Report to: Development Services Committee Report Date:
SUBJECT:
Class Environmental Assessment
PREPARED BY: Allan Arbuckle, Manager of Infrastructure and Capital Works
Nehal Azmy, Senior Capital Engineer, ext. 2197
RECOMMENDATION:
THAT the report entitled “
AND THAT the recommended restoration
implementation plan to address the erosion along
AND THAT the guidelines to restore erosion sites within private property as set out in this report be endorsed;
AND THAT staff report back to Council as to the funding for remediation of erosion sites on private property on a site by site basis;
AND THAT staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
The total future costs to undertake the restoration works of the top 30 priority sites identified in the Environmental Study Report is estimated as $12.8 million. These costs will be further refined once the detailed design for the erosion restoration works are completed.
Funding included in the 2004 Development Charges by-law for the Town wide watercourses erosion restoration works for the ultimate number of erosion sites (more than 30), are $44.6 million of which;
- $11.0 million is developers’ responsibility through plan of subdivision/site plan.
- $18.0 million, funded by Town wide development charges.
- $15.6 million,
funded by non growth sources (pre DCA
In the draft 2007 Capital Budget and the 2006 carry over,
$1.7 million is allocated for the restoration of the top six erosion sites as
outlined in this report.
1.
Purpose 2. Background 3. Discussion 4. Financial
5. Others (Environmental,
Accessibility, Engage 21st, Affected Units) 6. Attachment(s)
The purpose of this report is to
seek Council’s endorsement of the recommended restoration implementation plan
to address the erosion along
The Town is drained by nineteen
watercourses, many of which are tributaries of the
In 2005, the Town retained
Aquafor Beech Limited to update the Erosion Restoration Implementation Plan
study. The objective of the study was to
identify areas of erosion concern within the Town and to develop an implementation
plan to prioritize restoration of erosion sites. The focus of the study was to identify
erosion sites, evaluate risk to public health and safety, to identify
alternatives for restoration, to prioritize and prepare preliminary cost
estimates. The study was carried under Master Plans of the Municipal Class
Environmental
On
Public Consultation
Public
Consultation was initiated with regulatory agencies and a meeting was held at
the Town of
A newspaper ad was placed in both the Markham Economist & Sun and the Thornhill Liberal. Notice of the meeting was also mailed to numerous interest groups and residents who would be directly affected by restoration works at the priority erosion site locations.
Participants were invited to review poster boards and to determine whether any erosion sites, that they were aware of, had been omitted. A formal presentation was then given to provide an overview of the study. The presentation was followed by a question and answer period and then followed by roundtable discussions amongst participants, facilitated by members of the study team.
Twenty-one residents attended the public meeting, many of whom participated in round table discussions and provided responses and comments. In response to the received public comments, the study team completed follow-up field inspections to erosion sites that may have been missed and which were identified by the public. These sites were then included with the sites identified during the initial field walks and subsequently included in the analyses.
Regulatory Agency Involvement
At the outset of the study, the
TRCA was in overall support of the study and provided input regarding the erosion prioritization and restoration approaches. Each component of the priority ranking scheme was examined and agreement was attained as to the items to be included in each category.
Copies of the draft Class EA report were provided to TRCA for review. Any further comments to be received from TRCA regarding the Class EA report shall be addressed as part of the EA process.
The Recommended Restoration Implementation Plan
The recommended restoration implementation
plan detailed in the Class EA report identifies the top thirty prioritized
erosion sites as shown in (Attachment C).
Details of each site location, priority type, required action, recommended
rehabilitation alternative, class environmental schedule, required approvals,
benefits, habitat sensitivity class and costs pertaining to each priority
erosion sites have been tabulated and are presented in (Attachment D).
Funding Sources
The erosion sites that have been
identified for priority restoration are situated on lands which are owned by
various groups including private landowners, the Town of
Guidelines to Restore Erosion Sites within Private Property
Erosion sites on private property
are categorized as follows:
a) Erosion problems within private property which are the results of altered flow regimes due to upstream development. Funding for addressing erosion exacerbated by development was included in the Development Charges and should be funded by such.
b) Erosion that is not related to urbanization but is a result of natural process of river behavior. Funding for restoration works should be the responsibility of residents/TRCA.
c) Erosion of private property due to the alteration to watercourse by property owner and upstream development. Cost sharing with property owners on a site by site basis should be negotiated.
General steps identified in the Class EA report in dealing with private land owners are as follows:
a)
Landowner Contact;
- Discussion with landowner to explain what the problem is, and why restorative measures are required.
b) Permission to enter.
c) Funding resolution.
d) Agreement to undertake work on private property which will include;
- The Town is not admitting any liability.
- The property owner will indemnify the Town.
- The Town does not guarantee the effectiveness of the work to prevent additional erosion.
- The need for a permanent easement (in cases where public infrastructure is at risk on private property) and/or a temporary easement for construction access.
e) Construction of proposed works.
f) Inspection of final works including obtaining signoff on the items listed under the construction contract.
As part of any class environmental assessment, the Municipal Environmental Report should be reviewed on a 5 year basis to ensure consistency with new policies and to update priorities. The field inventory shall be completed at least every 5 years to determine whether there are any new erosion sites that pose a risk to public health and safety or whether previously identified sites should receive greater priority for restoration.
In
The detailed design is to be completed by July/August 2007, with the construction contract to be tendered in August. Construction could then commence late 2007. Staff are recommending that the construction contract not be tendered until required approvals/easements are obtained, agreements with private property owners are executed including cost sharing. The exact construction schedule will be dependent on TRCA/DFO conditions.
Costs included in the 2007 capital budget for the design and construction of the six erosion sites restoration is approximately $1.7 million. If the tendered cost of the six sites exceeds $1.7 million, then the number of restoration sites may have to be reduced or Council approval for additional funds will be required.
The study purpose is to develop an Adaptive Environmental
Management Plan which protects the public safety while concurrently improving
channel stability and the biological integrity of
Not applicable
Not applicable
The Finance, Legal, Operations and Asset Management
Departments have reviewed this report and their comments have been
incorporated.
RECOMMENDED BY:
________________________
________________________
Alan Brown, C.E.T. Jim Baird, M.C.I.P., R.P.P.
Director of
Attachment A - Study Area
Attachment B- Top six priority erosion restoration
sites
Attachment C - Thirty Priority Erosion Sites
Attachment D- Recommended Implementation Plan