1. Background
|
Region of |
Four-Lane Arterial |
Princess Street to ( |
Town of |
-Two-Lane Collector ( -Four-Lane Collector (Highway 7 to |
North of (Highway 48) |
Ministry of Transportation Town of |
Two-Lane Highway |
Past transportation studies
including the 2002 Markham Transportation Planning Study and the Greensborough
and Wismer Secondary Plan Transportation Studies indicate the need for certain road
improvements to deal with forecast north-south traffic demand. The commencement
of the Class Environmental Assessment which will determine the nature and
extent of these improvements has previously been deferred pending completion of
the Markham By-Pass from Highway 48 to Highway 407, the widening of the 9th
Line south of
Markham Council has directed that any improvements proposed for
With the recent completion
of the majority of the Markham By-pass by the Region of York, the start of the
9th Line reconstruction project, the impending transfer of ownership of Highway 48 from 16th
Avenue to Major Mackenzie Drive from the Province to the Town and continued
development of the Greensborough and Wismer Secondary Plan Areas along Highway 48,
the Town is now in a position to commence the EA Study.
2. Goal
The Environmental
Assessment will establish the preferred alternative solution and preliminary
design concepts to address traffic forecasts and Town streetscaping objectives for
the next 10-20 years for the entire section of Markham Road from Highway 407 to
the connection with the Markham By-Pass north of Major Mackenzie Drive Included in this assessment will be the
establishment of the appropriate road cross-section(s), streetscaping and
pedestrian related facilities, on-street parking opportunities, recommendations
for improvements to the Rouge River crossing north of Highway 407 and the
Robinson Creek crossing south of Major
Mackenzie Road, and recommendations for improvements to the current at-grade
crossing of the rail line located north of Bullock Drive/Parkway Avenue. It is expected that the project will be
undertaken as a Schedule “C” activity meeting the requirements of the Municipal
Class Environmental Assessment (June 2000).
The consultant will be required to confirm that this approach is
appropriate.
3. Scope of Work
The consultant must review
all available information and update this information to reflect the Town
heritage and urban design guidelines, current development proposals and
forecasts for land use/employment and capital infrastructure. The consultant will also be required to investigate
the need and justification for various transportation improvements in the Study
Area, identify existing and future deficiencies, develop and assess alternative
solutions to address these deficiencies, identify a preferred solution or
solutions and prepare preliminary designs for the preferred solution(s). The
study must address the requirements of the external review agencies and stakeholder
groups to develop broad based support for the implementation of the identified
preferred design concept. The consultant must work closely with and coordinate
the activities of the project team, the technical advisory committee (TAC) and
a community advisory group (CAG) to ensure that, to the greatest extent
possible, all viewpoints are identified, investigated and evaluated and that
the project documentation clearly supports the selection of the preferred
alternative solution and design concept.
3.1 Study Planning and Design
The study should follow the
first four phases of the Class EA planning process as outlined in the Municipal
Class Environmental Assessment (June 2000). The level of detail included in the
assessment must be sufficient to address the requirements of the external
review agencies and other stakeholders and must document the Study in sufficient
detail to address, if necessary, any Part II order requests.
Information to be prepared by
the consultant includes additional traffic data, topographical mapping and
property survey information to be used in the preparation of base mapping for
the project, aerial photographs, preliminary geotechnical, structural and
environmental investigations and other investigations and assessments as may be
required to establish, evaluate and determine the preferred design concept for
the project.
The evaluation of alternative solutions and designs must consider the
following as a minimum:
The Consultant will be required to provide the services described in the
following sections as a minimum. Additional investigations, assessments or
studies which the consultant believes are necessary to support the goals and
objectives of this EA should be described in the Proposal.
3.2 Transportation Analysis for Horizon Years 2006, 2011, 2021
Transportation requirements
must be considered in the context of existing and planned development and
having regard the diverse nature of adjoining land use along the
The consultant must consult
with the Town, Region and MTO staff to develop a representative data base to
illustrate existing traffic conditions and to confirm the most appropriate
transportation model to be used for analysis and assessment of the existing
conditions as well as the development and evaluation of future transportation
options. The study area, for purposes of
transportation analysis will extend, at minimum, from the Markham By-Pass to
The transportation analysis
should provide recommended phasing for the implementation of the preferred
alternative.
3.3 Natural
Environment Inventory
The consultant will conduct
an inventory of the natural environment throughout the Study Area with
particular focus of the terrestrial and aquatic habitat and wildlife in the
vicinity of the
and
3.4 Heritage
Resource Inventory
The consultant will prepare
an inventory of existing built heritage resources in the Study Area and will
develop, in consultation with the TAC and CAG, design criteria for the
recommended transportation facilities which will recognize, preserve and
enhance the distinct heritage characteristics of the Study Area.
3.5 Land Use/Urban Design
The consultant
will review Official Plan and Secondary Plan policies and Council endorsed
urban design guidelines for the Study Area, and reflect Town land use and urban
design objectives in their recommendations.
3.6 Archaeological Assessment
The consultant will prepare a Stage 1 archaeological assessment for the
Study Area to determine if any archaeological resources are present in the
Study Area and to identify what direct or indirect impacts might result from
construction activities.
3.7 Socio-Economic Assessment
The selected design option must support the
existing and planned land uses along the corridor while strengthening the
viability of the commercial core as a pedestrian oriented retail area. To
ensure these objectives are satisfied, the consultant must conduct a detailed
inventory of existing and future land uses along the corridor, assess the
sensitivity of the adjacent land uses to noise and vibration impacts associated
with roadway improvements and assess the demand for and supply of parking.
3.8 Infrastructure Inventory
A number of municipal infrastructure systems including storm sewers and
stormwater management facilities, wastewater mains and watermains are located
within the
3.9 Preliminary Design & Cost Estimation
The design concepts and
drawings developed as a part of previous transportation and urban design
studies must be considered during the preparation of alternative solutions and
preferred design concepts. The preferred
design concept should be prepared in sufficient detail to serve as a
preliminary design of major facilities including roadway, pedestrian and
cycling facilities, watercourse and rail crossings including preliminary structural
arrangements, municipal servicing upgrades including stormwater management
works, natural environmental protection and enhancements and streetscaping works.
The preliminary design must
also identify the property impact of the preferred concept. All alternatives should be reviewed to determine
the required property taking and the evaluation of alternatives should consider
not only the cost of land acquisition but the potential impact on adjacent land
uses.
The consultant will be
required to prepare preliminary cost estimates for the recommended alternative
and to include in this cost estimate construction and property acquisition
costs.
4. Technical Advisory Group (TAG)
A technical advisory group
(TAC) is required to review, advise and approve the approach, analysis and
findings through the project as well as to ensure that all issues and interests
are addressed. The TAC will consist of representatives
of:
5. Community Advisory Group (CAG)
The community advisory
group (CAG) will be comprised of appointed representation from Markham Council
and various stakeholders including but not limited to:
The CAG will
provide a forum for all stakeholders to provide input and to ensure solutions
are developed and evaluated considering all interests.
6. Public Consultation
Given the size and complexity
of the study, the consultation process will be expanded beyond the minimum
requirements as set out for a Schedule ‘C’ project (Notice of Study
Commencement, two public consultation centres and a Notice of Completion of the
Environmental Study Report), to include additional sessions to ensure that
those individuals or groups having interest in the study have the opportunity
to actively participate in the Study.
7. Facilitation
Given the large number and
diverse nature of stakeholders, the negotiation and facilitation skills of the
selected consultant are considered essential to ensure that all viewpoints are
considered and appropriately evaluated through the environmental assessment
process. Accordingly, facilitation should be an integral component of the
project approach and the consultant must demonstrate proven abilities and
experience in these areas.
8. Meetings Requirements
The Consultant shall allow
for participation in a number of meetings with the Town in connection with the
Environmental Assessment Process and the enhanced public consultation program.
For the purpose of this project, the consultant will be required to;
9. Final Report
Final delivery of the ESR
must include one camera ready copy, 6 bound copies (not including those copies
for submission purposes to external agencies), including digital copies of the
report, figures, design drawings in a reproducible PDF form as well as in the
AutoCad format.
10. Background Information
The following information will be made available to the consultants for
review and copies provided to the preferred consultant upon award of the
project.
11. Schedule
The initial phase of the
project, to be completed in 2007, will be dedicated to collecting and reviewing
background documentation and undertaking various background investigations including
bridge condition surveys, geotechnical & hydrogeological investigations,
preliminary hydraulic, hydrologic and stormwater management related
investigations, natural environment studies, heritage and archaeological
studies, evaluation of existing legal boundaries, compilation of traffic data, development
of a traffic model and preparation of base plans. In addition, consultation
with all external technical reviewing agencies will be undertaken to establish
the TAC and CAG.
Subsequent phases of the
project including public consultation, the development and evaluation of
alternative solutions, the selection of a preferred solution and design concept
and the preparation of the Environmental Study report will commence in late 2007
and it is anticipated that the Environmental Assessment will be completed by
The use of Microsoft
Project is required to illustrate the proposed master schedule. It is the intent that the preferred
consultant will use this particular project management software to establish,
guide an monitor the key elements of the project, namely budget, resources and
timeline.
The allocation of resources
and budget should be provided including key personnel and respective charge hourly
rates including the details of subconsultants and the relevant staff. During the course of the project regular
updates to schedule and budget are required with each invoice submission at
minimum.