SUBJECT: Eckardt Creek Erosion Control Optimization
Study
PREPARED BY: Soran Sito, Senior Environmental
Engineer
RECOMMENDATIONS:
That the
staff report entitled “Eckardt Creek Erosion Control Optimization Study” dated
And that staff be authorized to file the
Eckardt Creek Erosion Control Optimization Study Class EA study with the
Ministry of the Environment (MOE) for public review;
And that implementation of the retrofitting of the stormwater management pond (Bridal Trail Phases 3 and 4) to increase quality/quantity control be considered as part of the Markham Stormwater Strategy and future capital budget process;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
On
The results of the study show urbanization south and north
of
In general,
all parties agreed that restoring the creek naturally by increasing the control
of storm runoff at the source was the preferred option. However, because of the
considerable
limitations relating to availability and cost of land, retrofitting of the
existing stormwater management ponds via increasing quality/quantity control
will provide the greatest return on the investment in this project. Based on the results of the public meeting
held on November 30, 2006, it was established that retrofitting of the Bridal
Trail Phase 3 and Bridal Trail Phase 4 stormwater ponds located west of Eckardt
Creek, south of 16th Avenue (Figure -1) is the preferred option.
FINANCIAL
CONSIDERATIONS:
The estimated range of costs to retrofit the Bridal Trail
Phases 3 and 4 stormwater management ponds (two ponds) is in the range of
$900,000 - $1,000,000. The retrofit work
will be financed by development charges and pre-Development Charges Act
PURPOSE:
The purpose of this staff report is to seek Council’s endorsement of the above recommendations to address erosion problems in the Eckardt Creek and obtain authorization to file the Class Environmental Assessment.
BACKGROUND:
Eckardt Creek is located within the central part of the Town
of
On
The study objective may be defined as follows:
· Assess existing erosion conditions in Eckardt Creek and predict future erosion based on a number of different stormwater management scenarios.
· Evaluate the effectiveness of the various stormwater management scenarios and select a preferred scenario.
· Once the preferred scenario has been selected, undertake the detail design, construction supervision and monitoring of effectiveness of the proposed works.
The 5 phases of the Eckardt Creek Erosion Control Optimization Study and the status of each phase are described in Table-1 below:
Table-1: Project Phases & Status
Phase |
Description |
Status |
Phase I |
Background review, problem identification, selection and evaluation of alternative stormwater management options |
Completed |
Phase II |
Select the preferred stormwater management option. Complete the Class Environmental Assessment of the preferred option |
Completed |
Phase III |
Detail design and a tender package for the preferred option will be developed, and the proposed works will be constructed |
Subject to budget approval |
Phase IV |
Implement the environmental monitoring program to confirm the long term impact of urbanization |
Subject to budget approval |
Phase V |
A report summarizing the findings from the first four phases will be prepared |
Subject to budget approval |
Town staff and their consultant have completed Phase I and II of the study. Phases III, IV and V are subject to Council approval of the required funding. The Class EA document for this study will be filed with the Minister of the Environment before the end of 2007.
OPTIONS/DISCUSSION:
Problem Identification
As a result of urbanization, a
number of potential problems have been identified within Eckardt Creek. These problems include:
Establishing Existing
Conditions
Existing conditions were established by reviewing existing documents,
undertaking a hydrologic analysis and determining the stability of Eckardt
Creek via a field program. The above
noted activities will also be of assistance for determining the impact of
proposed development.
The field program focused on the natural portion of
the stream (i.e.: from approximately
500m north of 16th Avenue downstream to the confluence of Eckardt Creek and the
Rouge River – refer to Figure 1). Photographs
illustrating representative segments of the stream channel were taken. Furthermore, the data which characterized the
morphology of the stream (i.e.: channel gradient, pool/riffle structure,
channel dimensions, boundary material, vegetation type) was collected.
The objective of the field program was to characterize
existing stream conditions and to provide a benchmark for assessing the
potential impact of future development as well as the effectiveness of
alternative stormwater management strategies.
The results of the field program which was undertaken
in 1999, 2003 and 2006 show that Eckardt Creek has been significantly
degraded. Furthermore, the stream
continues to respond to the impact of development in the upstream reaches.
Establishing Options
In order to address the above noted concerns, 3
stormwater management options were investigated. These stormwater management options were categorized
into 4 groups as shown in Table-2 below:
Table-2: SWM Groups & Alternative Options
SWM Groups |
Options |
Source control measures |
Option 1: construction of an underground infiltration
facility in a recently constructed park located north of |
Infiltration measures |
|
Modification to
existing stormwater management facilities to improve water quality and/or
quantity control |
Option 2: retrofitting two existing stormwater management
ponds, Bridal Trail Phases 3 and 4 Ponds (identified in the Town of |
Stream restoration
measures |
Option 3: restoring approximately 500m of the Eckardt Creek
from |
Selection of the Preferred Option
In addition to developing a long term approach to protect, enhance and restore Eckardt Creek, selection of the preferred option also involved consideration of land cost, feasibility of implementation, environmental benefits, and social impact.
The environmental benefits and the feasibility of construction of the underground infiltration facilities (option 1) were limited due to:
The restoration of 500m of Eckardt Creek south of
of erosion south of
Retrofitting of the Bridal Trail Phase 3 and Bridal Trail Phase 4 ponds (option 2), was selected as the preferred one because option 2:
Based on the above, option 2 was selected as the preferred option for this study. In addition, as part of phase IV, additional instream monitoring and data collection is required to further understand the impact from recent development north of 16th Ave. on the section of Eckardt Creek south of 16th Avenue. The findings from the monitoring program will be used to assist in determining whether instream work is needed to restore the creek. The location and type of work, if necessary, would then be assessed.
Undertaking of Municipal Class EA for the Retrofitting of
Bridal Trail Phases 3 and 4 Stormwater Management Facilities
The Environmental Assessment (Phase 2 of the overall
project) has been initiated. The study,
which is being carried out under Schedule B of the Municipal Class EA process,
will define the Preferred Conceptual Design for each of the two
facilities. To-date, the Notice of
Commencement has been filed and alternatives for each facility have been filed. A Public Open House meeting was also held on
FINANCIAL TEMPLATE:
To be considered under future capital budgets.
ENVIRONMENTAL CONSIDERATIONS:
The implementation of the recommendations provided in this report, with the assistant of the Federation of Canadian Municipalities and the TRCA, should result in improved protection of the Eckardt Creek as a vital water course and a natural heritage system within the Eckardt Creek subwatershed. As such, an overall interest exists within most
government levels in promoting the protection of water courses and enhancing the long-term social and environmental benefits.
ACCESSIBILITY CONSIDERATIONS:
None
ENGAGE 21ST CONSIDERATIONS:
The findings and recommendations
of the Eckardt Creek Erosion Control Optimization Study are aligned with the
Environmental Focus goal of the Town’s Engage 21st Markham Strategic
Plan.
BUSINESS UNITS CONSULTED AND AFFECTED:
The Eckardt Creek Erosion Control Optimization Study has been prepared in consultation with the Operations and Asset Management Departments and their comments have been incorporated.
RECOMMENDED BY:
__________________________ __________________________
Alan Brown, C.E.T. Jim Baird, M.C.I.P., R.P.P.
Director of
ATTACHMENTS:
Attachment
A: Figure 1 - Location map
Q:\Development\Engineering\REPORTS\2007\October\Eckardt
Creek Erosion Control Optimization Study 101607.doc