Report to: Development Services Committee Date of Meeting:
SUBJECT: RECOMMENDATION REPORT
Box Grove Centre Inc., Box Grove Hill Developments Inc.& Box Grove North Inc. (19TM-030012) Phase 2
Proposed Plan of subdivision and implementing
zoning by-law amendments, Box Grove
PREPARED BY:
RECOMMENDATION:
That the staff
report entitled “Box Grove Centre Inc., Box Grove Hill Developments Inc. &
Box Grove North Inc. (19TM-030012) Phase 2, Proposed Plan of subdivision and
implementing zoning by-law amendments, Box Grove
That Phase 2 of draft plan of subdivision 19TM-030012 (SU. 03-115555) located east of 9th Line, north of 14th Avenue, proposed by Box Grove Hill Developments Inc. & Box Grove North Inc. & Box Grove Centre Inc., be draft approved subject to the conditions outlined in Appendix ‘A’;
THAT the
Director of
THAT
prior to issuance of draft plan approval, the Owner shall enter into an
agreement with the Town, applying to Lots 343, 359, 378, 395 and 410 of draft
plan 19TM-030012, which agreement shall be registered on title, committing the
Owner not to enter into any agreements of purchase and sale with anyone, including other developers or builders, for the
subject lots until such time as:
· the detailed design for the Markham By-pass (including the completion of the Reference Plan) has been completed; and,
·
a revised draft plan, if required, has been
approved by the Town of
That zoning application (ZA 03-115538) to amend By-law 304-87 and By-law 177-96, submitted by Box Grove Centre Inc., Box Grove Hill Developments Inc. & Box Grove North Inc. for lands east of 9th Line, north of 14th Avenue, be approved and the implementing Zoning By-Laws attached as Appendix ‘B’ be finalized and enacted;
That the
applicants agree to pay their proportionate share of the Highway 48 flow
control measures, to the satisfaction of the Director of
That servicing allocation for 527 units be granted to Box Grove Hill Developments Inc., Box Grove North Inc. and Box Grove Centre Inc. (19TM-030012) Phase 2 in accordance with the November 22, 2005 report on servicing allocation;
That the Town reserve the right to revoke or reallocate water and sewage allocation at its sole discretion;
That the Region of York be advised of the servicing allocation for this development;
That the applicants provide to the Town the 30% payment of the required subdivision processing fees in accordance with the Town’s Fee By-law (2005- 357);
And further
that the draft plan of subdivision approval shall lapse after a period of three
years commencing
EXECUTIVE SUMMARY:
The applicant has submitted
applications for draft plan of subdivision approval and zoning by-law amendment
to permit 527 residential units as well as a 0.1 ha.(0.25
ac.) parkette, a storm water management pond and approximately 17.9 ha. (44
ac.) of employment lands. A future
service station and associated retail/convenience store is proposed on the
The subject lands form part of the Box Grove
Sufficient
employment lands will be available within approved and proposed developments in
the area which, when combined with employment lands expected to be available to
the east, will satisfy the obligation in the MOU and the Secondary Plan that
42.5 ha (105 acres) of employment lands be provided within the Box Grove
Construction
of the 9th Line re-alignment is currently underway, and is expected
to be completed by the summer of 2006, subject to the right-of-way for the
The Environmental
Assessment Study for the Markham By-Pass has been completed and is awaiting Ministry
of Environment approval. A number of
matters with regard to the
There are lands in the Town’s ownership to be
transferred to the Owner upon confirmation of ultimate alignment of
A Phasing
Plan has been prepared and the Phasing Agreement between the Town and the
Developer’s Group has been executed and reflects most of the requirements of
the Memorandum of Understanding (MOU) executed in June, 2002 between the
developers, the Town and the Region. Most
of the developer’s obligations within the MOU have been completed or are being
addressed to the Town’s satisfaction. Sufficient
servicing allocation has been assigned by Council to accommodate the 527
proposed units but the issuance of building permits is to be limited to 291
units within the subject Plan, in accordance with the MOU and the Phasing
Agreement, until the Markham By-Pass link is operational.
While the proposed Draft Plan
deviates slightly from the Community
FINANCIAL CONSIDERATIONS:
Not applicable
1. Purpose 2.
Background 3. Discussion 4.
Financial
5. Others (Environmental,
Accessibility, Engage 21st, Affected Units) 6. Attachment(s)
The purpose of this report is to
recommend draft plan approval of Phase 2 of
a larger draft plan of subdivision which was partially draft approved and zoned
based primarily on the availability of servicing allocation, subject to
the conditions attached as Appendix ‘A’ and the enactment of implementing
zoning by-laws (Appendix B).
Location
and Area Context
The subject lands form part of the Box Grove
Draft plan approval was granted for Phase 1
land
In May
2004, Council granted draft plan of subdivision approval for the applicant’s
Phase 1 lands (Figure 4). That plan
included 827 residential units, employment lands, a number of natural features
(woodlot, two minor tributaries of the Little Rouge Creek, minor tributary of
Lands in Town’s ownership to be transferred to the
applicant upon confirmation of ultimate alignment of
In 2001,
the Committee of Adjustment approved the conveyance of a 16.2 ha (40 acres)
parcel of land from the Ontario Realty Corporation (ORC) to Box Grove Hill
Developments Inc. located north of
The
proposed future alignment of the
Proposed plan of subdivision (Phase 2)
The subject lands comprise the 2nd Phase
of a larger draft plan of subdivision which was partially draft approved and
zoned based primarily on the availability of servicing allocation. The subject site is intended to eventually accommodate 527 conventional
residential units as well as a 0.1 ha.(0.25 ac.) parkette, a storm water
management pond and approximately 17.9 ha. (44 ac.) of employment lands
including a future service station and associated retail/convenience
store. The residential component
consists of 383 single detached units and 144 semi-detached units (Figure 4). The proposed residential mix / lot frontages
are outlined below:
Unit Type |
Frontage |
No. of Units |
|
Metres |
Feet |
||
Single
Detached |
Min. 10.4 |
31.4 |
86 |
Single
Detached |
Min. 12.8 |
41.9 |
216 |
Single
Detached |
Min. 14.0 |
45.9 |
81 |
Semi-Detached |
Min. 7.5 |
24.6 |
144 |
TOTAL 527 |
All the
proposed semi detached units are located in the south portion of the Plan,
between the easterly tributary of the Little Rouge Creek (Trib B) and the CPR
rail line.
Applicant is a signatory to the Developers Group Agreement A
Developers Group Agreement is in place for the Box Grove Area to secure community facilities including
parkland and schools, and to compensate the landowners on whose properties the
community facilities are located. The
applicant is a signatory to the Developers Group Agreement.
Phasing Plan has been prepared and the Phasing
Agreement has been executed
In May
2004, Council endorsed the Box Grove Community Phasing Plan subject to
revisions. This Phasing Plan reflects the
requirements of the Secondary Plan and the Memorandum of Understanding (MOU) between
developers in the Box Grove area, the Town and the Region of York, dated
Acquisition of required road and parkland are expected in the near
future
The 9th Line re-alignment
is critical to the continued development of the Box Grove area. While the majority of this road has been
constructed the Region of York has indicated that it will not allow this road
to become operational until
As part of the purchase of the
right-of-way, the Town will also be acquiring a parcel of parkland of
approximately 1.1 ha. (2.8 ac.) necessary to complete the
Proposed plan of subdivision generally conforms
to Secondary Plan and Community
The lands
comprising the draft plan are primarily designated in both the Secondary Plan
and the
Community
With regard
to the proposed Plan, the Secondary Plan provides residential density
requirements only for the Urban Residential II – Low Density designation and
the proposed density of the units within this designation is shown in the table
below. In addition, since all the
residential units within the proposed subdivision are of a low density nature
the table below also shows the overall net residential density within the
subdivision:
|
Proposed Density |
Permitted Net Density Low
Density Housing II 17.0 to
37.0 units per net ha. (6.8 to
14.9 units per net acre) |
24.65 units per net hectare (9.97 units per net acre) |
Overall Net Residential Density |
27 units per net hectare (10.98 units per net acre) |
Housing type mix targets
contemplated by the Secondary Plan have been modified Appendix 1 to the Secondary Plan, which
is not an operative part of the Plan, sets housing type mix targets of 77% low density housing and 23% medium
density housing for the Secondary Plan area.
The Community
The location of 15 single
and semi-detached units within a small
Community Amenity Area II designation is considered acceptable The Secondary Plan identified a Community
Amenity Area II designation between Trib.
B and the employment collector (Figure 5).
However, in accordance with provisions of the Secondary Plan,
refinements to the design vision for the
This designation would only accommodate medium or high density developments but the applicant is proposing 12 semi-detached and three single detached units. The applicant’s goal is to be consistent with the built form in the immediate vicinity. As there is no compelling reason to have a medium density development in this particular area staff does not object to the development as proposed.
Service station site is proposed
to be relocated The Community
Realignment of employment
collector provides access to employment lands east of the proposed
An appropriate amount of
employment lands have been provided The Secondary Plan requires that 42.5 ha (105
acres) of employment lands be provided within Box Grove, of which 14.912 ha
(36.8 acres) were draft approved as part of Phase 1. The proposed plan of subdivision includes
17.87 ha. (44 ac.) of employment lands required for the Box Grove Area (Figure 4). Staff’s calculations indicate that lands
owned by others to the east can, based on reasonable assumptions for roads and
valley lands, accommodate the remainder of the required employment lands.
It should be noted that all of the employment
lands east of the Town Arterial Road have been denoted with a Regional Gateway
symbol in the Secondary Plan to reflect the fact that these lands have been
identified by the Province as a potential site for a regionally scaled
transportation gateway, intended to become a transfer point among various modes
of local, regional and interregional transit facilities. Development of the Regional Gateway is to be
integrated with, and include employment generating land uses. Employment lands in the Draft Plan in this
area will be zoned with a Hold ‘H’ provision to ensure that the development of
the lands will be carried out in a comprehensive manner with input from the
Province and other external agencies.
Most obligations of the Memorandum of
Understanding have been met
As noted
earlier, the Owner, together with other developers in the Box Grove area,
entered into a Memorandum of Understanding (MOU) with the Town and the Region
of York outlining obligations of the parties towards transportation and
servicing improvements for the Box Grove community. To date the obligations have been addressed
by the developers as follows:
The Box
Grove developers are also obligated to construct a road that could form part of
the Markham By-Pass. This is discussed
later in this report.
The EA Study for the
The Region
of York has completed the “Individual Environmental Assessment for
Transportation Improvements in the Markham By-Pass Corridor South of Highway
407” (Markham By-Pass EA). This Study includes the realignment of
While the general location of the recommended alignment of
the Markham By-Pass and the
The pre-condition to be satisfied prior
to the granting of draft plan approval involves a requirement that the
applicant enter into an agreement with the Town, to be registered on title,
which prohibits the sale of five (5) residential lots until such time as the
detailed design of the By-pass is completed and a revised Draft Plan, if
required, has been approved by the Town in consultation with the Region. The related condition of Draft Plan approval
requires that these five (5) lots be subject to a Holding provision pending the
completion of the detailed design of the By-Pass and the approval of a revised
Draft Plan if necessary. A pre-condition
of draft approval has been included as part of the staff recommendation above and conditions of Draft Plan approval
are included in Appendix ‘A’.
The
The
Secondary Plan identifies a route alignment and a 20 metre right-of-way for a
A number of matters with regard to the
A number of
matters with regard to the
Another
possibility is to obtain the necessary lands as a condition of a future
subdivision approval. In the Spring 2006
servicing allocation distribution staff is recommending that 150 units of
allocation be assigned to the Box Grove Trustee to facilitate the development
of a key parcel of land which will contain a segment of the
Further,
the Town in consultation with the Region of York and the Box Grove developers
must also determine whether to proceed as per the MOU with an interim two lane
rural road or, in order to avoid “throw-away” costs, construct the ultimate
four lane road consistent with the future Markham By-Pass. Finally, the future intersection alignment
of
Sufficient servicing allocation is available to
accommodate 527 units (Phase 2)
Sufficient
servicing allocation (1365 units) for the first Phase of development in Box
Grove, including Phase 1 of this Plan of subdivision, was granted in 2004. The Phasing Agreement between the Town and
the Developers’ Group executed in June 2005, which was based on the principles
established in the MOU, provide that servicing allocation over and above the
initial 1365 units is subject to the 9th Line re-alignment being
completed and operational by December 31, 2006 and the Town Arterial Road being
designed and constructed no later than December 31, 2007, subject to the
necessary right-of-way being available.
As noted
above, the 9th Line re-alignment is expected to be completed this
summer but the timing of completion of the
As
discussed below, build-out of the applicant’s residential lands in the area
will not be permitted until the
Building permits will be limited to 80% of the
units within the applicant’s ownership
The MOU and
the Phasing Agreement provides that no
Group member (with the exception of certain
small landholdings specified in the Phasing Agreement) shall receive
building permits for more than 80% of the total number of units within their
ownership until the Town Arterial Road (Markham By-Pass Link) is fully
constructed, including across non participating owner(s) lands, (subject to the
acquisition of such non- participating owner’s land by the Town), provided such
80% release of lands for development can be supported by transportation
analysis.
The
transportation study submitted for the Box Grove area provides that the Markham
By-Pass Link will be required to support the build out of the Phase II
lands. An update of the Transportation
Study will be required prior to the registration of the final 20% of the
applicant’s land holdings in the area.
Within the
Box Grove area the applicant owns residential lands that will accommodate,
according to currently submitted plans, approximately 1294 units. Therefore, the zoning of approximately 258 of
these units, which include about 236 units within the proposed Plan, will be
subject to a Hold ‘H’ provision which will not allow building permits to be
issued until the Markham By-Pass Link is completed.
Certain site specific technical studies remain
to be completed
The Owner
will be required to provide an updated Traffic Impact Study and Internal
Functional Traffic
Public Meeting was held to consider subdivision
and zoning amendment applications
On
concerns
raised with respect to the subject lands (Phase 2) and how each issue has been
addressed:
9th
Line will be accessible during construction
One
resident expressed a concern that access might be restricted on 9th
Line during construction. Construction
vehicles will be required to access the subject lands primarily from
Acceptable
location for proposed gas bar
The lands
at the northwest corner of the proposed employment collector road and proposed
Additional concern was raised by area resident
following Public Meeting
Following
the public meeting, an additional letter was received by an area resident
expressing concerns with the potential location of the Markham By-Pass.
The Owner
of 7960 Reesor Road expressed concern with the location of the proposed
The
previously proposed alignment of the
However, as
noted above, the final proposed alignment of the By-pass Link was adjusted to
reduce the impact on
Proposed zoning by-law amendments
In accordance with the Secondary Plan requirements, the applicants have applied for zoning by-law amendments to implement the proposed draft plans of subdivision. The subject lands are currently zoned Agricultural One (A1) and Institutional (INST) under the Town’s rural area By-law 304-87 (Figure 2). It should be noted that in 1983, the majority of the northwest portion of the lands owned by the applicant were zoned Institutional (INST) under By-law 304-87 consistent with the Ministers Zoning Order, which permitted a cemetery use. Through the approval of the Box Grove Secondary Plan by the Ontario Municipal Board, the Minister’s Zoning Order was rescinded and the lands can now be rezoned to implement the proposed draft plan of subdivision.
Amendments are required to delete the lands from By-law 304-87, and to incorporate the subject lands within the Town’s Urban Expansion By-law 177-96. The proposed zoning for the plan of subdivision under By-law 177-96 will include the following:
These zone categories/exceptions will contain development standards consistent with those proposed on similar lots on other proposed plans of subdivision in the vicinity and current Town standards. Draft amending zoning by-laws for the proposed plan of subdivision are attached as Appendix ‘B’.
Conclusion
While the proposed Draft Plan deviates slightly from the
Community
FINANCIAL TEMPLATE:
Not applicable.
ENVIRONMENTAL CONSIDERATIONS:
All of the valleylands to be
dedicated and the required buffers were conveyed to the Town as part of
registration of Phase 1 of the overall Draft Plan.
ACCESSIBILITY CONSIDERATIONS:
Not applicable.
ENGAGE 21ST CONSIDERATIONS:
The Box Grove development plans
were prepared in consultation and cooperation with the existing residents in
the area which is in keeping with a goal set out in “Engage 21st
Century Markham”, namely investment in the expectations and requirements of the
different communities within the Town. Approval
of the proposed draft plan of subdivision will promote another key goal which
is Managed Growth. The Box Grove Phasing
Plan establishes a framework for the phasing and coordination of key infrastructure
relative to the timing of development.
It is intended that build out of the proposed Plan, in accordance with
the Phasing Plan, will result in key pieces of infrastructure such as the 9th
Line re-alignment and the
BUSINESS UNITS CONSULTED AND AFFECTED:
The requirements of other municipal departments and
external agencies have been incorporated into the draft plan and recommended
conditions of draft plan approval.
RECOMMENDED BY:
________________________________ ______________________________
Val Shuttleworth, M.C.I.P., R.P.P. Jim Baird, M.C.I.P., R.P.P.
Director, Planning & Urban Design Commissioner, Development Services
Q:\Development\Planning\APPL\SUBDIV\03
115555_BoxGroveHill Phase 2\Box Grove Hill
Phase 2 - Final Report.doc
Figure 1. - Location Map
Figure 2 - Area Context / Zoning
Figure 3 - Aerial Map
Figure 4 - Proposed Draft Plan of subdivision
Figure 5 - Subject property as it relates to
Community