Report to: Development Services Committee                               Date of Meeting: June 6, 2006

 

 

SUBJECT:                          Credit Agreement with – Wismer Commons Developer’s Group Inc.

 

PREPARED BY:               Frank Ierfino, ext. 7920

 

 

 

RECOMMENDATION:

That the report entitled “Credit Agreement with – Wismer Commons Developer’s Group Inc.” dated May 16, 2006, be received;

 

And that the Mayor and Clerk be authorized to execute a Development Charge Credit Agreement with Wismer Commons Developers Group Inc. in a form satisfactory to the Chief Administrator Officer and Town Solicitor pursuant to section 38 of the Development Charges Act, 1997 for the construction of public works;

 

And that the Financial Services Department be authorized to make final adjustments to the financial schedules of the Development Charge Credit Agreement to reflect development charge credits upon execution of the Credit Agreement.

 

EXECUTIVE SUMMARY:

Not applicable

 

FINANCIAL CONSIDERATIONS:

There is no net financial impact to the Town. The collected development charges for constructing the external public infrastructure will be reimbursed to the Owner, who will then be responsible for paying the full cost of the infrastructure.


1. Purpose                2. Background         3. Discussion             4. Financial         5. Environmental

 

6. Accessibility       7. Engage 21st             8. Affected Units       9. Attachment(s)

 

 


PURPOSE:


The purpose of this report is to obtain Council’s authorization to execute a Development Charges Credit Agreement with Wismer Commons Developer’s Group for the external storm sewer system infrastructure, intersection works and improvements (Works) that are required in order for the Wismer Commons Developers Group Inc. (Group) to proceed with development in their secondary plan. These Works, as shown in Figure ‘A’, have been identified and included in the Town’s Development Charge By-law (Area Specific By-Law 2004-245). The credit agreement will make provision, if need be, for the update of the financial schedules to reflect updated cost estimates and assessment to be undertaken as part of the D.C. update to be completed in the Fall of 2006.

 

The Group, as per Attachment ‘B’, has requested authorization to undertake the works subject to the Town providing development charge credits for the construction of the public works, at the subdivision agreement stage.  The extent of the said works may be revised during finalization of this Agreement with the Group.

 

 

 


 

BACKGROUND:


The Town’s Development Charge by-law identified and quantified external works required to service the Wismer Community. The external storm sewer system infrastructure, intersection works and improvements (Works), were included in the Area Specific Development Charges By-law for this area.  In order to facilitate an early completion of the Works, and meet the Group’s development schedule, the Group has proposed to up-front funding and construct these works at their own cost and receive development charge credits as may be applicable upon execution of their future subdivision agreements.

 

Subsection 38(1) of the Development Charge Act provides as follows:

 

 

“If a municipality agrees to allow a person to perform work that relates to a service to which development charge by-law relates, the municipality shall give the person a credit towards the development charge in accordance with the agreement.”

 

The Town has entered into similar agreements with other owners in OPA5 such as Minto/Legacy, Cornell, Angus Glen, Berczy etc.. The draft credit agreement (Attachment ‘C’) has been prepared for review and discussion by the Town and the Group and its financial schedules will be prepared by staff. 

 


 

OPTIONS/ DISCUSSION:


Development charges credit agreements have been used in a number of development applications. This allows the land owner to construct the necessary external infrastructure to serve their development ahead of the Town’s capital program. The Group will be required to retain a professional consulting engineer to design and supervise the construction of the above noted works in accordance with the Town’s engineering standards.  This ensures the standard of design and construction will meet the Town’s requirements.  Town  staff support this request, subject to the Group entering into a development charges credit agreement, which will include the following components:

 

 

 

 


 

FINANCIAL TEMPLATE (Separate Attachment):


 

Not applicable

 


 

ENVIRONMENTAL CONSIDERATIONS:

Not applicable

 

 

ACCESSIBILITY CONSIDERATIONS:

Not applicable

 

 

ENGAGE 21ST CONSIDERATIONS:

Not applicable

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Financial Services Department will have to track and administer credits and reimbursement payments in accordance with the Credit Agreement.  The Legal Services Department will draft the Credit Agreement.

 

 

RECOMMENDED BY:  

 

 

 

 

________________________                                    ______________________________

Alan Brown, C.E.T.                                                      Jim Baird, M.C.I.P., R.P.P.

Director, Engineering                                                    Commissioner, Development Services

 

 

 


 

ATTACHMENTS:


Attachment ‘A’ – Location Plan

Attachment ‘B’ – Letter from Anison Management Inc. on behalf of the Wismer Developers Group

Attachment ‘C’ – DRAFT Credit Agreement