Report to: Development Services Committee Date:
SUBJECT: Highway 404 Northbound Off Ramp Extension at Highway 7
Class Environmental Assessment
PREPARED BY:
Renee Chong, Capital Works Engineer, ext 2034
RECOMMENDATION:
THAT the staff report entitled “Highway 404 Northbound Off Ramp Extension at Highway 7 Class Environmental Assessment” , dated December 4, 2007, be received;
AND THAT the preferred alternative for the construction of the Northbound Off Ramp at Highway 404 and Highway 7 as set out in the Environmental Study Report be endorsed;
AND THAT staff be authorized to issue a
Notice of Study Completion for the project which will make the Environmental
Study Report available for public review for a period of 45 days commencing
AND THAT the Mayor and Clerk be authorized to enter into Agreements to acquire land which may be required to implement the preferred alternative in a form satisfactory to the CAO and the Town Solicitor and subject to capital budget approval;
AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.
The purpose of this report is to
seek Council’s endorsement of the preferred alignment of the Highway 404
northbound off ramp at Highway 7 as set out in the Class Environmental Assessment.
The need for traffic improvements
in the
Previous traffic studies have
recommended that the existing 404 northbound off-ramp at Highway 7 be extended
northerly to provide a direct connection to
DISCUSSION
Recommended Alternative
The recommended alternative is
presented on Attachment “B” and includes the creation of a new north-south road
which will form the fourth leg of the existing tee intersection at Highway 7
and the 404 off ramp. The new roadway will be extended northerly along the west
limit of the
The proposed road will have a 3 lane cross section with 2 northbound lanes and one southbound lane. Turning movements at the Highway 7 intersection will be restricted to an outbound right out only and no access from Highway 7 to the new road will be permitted.
Land Requirements
The majority of land required to
construct the project was acquired from
Public Consultation
The Environmental Assessment for the Highway 404 Northbound Off Ramp Extension at Highway 7 has followed the public and stakeholder consultation process requirements for Schedule ‘C’ projects as set out in the Municipal Class EA. This consultation process involved the publishing of a Notice of Project Commencement, two public open houses, meetings with reviewing agencies and a Notice of Study Completion which will be published. One written comment and a number of verbal comments have been received to date as a result of the consultation process and all of these comments have been supportive of the project.
Construction Schedule
The
The cost of construction for this
project is estimated at $7.0 million excluding property costs. Funding in the
amount of $206,200 is available in account #7712 for the design of this project
in 2008. A more detailed cost estimate
will be provided during the detailed design stage.
The alignment of the off ramp road extension was selected through an Environmental Assessment process to minimize the potential impacts to the environment.
The Legal Department has reviewed this report and their comments have been incorporated.
RECOMMENDED BY:
_______________________ ________________________
Alan Brown, C.E.T. Jim Baird, M.C.I.P., R.P.P.
Director of
Q/development/engineering/reports/2007/november
Attachment A - Site Location
Attachment B - Road Alignment