M I N U T E S
BUILDINGS
& PARKS CONSTRUCTION COMMITTEE
2007-11-16
Attendance
Members: Councillor C. Moretti, Chair Councillor V. Burke Regional Councillor J. Heath Deputy Mayor J. Jones |
Staff: J. Livey, Chief
Administrative Officer W. Snowball, Deputy Fire Chief A. Seabrook, Director Strategic Services P. Loukes, Director, Operations D. C. Biss, Chief Executive Officer, D. Pearce, Manager, Real Property S. Andrews, Director Asset Management S. Sydij, Sr. Construction Buyer M. Shatil, Project Consultant A. Wolfe, Project Consultant A. Tari, Committee Clerk |
The
DISCLOSURE OF INTEREST
Councillor C. Moretti disclosed an interest with respect to Item 5(b), as she is the President of the Markham Bocce Association Board of Directors and Vice-President for the new Centennial Bocce Club, and did not take part in the consideration or discussion of or vote on the question of the approval of such matters.
1. MINUTES OF BUILDING
AND PARKS CONSTRUCTION COMMITTEE MEETING HELD ON
Moved by Regional Councillor J. Heath
Seconded by Councillor C. Moretti
That
CARRIED
2. PARKS
No
update.
3. EVENTS
No update.
4. FIRE
a)
CATHEDRAL
Design Issue – Alan Wolfe,
Project Consultant, reported design work is progressing and anticipate a report
in a couple of months with the details.
He advised the building will be LEED certified and that the architect
will present the cost benefits of the levels of certification in order that the
committee can select the appropriate level of certification.
b) CORNELL
Bill Snowball,
Deputy Fire Chief, provided a PowerPoint presentation with respect to the “Fire
Responses, Roseway Area” from 2004 to date.
He advised that once the “
Land Acquisition - David
Pearce, Manager, Real Property advised that a meeting is scheduled for
Design Issues – No report.
5. RECREATION
AND CULTURE
a) EAST
Allan Seabrook,
Director Strategic Services, advised the Committee that a second charette has
been scheduled for
There was some
discussion with respect to
b) CENTENNIAL
COMMUNITY CENTRE PROJECT
Construction Update - Mr. Michael Shatil, Project
Consultant, provided an update on the construction of the Centennial Community
Centre Project. He advised the Contractor has requested that the contract time
be extended from
Moved by Regional Councillor J. Heath
Seconded by Deputy Mayor J. Jones
And
that Contract Number 055-T-05 between the Town of Markham and Canning
Contracting Limited for the expansion and renovation of the Centennial
Community Centre be extended from November 27, 2007 to January 31, 2008 as a
result of the time lost due to the strikes.
CARRIED
Arena (South) Parking Lot – Mr. Shatil advised that the parking lot is 90% complete and has been opened to the public. The light pole installation is expected to be completed in the next couple of weeks. He also advised there are six handicap spaces with no parking between them.
c) GO TRANSIT PARKING
DECK
Mr. Alan Wolfe,
Project Consultant, advised GO Transit has prepared a Site Plan application for
submission to the Town of
d)
Mr. Wolfe
advised the Committee the design of the
The Committee will invite all members of Council be in attendance for the presentation to allow for discussion and/or comments before the report is presented at General Committee.
6. LIBRARY
a)
Mr. Michael
Shatil, Project Consultant, provided an update on the Markham Village Library
construction. He advised installation of
major finishes is complete. Outstanding
work consists of paint finishes, internal window sills, baseboards, etc. The Building Department has conducted
preliminary inspections and has provided the contractor with a list of
deficiencies to rectify. Mr. Shatil
advised the official opening is scheduled for
Mr. Shatil
advised the architect will be submitting a letter to the Town indicating the required
maintenance for the wood slats and the reasons for incorporating it into the
design. It was suggested that the letter
be brought to the
NEXT MEETING
The next meeting
of the
ADJOURNMENT
The
APPENDIX ‘B’
CENTENNIAL COMMUNITY CENTRE
EXPANSION
Construction
Contingency Report
·
INCREASED
CONTINGENCY AMOUNT $845,300
·
CO
APPROVED TO DATE $688,000
·
CONTEMPLATED
CO (ESTIMATE) $ 60,000
·
CONTINGENCY
REMAINING $
97,300
APPENDIX ‘C’
Construction
Contingency Report
·
CONTINGENCY AVAILABLE FOR
CONTRACTUAL CHANGE ORDERS* $442,000
·
APPROVED CHANGE ORDERS $371,000
·
CONTEMPLATED CO (ESTIMATE) $ 61,500
·
CONTINGENCY REMAINING $ 9,500
*$32,255 of the construction contingency has been identified as the
funding source for the transformer upgrade.