
Report to: General Committee Report
Date: April 16,
2007
SUBJECT: Status Report on the
Ontario Power Authority’s Integrated Power System Plan (IPSP)
PREPARED BY: Viive Sawler, Manager, Markham Energy
Conservation
Office
- x 7523
RECOMMENDATION:
THAT the Report
titled, “Status Report on the Ontario Power Authority’s Integrated Power System
Plan (IPSP)” be received;
THAT Council
supports the position that efforts on Conservation Demand Management (CDM)
should be given priority and emphasized within the Province’s IPSP;
THAT Council
supports the position that a greater system planning emphasis and dependence on
distributed generation and district energy technologies in communities be
included within the Province’s IPSP;
THAT Council
supports an “integrated solution” for supply to Northern York Region comprised
of: Demand Reduction; New Transformer
Station capacity; and Local Generation as adopted by Council on September 27, 2005;
THAT The Town of
Markham is strongly opposed to a transmission contingency solution for Northern
York Region and requests the OPA to expedite supply options to Northern York
Region that do not include transmission solutions;
THAT Council supports
submission of this Report to the Ontario Power Authority, the Ontario Energy
Board, Hydro One, PowerStream, Region of York, and the Ministry of Energy;
AND THAT Staff be
authorized and directed to do all things necessary to give effect to this
resolution.
EXECUTIVE SUMMARY:
Not applicable
FINANCIAL CONSIDERATIONS:
Not applicable
PURPOSE:
The purpose of
this Report is to provide Committee with an update on the status of the Ontario
Power Authority’s Integrated Power System Plan (IPSP) and outline the Town of Markham’s position in
terms of supporting Conservation Demand Management, distributed generation and
district energy technologies and a lessened dependence on the high voltage
transmission system.
BACKGROUND:
Ontario’s electricity sector has reached a challenging point in
history. The system has less capacity today
than it had 12 years ago while demand has increased due to population and economic
growth. The Ontario Power Authority was
established in 2004 with a mandate to address the Province’s electricity
conservation and supply challenges.
In December 2005,
the OPA delivered the Supply Mix Advice Report (SMA) recommending options for the
future development of Ontario’s
electricity system. In June 2006, the
Ontario Ministry of Energy issued its Directive specifying the relative
contributions to be made from Conservation Demand Management (CDM), renewable
generation and conventional sources of supply.
Between June 2006 and January 2007, the OPA held various stakeholder
workshops and teleconferences to solicit feedback on the eight Discussion
Papers that were published to inform the IPSP.
The Preliminary IPSP was released in February 2007 and represents a
mechanism by which key electricity system, sustainability and government policy
requirements are met. With the input
from the stakeholder consultation process, the OPA will refine the Preliminary
Plan into a recommended plan that the OPA will file with the OEB in the spring/summer
of 2007.
OPTIONS/ DISCUSSION:
The IPSP is
intended to present a vision of Ontario’s
electricity future and the steps that must be taken today to make it a reality
in the near and longer term future. It
will map out changes to how electricity is made as well as consumed and will
include newer, cleaner and more
efficient technologies while providing a greater role for conservation and
renewable energy resources. The Plan
will cover the next 20 years through to 2027 and will be renewed every three
years to adapt to changing conditions, new information and emerging
technologies.
Below is a
summary of the key initiatives of the OPA’s Preliminary Plan that will be put
into place in the near, mid and longer term.
Near Term – 2008 – 2010
·
More
conservation programs
·
Hydro
electric resource development around the province
·
Increased
interconnection capability with Quebec
·
More
combined heat and power facilities
·
Coal
phase-out plan put into action
·
Urgently
needed natural gas generators, including those in northern York Region and
around Kitchener
·
Transmission
reinforcements in the GTA and Windsor-Essex
·
Also need
to make decision about what’s required in medium term – i.e., refurbishing
nuclear units at Pickering B, whether to buy power from other provinces under
long-term contracts
Mid-Term – 2011 – 2015
·
Complete
coal phase-out
·
Add more
renewables
·
Pursue
Pickering B refurbishment or alternative
·
Decide on
refurbishment of Darlington
·
Decide on
transmission upgrades for west of Sudbury,
south of Barrie
and Sudbury to
GTA
·
Decide on
a third supply line to Toronto
·
Decide on
wind developments for eastern Lake Superior,
eastern Lake Nipigon, Manitoulin Island
and the Bruce Peninsula
·
Decide on
renewable energy imports from neighbouring provinces
Long-Term – 2016 – 2027
·
Refurbish
or retire active nuclear units
·
Develop
hydroelectric projects in northern Ontario
as transmission permits
·
Continue
to evaluate changes in demand, technology and socio/economic contexts
As summarized in
an earlier Report to General Committee, General
Comments on Ontario’s Future Energy Supply Mix, April 3, 2006, the Town of
Markham has actively pursued and demonstrated a leadership role in Conservation
Demand Management by establishing the Markham Energy
Conservation Office (MECO) in partnership with PowerStream in
2005 and by investing in distributed generation and district energy technologies
through Markham District Energy Inc., a wholly owned company of the Corporation
of the Town of Markham that was created in 1999.
With respect to
high voltage transmission lines, the Town of Markham continues to strongly oppose a
transmission solution as demonstrated with the Markham-Aurora Hydro One Task
Force experience. As a rapidly growing area in Ontario, York Region has experienced an
electricity supply infrastructure shortage which has posed a long-standing and
contentious challenge, especially in Northern York Region. There are two main options for addressing
this problem: the construction of local
generation, or the upgrade of transmission capability to the Region to bring in
system generation that must be installed elsewhere. On September 27, 2005, Council resolved that
the Town of Markham continues to strongly support the preferred “integrated
solution” recommended by the OPA in their report, Northern York Region
Electricity Study, submitted to the Ontario Energy Board in September 2005
which was comprised of: demand reduction
across York Region; new transformer station capacity in northern York Region; and,
local generation in Northern York Region.
In the OPA’s Discussion
Paper #5: Transmission (November 13, 2006), the
recommended plan consists of the 3-pronged integrated solution. However, the document also indicates that: “In the event that a successful procurement contract
for local generation cannot be concluded, the alternative option is to upgrade
the line from the Buttonville Station to Gormley with a double-circuit 230 kV
line and build a transformer station at Gormley” (page 99). The Town of Markham does not support this
alternative. A transmission solution
does not need to be pursued at this time, and should not be pursued given the
extensive public opposition and the detrimental social, economic and
environmental impacts. There are many technical
and public policy reasons to favour a solution encompassing local generation
rather than transmission using generation elsewhere.
FINANCIAL
TEMPLATE: (external link)
There are no
direct financial implications for the Town of Markham.
However, the final IPSP approved by the Province will have an impact on
rates for the generation, transmission and distribution of electricity.
RECOMMENDED
BY: ________________________ ________________________
Viive Sawler, Manager, MECO Jim
Sales, Commissioner,
Community
& Fire Services
ATTACHMENTS:
Minister of
Energy’s Directive on Integrated Power System Plan, June 13, 2006.
Ontario’s Integrated Power System Plan – The Road Map for Ontario’s Electricity Future, Preliminary,
February 2007, OPA.
Ontario’s Integrated Power System Plan – Discussion Paper 5: Transmission, November 13, 2006, OPA. (Please refer to link: http://www.powerauthority.on.ca/ipsp/Storage/32/2716_DP5_Transmission.pdf)