Report to: Development Services Committee                             Date of Meeting:  May 1, 2007

 

 

SUBJECT:                          RECOMMENDATION REPORT

                                            Dufferin Concrete

                                            7655 Woodbine Avenue

                                            Applications for Official Plan and zoning by-law amendment to permit the modernization of an existing concrete plant

 

                                            FILES:  OP 06 132795 and ZA 06 132837

                                           

PREPARED BY:               Scott Heaslip, ext. 3140

                                            Senior Project Coordinator,

                                            Central District

 

 

RECOMMENDATION:

That the report dated May 1, 2007 entitled “RECOMMENDATION REPORT, Dufferin Concrete, 7655 Woodbine Avenue, Applications for Official Plan and zoning by-law amendment to permit the modernization of an existing concrete plant,” be received;

 

And that the record of the Public Meeting held on March 20, 2007 to consider the requested Official Plan and zoning by-law amendments, be received;

And that the Official Plan Amendment application (OP 06 132795) be approved as outlined in the staff report and the draft Official Plan Amendment attached as Appendix ‘A’ be finalized and adopted;

And that the Zoning By-law Amendment application (ZA 06 132837) be approved as outlined in the staff report and the draft implementing zoning by-law attached as Appendix ‘B’ be finalized and enacted;

And that staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

The 3 hectare (7.4 acre) property,  located at the south-east corner of Woodbine Avenue and Riviera Drive, is occupied by a concrete batching plant operated by Dufferin Concrete.  Dufferin Concrete is proposing to modernize and upgrade this facility by replacing the existing equipment with newer, more modern equipment. 

 

Official Plan and zoning by-law amendments are required to permit the proposed facility modernization. A Public Meeting was held to consider the requested amendments, and   all technical and design issues have been addressed to the satisfaction of staff.  This report recommends approval of the proposed Official Plan zoning by-law amendments.

 

 

 

 

 

FINANCIAL CONSIDERATIONS:

Not applicable.


1. Purpose                2. Background         3. Discussion             4. Financial         5. Environmental

 

6. Accessibility       7. Engage 21st             8. Affected Units       9. Attachment(s)

 

 


PURPOSE:


The purpose of this report is to discuss and recommend approval of applications for Official Plan and zoning by-law amendment to permit the proposed modernization of the Dufferin Concrete batching plant located on the east side of Woodbine Avenue, south of Riviera Drive.


 

BACKGROUND:


 

Subject Lands and Area Context

The 3 hectare (7.4 acre) property is located at the south-east corner of Woodbine Avenue and Riviera Drive.   The property is occupied by a concrete batching plant operated by Dufferin Concrete, a division of St. Lawrence Cement.  

 

Surrounding uses include multiple unit industrial buildings to the south and east, vacant lands, a multiple tenant industrial building and a Town of Markham fire station to the north across Riviera Drive, and commercial uses to the west across Woodbine Avenue (Figure 3).

 

Applicant proposes to modernize existing facility

Dufferin Concrete is in the midst of a program of modernizing and upgrading their existing facilities across the GTA to reduce environmental impact, improve efficiency, and improve customer service.  

 

The proposed modernization and upgrading of this facility includes the replacement of the existing batch plant (cement storage silos and mixers), operations building (operator’s office and storage), aggregate handling system (aggregate storage and conveyors to batch plant), boiler house (compressed air for machinery and steam for winter operations), and washout facility (wash down and wash out returning trucks). 

 

The applicant also proposes to remove the front section of the existing truck repair garage building and reface the remaining section, as required, to match the other facilities.   

 

Official Plan and zoning by-law amendments required

The subject property is designated “Commercial (Commercial Corridor Area)” in the Official Plan.  This designation does not provide for a concrete batching plant and the associated outside storage, which is an industrial use. The majority of the property is zoned M4, which permits the concrete batching plant and the associated outside storage.  However the north-east portion of the property is zoned A1 – Agricultural, which permits only agricultural uses (Figure 2).   Official Plan and zoning by-law amendments are required to permit the proposed facility modernization.

 

 


 

OPTIONS/ DISCUSSION:


 

Existing facility is long standing use at this location

The existing concrete batching plant has operated at this location for more than 25 years.  The applicant advises that it would be difficult to relocate this facility as concrete batching plants need to be close enough to their customers that the delivery trucks can make their deliveries and return to the plant before the concrete begins to set.

  

Proposed modernization provides opportunity for site improvements and upgraded landscaping

The proposed modernization includes the following site improvements (Figure 4 and 5):

·        Replacement of the batch plant, operations and aggregate handling facilities with more modern equipment.  The new equipment will be primarily faced with grey prefinished metal.

·        New 6 metre wide landscape buffer containing a 1.2 metre high berm, screen fencing and intensive plantings along the Woodbine Avenue and Riviera Drive frontages.

·        Consolidation of access driveways.

·        Curbing and paving of access driveways and the employee parking area. 

 

The environmental impact of the facility will be reduced through the following:

·        New truck washout and washdown facility will act as a sedimentation basin to contain wash water and reduce tracking onto adjacent streets.

·        Wash water will be recycled back into production.

·        Concrete remaining in returning trucks will be cast into blocks, crushed and reused.   This activity involves dumping the material into forms to solidify, storing the material in a pile at the rear of the property, and bringing in portable equipment twice each year to crush the concrete to allow it to be recycled into the batching plant.

 

No Public Concerns

A Public Meeting was held on Tuesday March 20, 2007 to consider the requested Official Plan and zoning by-law amendments.  No members of the public attended the meeting.  

 

Committee raised a minor concern about the condition of the existing sidewalk along Woodbine Avenue.  As a condition of site plan approval the applicant will be required to reinstate any damaged sections of the existing sidewalk along Woodbine Avenue and also to construct a new sidewalk along the Riviera Drive frontage of the subject property.

 

Technical issues have been addressed by the applicant

The technical issues identified by Town staff and public agencies have been addressed, as follows (see Figure 4): 

  • The requirements of the Region of York have been incorporated into the project plans.
  • The design of the landscape buffers adjoining the streets and the security fencing and gating have been refined to the satisfaction of staff.   
  • The fencing along the south and east boundaries has been upgraded to a solid board wood fence.   The wood fence has also been extended, behind the berm,  across the southern portion of the Woodbine Avenue frontage and eastern portion of the Riviera Drive frontage.  

 

The applicant has also applied for site plan approval.  Site plan approval for industrial developments is delegated to staff.  Staff will ensure that these matters are addressed in the conditions of site plan approval and secured in the required site plan agreement.

 

Draft Official Plan and Zoning By-law amendments

The draft Official Plan Amendment (Appendix ‘A’) incorporates a site specific exception into the Official Plan permitting a concrete batching plant at this property, notwithstanding the Commercial (Commercial Corridor Area) designation.

 

The draft zoning by-law amendment (Appendix ‘B’) zones the entire property M4, and incorporates site specific provisions reflecting the proposed development and regulating the location and maximum height of the proposed recycled material pile.


 

FINANCIAL TEMPLATE (Separate Attachment):


None at this time.

 

ENVIRONMENTAL CONSIDERATIONS:

The proposed modernization would reduce the environmental impact of the facility. 

 

ACCESSIBILITY CONSIDERATIONS:

None at this time.

 

ENGAGE 21ST CONSIDERATIONS:

The proposed development will support the following key goal of “Engage 21st Century Markham -   Environmental focus.           

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The application has been circulated to all relevant departments and outside agencies.  The  requirements of Town department and public agencies will be secured in the required site plan agreement .

 

 

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                       Valerie Shuttleworth, M.C.I.P, R.P.P                 Jim Baird, M.C.I.P, R.P.P

                                             Director, Planning & Urban Design                Commissioner, Development

                                                                                                                                Services

 

 

 


 

ATTACHMENTS:


Figure 1 - Location Map

                                                Figure 2 - Area Context

                                                Figure 3 - Air Photo

                                                Figure 4 - Proposed Site Plan

                                                Figure 5 - Existing and proposed concrete batching plant

                                               

                                                Appendix ‘A’ - Draft Official Plan Amendment

                                                Appendix ‘B’  - Draft zoning by-law amendment

 

                                                Contact:           Dana Anderson

                                                                        Meridian Planning Consultants

                                                                        2400 Meadowpine Boulevard, Suite 102

                                                                        Mississauga, Ontario

                                                                        L5N 6S2

 

                                                                        Tel:       (905) 818-2993

                                                                        Fax:      (905) 819-2994

                                                                        Email:   dana@meridianplan.ca

 

                                                Q:\development\planning\appl\zoning\06 132837\final report