Report to: General Committee                                                     Report Date: March 26, 2007

 

 

SUBJECT:                          Award of Tender 230-T-06

                                            Steeles Avenue Watermain Replacement (Phase 1)

                                            from Yonge Street to Henderson Avenue

PREPARED BY:               Jeff Flewelling, Acting Manager of Capital Right-of-Way

                                            Alex Moore, Senior Construction Buyer

 

RECOMMENDATION:

THAT the report entitled “Award of Tender 230-T-06 Steeles Avenue Watermain Replacement (Phase 1), from Yonge Street to Henderson Avenue” be received;

 

AND THAT the contract for tender 230-T-06 for the construction of the Steeles Avenue Watermain Replacement (Phase 1) be awarded to the lowest price qualified bidder, Sam Rabito Construction Ltd. in the amount of $1,279,809.54 exclusive of GST;

 

AND THAT a contingency in the amount of $127,980.00  exclusive of GST be established to cover any additional construction costs and that the Director of Asset Management be authorized to approve expenditure of this contingency amount up to the specified limit and to provide a monthly statement of these expenditures to the Town Treasurer;

 

AND THAT fees for the construction inspection and contract administration, to an upset limit of $94,600.00 exclusive of GST, be added to the existing Cole Engineering Group Ltd. purchase order D7 00045;

 

AND THAT a contingency amount of $9,460.00 exclusive of GST be established to cover any additional construction inspection and contract administration fees and that the Director of Asset Management be authorized to approve expenditure of this contingency amount up to the specified limit;

 

AND THAT the award be funded from the 2007 pre-approved Waterworks Department Capital Project 053-6150-7511-005 Watermain Construction/Replacement in the amount of $1,790,000.00;

 

AND THAT upon payment of all the invoices, any remaining funds will be returned to the original funding source;

 

And that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

Not applicable

 

FINANCIAL CONSIDERATIONS:

On February 13, 2007 Council approved the Waterworks Department Capital Project 053-6150-7511-005 Watermain Construction/Replacement for the construction of the Steeles Avenue watermain replacement from Yonge Street to Henderson Avenue.

 

The following table is a summary of the financial considerations for this report:

 

 

 

 

 

Original Budget and Account #

 

$1,790,000

 

053-6150-7511-005 Watermain Const/Repl

Current Budget Available (unspent)

 

$1,790,000

 

 

Less Cost

 

($1,374,410)

 

Awarded to Sam Rabito Construction/ Cole Engineering

Less Contingency

 

($137,440)

 

 

Budget Remaining

 

$278,150

 

 

Close upon final payment:

 

YES

 

 

 

 

 

 

 

 

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (Environmental, Accessibility, Engage 21st, Affected Units)             6. Attachment(s)

 

PURPOSE:

The purpose of this report is to award the contract for the construction of the Steeles Avenue Watermain Replacement (Phase 1), from Yonge Street to Henderson Avenue.

 

BACKGROUND:

The Town is proposing to replace the existing aging municipal watermain on Steeles Avenue East, from Yonge Street to Henderson Avenue with a new watermain.  This is one of the oldest watermains in the Town and it has experienced a high number of watermain breaks.  Therefore, it is necessary to replace this watermain in order to reduce the number of service disruptions to businesses and residences in the area. The tender documents issued by the Town stipulated a construction period of June 4, 2007 to September 28, 2007.

 

It is noted that Steeles Avenue Watermain Replacement (Phase 2) will involve Steeles Avenue from Henderson Avenue to Bayview Avenue.  It is intended that the design portion of this project will be carried out in 2007 pending the approval of funding in the 2007 budget for Waterworks.

 

Both the Phase 1 and Phase 2 projects are part of the Waterworks Department’s on-going watermain improvement program to systematically replace and upgrade deficient water mains to improve supply capacity and reliability.

 

In October 2005, Staff awarded RFP 171-R-05 for the design portion of the Steeles Avenue Watermain Replacement (Phase 1) to Mitchell Hatt & Associates.  This company has merged recently with Cole Engineering Group Ltd.

 

In the RFP, staff also requested prices for construction inspection and contract administration, but did not award that portion of the work. It is the opinion of Staff, that the company’s performance on the design portion of the project was acceptable.  Therefore, it is recommended that the construction inspection and contract administration portion of the project be awarded to Cole Engineering Group Ltd.

 

Staff has since requested and received confirmation that Cole Engineering will maintain the same 2005 prices submitted in this RPP for completion of this project

 

BID INFORMATION

Advertised

ETN

Bids closed on

February 23, 2007

Number of contractors picking up bid documents

27

Number of contractors responding to bid

15

DETAILED PRICING INFORMATION:

Company

      Total  *

Sam Rabito Construction Ltd.

                $1,279,809.54

Dig Con International

                $1,396,196.00

FDM Contracting

                $1,414,735.00

C G Construction

                $1,441,610.00

Vipe Construction Ltd.

                $1,504,600.00

Finch Paving

                $1,514,952.00

Kenco Construction Ltd.

                $1,556,851.00

North Rock Group

                $1,678,939.12

FCM Construction

                $1,768,867.12

Comer Group Ltd.

                $1,779,300.00

Co-X-Co Construction Ltd.

                $1,803,275.00

Drain Star Contracting

                $1,836,830.00

Trisan  Construction

                $1,923,610.00

Memme Construction

                $1,981,656.06

Direct Underground

                $1,985,663.00

*Prices are exclusive of GST and have been verified for accuracy and compliance with the tender terms and conditions.

OPTIONS/ DISCUSSION:

None

 

FINANCIAL TEMPLATE: (external link)

See attached

 

ENVIRONMENTAL CONSIDERATIONS:

The proposed watermain replacement would reduce the number of watermain breaks, which would minimize the risk of water system contamination.

 

ACCESSIBILITY CONSIDERATIONS:

None

 

ENGAGE 21ST CONSIDERATIONS:

The proposed watermain replacement supports the corporate goal related to infrastructure management, which is “to build, renew and strategically manage the Town’s infrastructure to meet the demands and expectations of a growing community”.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Finance Department has reviewed this report and their comments have been incorporated.

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                      Steve Andrews, P. Eng.                      Jim Sales, Commissioner,

                                      Director, Asset Management   Community and Fire Services

                           

                         

                                               

 

ATTACHMENTS:

None

 

 

 

Q:\Commission Share\Operations and Asset Management\Reports\2007\Asset Management\Award of tender 230-T-06.doc