Report to: Development
Services Committee Report Date:
SUBJECT: Update on Train Anti-whistling at Rail Crossings
PREPARED BY: Sabbir Saiyed, Manager, Transportation, ext. 8120
RECOMMENDATION:
That the report entitled “Update on
Train Anti-whistling at Rail Crossings”, be received;
And that staff report back on an
Automated Horn System and the anti-whistling pilot project in the Unionville
and Markham areas;
And that staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable.
1.
Purpose 2. Background 3. Discussion 4. Financial
5. Others
(Environmental, Accessibility,
Engage 21st, Affected Units) 6.
Attachment(s)
This report provides an update to Council on the status of train anti-whistling at rail crossings on the Uxbridge line in Markham.
Uxbridge Line - Description
The Uxbridge Line runs generally
in a north-east direction and is owned by GO Transit and operated by CN on
their behalf. The most southerly rail crossing is located on
September 2003 – Council Request
In September 2003, Council requested staff to report on the feasibility of train whistle cessation at rail crossings. Staff reported back later that month outlining the overall process for the elimination of train whistling at rail crossings. Staff was then directed by Council to investigate train whistle cessation at 17 locations along the Uxbridge Line (Attachment A). In 2004, staff launched a rail crossing safety audit along the Uxbridge Line which was completed in early 2005. The results of the safety audit identified various rail crossing improvements in order to implement train whistle cessation along the Uxbridge Line. Rail crossing improvements include installation of signs, pavement markings, gates, bells and flashing lights.
As Town staff was investigating the train whistle cessation, GO Transit had conducted their own safety review and consequently installed safety measures at six rail crossings along the Uxbridge Line that included, bells, lights and gates at the following locations (see Attachment A):
In December 2005, staff contacted GO Transit regarding the safety audit results and discussed liability issues in the event of train whistle cessation implementation at rail crossings. The discussions revealed that the Town and Region would likely assume increased liability where train whistle cessation is implemented at rail crossings.
During this process, staff had
discussions with the Region regarding train whistle cessation at the eight
Regional railway crossings in which all are located in
On
On May 24, 2007, York Region Council adopted a staff report entitled “Anti-whistling at Regional Road Rail Crossings”, with the following recommendations:
As identified in the Region’s
report, train whistle cessation at
Train Whistling – General Information
Locomotive engineers are required to sound the train whistle approximately 400 metres (quarter mile) from every public grade crossing and until the rail crossing is fully occupied. Where conditions are met for train whistle cessation, the restriction of whistling could be on a 24 hour basis. The following factors are considered for train whistling cessation at rail crossings:
o Train speed
o Number of tracks
o Pedestrian/bikeway crossing protection
However, even under train whistle cessation at rail crossings, the operator of the train is at liberty to sound the train whistle when deemed necessary.
Automated Horn System (AHS)
An alternative to train whistle
cessation, which has recently been supported by Transport
Although the AHS may be an alternative option to train whistle cessation, the following concerns require resolution:
York Region staff have met with both Canadian National Rail and GO Transit to discuss the use of AHS. There are several outstanding concerns that are preventing the AHS from being fully considered by the Region at this time, namely: the noise impacts at the grade crossings, the lack of standard specifications available for AHS, safety measures to be used at the crossing and the legal and insurance requirements to implement the system. York Region staff will continue to collaborate internally with their Risk Management and Legal staff to come up with a plan to continue moving forward on this matter.
At the time of authoring this
report, a meeting has been set on
Next Steps
The amount of $182,145 has been budgeted for the train whistle cessation project in accounts 083-5350-6146-005 and 083-5399-6501-005 for capital works associated with train whistle cessation.
The Finance and Planning Departments have reviewed this report and their comments have been incorporated.
RECOMMENDED BY:
Alan Brown, C.E.T. Director of |
|
Jim Baird, M.C.I.P., R.P.P Commissioner, Development
Services |
Attachment A – Uxbridge Train Line
Attachment B – Automated Horn System Sound Contour