Report to: Development Services Committee Report Date:
SUBJECT: RECOMMENDATION REPORT
JM
Hospitality & HDBB Investments Inc.
Application
for Site Plan Approval to permit a seven storey hotel with 99 suites (
File No. SC 07 117171
PREPARED BY: Stacia Muradali, Ext. 7922
Project Planner, Central District
RECOMMENDATION:
That the report
dated
That the application for site plan control approval (SC 07 117171) by JM Hospitality & HDBB Investments Inc. for a seven storey, 99 suite hotel (Hampton Inn and Suites), be endorsed in principle, subject to the conditions attached as Appendix ‘A’;
That the site plan approval be delegated to the Director of Planning and Urban Design, or her designate, to be issued following execution of a site plan agreement. Site plan approval is issued only when the Director has signed the site plan;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
JM Hospitality & HDBB
Investments Inc. are requesting site plan approval for
Phase 2 of a hotel development. Phase 1, a six storey, 101 suite hotel (
FINANCIAL CONSIDERATIONS:
Not applicable
1. Purpose 2. Background 3. Discussion 4. Financial 5. Environmental
6. Accessibility 7.
Engage 21st 8. Affected Units 9.
Attachment(s)
BUSINESS
UNITS CONSULTED AND AFFECTED:
________________________ ________________________
Valerie Shuttleworth, M.C.I.P,
R.P.P Jim Baird, M.C.I.P, R.P.P
Figure 2: Area Context and Zoning
Figure 4: Proposed Site Plan (Phase 2)
Figure 5: Proposed Building Elevations
Figure 7: Proposed Site Plan for Phases 1 and 2
Appendix ‘A’: Conditions of Site Plan Approval
JM Hospitality & HDBB Investments Inc.