
Q:\Development\Engineering\REPORTS\2006\Feb\Berczy
Village Community Pond 'A' Report.doc