Report to: Development Services Committee Date of Meeting: May
16, 2006
SUBJECT: RECOMMENDATION REPORT
Monarch Corporation
Applications for Draft Plan of Subdivision Approval and By-Law Amendment
North side of
Elgin Mills, west side of
Cathedral Community
PREPARED BY:
RECOMMENDATION:
That the draft plan of subdivision 19TM-05006, prepared by Bousfields
Inc., dated February 21, 2006, to permit 204 single detached lots, 66 lane base townhouse units and 5.65
hectares of employment lands, north side of Elgin Mills, west side of Woodbine
Avenue, be endorsed subject to the conditions of draft plan approval as set out
in Appendix ‘A’ to the staff report dated May 16, 2006, and the following
redline revisions:
·
Woodbine
Avenue (Existing) / Street B intersection, West leg: Provide 24.0m ROW for 45m
in length. Remove 0.3m Reserve on both the north and south sides of the Street
B within the 24m ROW.
·
Woodbine
By-Pass / Street A intersection (West Leg): Provide 26.5m ROW for 30.0m in
length, and provide taper transition from 26.5m ROW to 22m for 30m in length.
·
Woodbine
By-Pass / Street B intersection (East Leg): Provide 26.5m ROW for 30.0m in
length, and provide taper transition from 26.5m ROW to 22m for 30m in length.
That the application submitted by Monarch Corporation to amend Zoning
By-laws 177-76 and 304-87, as amended, be approved, and the draft by-laws attached
as Appendix ‘B’ to the staff report dated May 16, 2006, be enacted;
That the
Director of
1.
The
Town has completed a detailed design study for the Woodbine Avenue By-pass;
2.
The
Landowner’s Group has prepared a survey plan of the proposed Woodbine Avenue
By-pass right-of-way that reflects the recommendations of the detailed design
study, to the satisfaction of the Town and the Region of York;
3.
The
Owner has conveyed to York Region, free of all costs and encumbrances, any land
required for the Woodbine Avenue By-pass within the boundaries of the draft
plan 19TM-05006 as identified by the above survey; and,
4.
If
required, the draft plan has been revised to reflect any changes to the
Woodbine Avenue By-pass alignment and any associated changes to the
configuration of the subject blocks and lots, resulting from the above survey.
That the applicant agree to pay their proportionate share of
the Hwy. 48 flow control measures, to the satisfaction of the Director of
That Monarch Corporation be granted a servicing allocation of 270
units, such allocation to be from the total allocation for the Cathedral
community, in accordance with the February 15 and
That
the Town reserves the right to revoke or reallocate the servicing allocation
for this development;
That the Region of York be advised of the
servicing allocation for this development;
That the
Mayor and Clerk be authorized to execute a parkland agreement between the Town
and the Cathedral West Landowners Group, in a form satisfactory to the Town
Solicitor and the Commissioner of Development Services with respect to
compensating the Cathedral West Landowners Group for the over-dedication of
0.702 hectares of park space that will result from the conveyance of the 4.89
hectare environmentally significant woodlot (Block 220) located at the
northwest corner of the draft plan area.
The basis for establishing the final value of the over-dedicated portion
of the woodlot shall be based on a land appraisal, to the satisfaction of the
Commissioner of Development Services. Payment to the West Cathedral Landowners
for this over-dedication shall be from funds secured through previous
cash-in-lieu of parkland contributions associated with subdivision approvals in
the East Cathedral Community, specifically for the purpose of the acquiring the
woodlot in the Monarch subdivision.
That the applicant provide the Town with the required
payment of 30% subdivision processing fees in accordance with the Town’s Fee
By-law (By-law 2005-357);
And further that the draft plan
approval for plan of subdivision 19TM-05006 will lapse after a period of three
years commencing
EXECUTIVE SUMMARY:
The 45.83 hectare (113.24 ac.)
site is located on the north side of
The proposed single detached and townhouse lots within Phase 1 comply with the uses and density (17 to 37 units per hectare) provided for in the Urban Residential - Low Density designation in the Official Plan. A zoning by-law amendment is required to implement the draft plan which is attached as an appendix to this report.
The first phase of the draft plan of subdivision proposes 270 residential units in the form of single detached, semi-detached and townhouses (204 singles, 66 townhouses). This phase also includes a 4.89 hectare (12.08 ac) woodlot, 2.27 hectare (5.63 ac) stormwater management pond and 5.65 hectares (13.96 ac) of employment lands located west of the proposed Woodbine By-pass. Servicing allocation has been granted only for Phase 1. The employment lands do not require servicing allocation. The second phase will not be approved until additional servicing capacity becomes available.
A statutory Public Meeting was
held on
Other issues raised and resolved as part of the circulation process include:
· Submission of studies
Staff are generally satisfied with the configuration
of the draft plan of subdivision and recommend that the plan be draft approved,
subject to the conditions above and in Appendix ‘A’.
FINANCIAL CONSIDERATIONS:
Not applicable.
1.
Purpose 2. Background 3. Discussion 4.
Financial 5.
Environmental
6. Accessibility 7. Engage
21st 8. Affected Units 9. Attachment(s)
This report presents an overview
and evaluation of the proposed plan of subdivision (19TM-05006). The report also includes draft zoning by-law
amendments to permit the proposed development.
The report recommends approval of the draft zoning by-laws and the draft
plan of subdivision, subject to conditions.
Property and Area Context
The 45.83 hectare (113.24 ac.)
site is located on the north side of
Official Plan designation
The subject lands are designated Urban Residential – Low Density, Urban Residential Medium Density, Open Space, Environmental Protection Area, Business Park and Business Corridor in the Cathedral Community Secondary Plan (OPA 42). The Secondary Plan was originally approved by York Region in 1997. An amendment was adopted by Town Council in June 2004 and approved by the Region in 2005. The proposed single detached and townhouse lots within Phase 1 comply with the uses and density (17 to 37 units per hectare) provided for in the Urban Residential - Low Density designation in the Official Plan (see Table A).
Existing Zoning
The lands are currently zoned Agriculture One (A1) by By-law 304-87. A zoning by-law amendment is required to implement the draft plan of subdivision.
A draft plan of subdivision with a mix of singles, townhouses and
employment lands
The first phase of the draft plan of subdivision (30.52 ha/75.41 ac) proposes 270 residential units in the form of single detached and townhouses (204 singles, 66 townhouses). This phase also includes a 4.89 hectare (12.08 ac) woodlot, 2.27 hectare (5.63 ac) stormwater management pond and 5.65 hectares (13.96 ac) of employment lands located west of the proposed Woodbine By-pass. Servicing allocation has been granted for only Phase 1. The employment lands do not require servicing allocation. Phase 2 comprises 192 single detached units, 29 lane base townhouse units, a 2.39 hectare (5.90 ac) school site and a 1.55 hectare (3.82 ac) park block. The single detached lots have frontages of 11.6 metres (38 ft), 14 metres (46 ft) and 17 m (56 ft) while the townhouses have a minimum lot frontage of 6.1 metres (20 ft). Phase 2 is not part of the Phase 1 application and will not be draft approved or zoned until additional servicing capacity has been allocated.
TABLE A |
|||
Phase 1 |
|||
|
Units |
Hectares |
Acres |
Gross site area Roads and laneways Road widening Open space Woodlot 2.7 m buffer SWM pond Employment lands 0.3 m reserve Single detached Townhouses |
204 66 |
30.52 7.50 0.102 0.621 4.893 0.023 2.27 5.65 0.032 8.048 1.375 |
75.41 18.53 0.252 1.53 12.08 0.056 5.60 13.96 0.079 19.88 3.397 |
Net Residential Area (Low Density) |
|
8.048 |
19.886 |
Net Residential Area (Medium Density) |
|
1.375 |
3.397 |
Net Residential Density (Low Density) |
204 |
25.34 uph |
10.25 upa |
Net Residential Density (Medium Density) |
66 |
48 uph |
19.42 upa |
Phase 2 |
|||
Gross Site Area Roads Park Buffer School Single detached Townhouses 0.3 Reesrve Widening Residential Reserve |
192 29 |
15.31 2.85 1.55 0.028 2.39 7.69 0.623 0.003 0.040 0.123 |
37.83 7.04 3.82 0.069 5.90 19.0 1.53 0.074 0.098 0.303 |
Net Residetial Area (Low Density) |
192 |
7.69 |
19.0 |
Net Residetial Area (Medium Density) |
29 |
0.623 |
1.53 |
Net Residential Density (Low Density |
|
24.96 upa |
10.10 upa |
Net Residential Density (Medium Density) |
|
46.54 |
18.95 |
Public Meeting was held on June 7, 2005
A statutory Public Meeting was
held on
·
Traffic
pressures on
Currently the
Region has scheduled the construction of the Woodbine Avenue By-pass from Major
Mackenzie Drive to north of Victoria Square in the 2006 Ten Year Capital Plan
for construction in the year 2012.
However, the Cathedral Developer’s Group and the Town have requested that
the project be considered in three distinct phases. Phase 1 is the portion of road from just
north of Major Mackenzie to Elgin Mills; Phase 2(a) is the portion of road
works that extends approximately 200 metres north of
To date, 300 units have been allocated to Cathedral Town Phase 1 and Phase 2 draft plans, which where approved 2003 and 2005 respectively. Subject to advancement of Phases 1 and 2(a) of the Woodbine By-Pass construction (Figure 5) and the Developer’s Group entering into a pre-paid Development Charges Credit Agreement, the Town allocated servicing capacity for an additional 800 units (500 in February 2005 and 300 in November 2005) for a total of 1,100 units to the West Cathedral Community.
This
draft plan includes the Phase 2(a) portion of the By-pass construction. This portion of the by-pass is essential for
diverting traffic around
To allow flexibility in the final alignment of the by-pass, should revisions be required, a condition of draft plan approval has been incorporated, whereby the owner agrees to convey to the Region of York, free of all costs, any portion of the by-pass within the boundaries of the draft plan of subdivision, if required by the detailed design study.
·
Construction
traffic and its impact on area
homeowners
Residents
expressed concern with respect to the impact construction vehicles would have
on their homes. The
The
townhouses adjacent to
·
Ensuring
the designs are appropriate for the character of the Cathedral Community
The applicant has submitted to the Town for review, housing prototypes which will help staff understand the impact of the various housing types on lot size configurations and will ensure that the designs are appropriate for the character of the Cathedral Community. Furthermore, the Developer must prepare Architectural Control Guidelines to the Town’s satisfaction prior to final approval of the plan.
·
The
alignment of roadways results in a number of collector roads exiting onto
While
it is true that the majority of east/west roads in this subdivision will
terminate at Woodbine Avenue, it is important to note that these roads will be
designed as local roads, not collector roads, and individually will carry small
volumes of traffic, related only to the houses that actually front on the
streets. More specifically, these local
roads will not carry through traffic since the plan does not provide for any
direct intersections between these local roads and the proposed Woodbine
By-pass. Only one east/west road in the
subdivision, located immediately south of the proposed park, has been designed
to collector road standards. This road
will provide a direct link between
1.
It will improve accessibility for
2.
As noted above, the number of vehicles entering
3.
The increased number of local intersections will reduce
traffic speeds on the section of
Sufficient servicing allocation to permit draft plan approval of Phase 1
As set out in the February and November 2005 servicing allocation reports, Council recommended that 270 units be allocated to the Monarch Corporation subdivision. This allocation is part of a larger regional allocation to the Town, approved by Regional Council in June of 2005. The 270 units comprise the applicant’s Phase 1, with the remaining units (Phase 2) to be approved once additional servicing capacity becomes available.
In February, 2005, Markham Council endorsed a proposed flow control option intended to bring the Town’s sewage allocation to a point that would match it’s current water allocation. Regional Council approved the flow Control option in June 2005.
The applicant will be required to pay $100 per unit as their proportionate share for the cost of the Highway 48 Flow Control System, which is required to create the sanitary sewer capacity for this project.
Agreement to advance the construction of the
Council authorized staff in March 2005, to finalize a tri-party agreement between the Region, Town and the Cathedral Developers Group, to advance the construction of the Woodbine Avenue By-pass. The agreement advances the construction schedule from its current date of 2011/2012 to 2007/2008. Detailed conditions are set out in the tri-party agreement.
The Region of York requests that prior to draft plan approval, the Cathedral West Landowners Group enter into an agreement with the Region for the construction and completion of the Woodbine Avenue By-pass, as outlined in the report adopted by York Region Council at its meeting on June 23, 2005 and revised on February 16, 2006.
On street parking not in close proximity to townhouse units adjacent to
On street parking is not
currently permitted on
The Town’s parking by-law only requires 2 parking spaces per unit. The attached draft by-law incorporates a provision permitting attached garages which would create two parking spaces in the garage and two additional spaces in the driveway which could be utilized for visitor parking.
Large woodlot conveyed as part of the parkland dedication for the
Cathedral Community
A 4.89 hectare (12.08 ac)
portion of a large woodlot located at
the northwest quadrant of the draft plan is being conveyed as part of the
parkland dedication for the Cathedral Community as part of Phase 1 of the
Monarch draft plan.
It was determined in the early
stages of the community design process that the Town was to secure the
dedication of the 4.89 ha portion of woodlot contained in the Monarch draft
plan area. In order to acquire this
woodlot an additional 1 acre/1000 population of parkland was requested at the
time of the East and West Cathedral Community
The West Cathedral community has
dedicated the 4.89 ha woodlot to satisfy the additional 1 acre/1000 population
requirement. The conveyance of the 4.89 ha portion of woodlot constitutes an
over-dedication of woodlot as 4.24 ha of parkland is required under the Town of
Draft zoning by-law implements draft plan of subdivision
The draft zoning by-laws delete the lands from the rural area by-law and incorporates them into the urban expansion by-law to permit the construction of the 270 units. The by-law also includes exceptions to permit attached garages for the townhouses adjacent to Elgin Mills and reduces the rear yard setback for certain single detached units affected by road widenings.
2.7 metre buffer required adjacent to flankage lots
A 2.7 metre (8.8 ft) landscape buffer adjacent to the flankage lots adjoining the Woodbine Avenue By-pass will be utilized for a berm/fence and associated landscaping, should noise attenuation be required.
All studies submitted
The
Functional Servicing Study (submitted, not yet approved)
Noise Impact Study (submitted, not yet approved)
Internal Traffic Study (submitted, not yet approved)
Stormwater Management Study (submitted, not yet approved)
Heritage Resource Study (submitted, not yet approved)
Tree Preservation Plan (submitted, not yet approved)
Phase 1 EA (submitted, not yet approved)
Hydrogeologic Study (submitted, not yet approved)
Lotting Distribution Plan (submitted, not yet approved)
Housing Prototypes (submitted, not yet approved)
These studies have been submitted by the applicant, and are currently under review by Town staff. The approval of the above noted studies will be required as conditions of draft approval. Red line revisions to the draft plan may be required, once the studies have been reviewed.
The base application fees and studies submitted in conjunction with the applicant’s original application was based on the entire draft plan (Phase 1 and 2). A second base fee will not be required at the time of application for the second phase. In addition, a resubmission of the studies will not be required, however, addendums may be necessary.
Draft zoning by-laws incorporate exceptions for attached rear garages
and for a reduction in the rear yard setback for single detached lots affected
by road widenings
The attached draft zoning
by-laws incorporate the subject lands into appropriate residential zone
categories within By-law 177-96.
Exemptions are incorporated into the draft by-law to permit attached rear
garages for the townhouse units adjacent to
An exception is also incorporated into the by-law, permitting a reduced rear yard setback for certain lots that were reduced due to road widenings at certain intersections of the collector roads to accommodate turn lanes.
CONCLUSION:
Staff are generally satisfied with the configuration of the draft plan of subdivision and recommend that the plan be draft approved, subject to the conditions above and in Appendix ‘A’.
FINANCIAL TEMPLATE (Separate Attachment):
Not applicable.
ENVIRONMENTAL CONSIDERATIONS:
The T
Not applicable.
ENGAGE 21ST CONSIDERATIONS:
The proposed development promotes a number of key goals set out in “Engage 21st Century Markham” by providing for efficient use of infrastructure, land use patterns and density , compact development and high levels of architectural and urban design.
BUSINESS UNITS CONSULTED AND AFFECTED:
The application has undergone a full circulation. Comments have been incorporated into the report, draft by-law and draft conditions.
DOCUMENT:
Q:\Development\Planning\APPL\SUBDIV\05 010968 MONARCH
CATHEDRAL\ReportTemplate_060426_v2.doc
RECOMMENDED BY:
________________________ ________________________
Director of
Figure 1 – Location Map
Figure 2 – Air Photo
Figure 3 – Site Context and Zoning
Figure 4 – Proposed Draft Plan of Subdivision
Figure 5 – Woodbine By-pass Phasing Map
Appendix ‘A’ – Draft Conditions
Appendix ‘B’ – Draft By-law
APPLICANT/AGENT:
Monarch Corporation
Attn:
M2J 1V7
Tel: (416) 491-7440 ext 275
Fax: (416) 640-1574