Report to: General Committee Report
Date:
SUBJECT: Award of Tender
PREPARED BY: Jeff Flewelling, Acting Manager of Capital Right-of-Way
Alex Moore, Senior Construction Buyer
RECOMMENDATION:
THAT the report entitled “Award of Tender
231-T-06 Reesor Road Bridge Replacement Over Little Rouge River” be received;
AND THAT Tender 231-T-06 Replacement of Reesor Road Bridge Over Little
Rouge River be awarded to the lowest priced bidder, Dufferin Construction
Company in the amount of $2,298,156.00, exclusive of GST;
AND THAT a contingency
in the amount of $114,908.00, exclusive of GST,
be established to cover any additional construction costs and that the
Director of Asset Management be authorized to approve expenditure of this
contingency amount up to the specified limit and to provide a monthly statement
of these expenditures to the Town Treasurer;
AND THAT
the award be funded from the 2007
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not required.
The 2007 Capital Works project #7454 – Bridges and Culverts Improvement Project included a budget of $2,428,200.00 for the Reesor Road Bridge Replacement. This award is within the allotted budget for this project
The following
table is a summary of the financial considerations for this report: |
||||
Original Budget and Account # |
|
$3,348,200 |
|
|
Current Budget Available (unspent) |
|
$3,348,200 |
|
|
Less Cost |
|
($2,298,156) |
|
Awarded
to Dufferin Construction Company |
Less Contingency |
|
($114,908) |
|
|
Budget Remaining |
|
$935,136 |
|
|
Close upon final
payment: |
|
NO |
|
|
The remaining balance will be used for
other projects identified in the 2007
1. Purpose 2. Background 3. Discussion 4. Financial
5. Others
(Environmental, Accessibility, Engage 21st, Affected Units) 6.
Attachment(s)
The purpose of this report is to award the
contract for the replacement of the bridge on
The Town is proposing
to replace the bridge on
On
The Town’s 2006 Capital Budget for the construction portion of this project was $1,550,000.00, which was based on a cost estimate prepared by Chisholm, Fleming and Associates who are the Town’s consulting engineers for the project. Based on the lowest price of the two bids there was a budget shortfall of $449,537.00. Accordingly, the report recommended that the project be deferred to 2007 and retendered in 2007 with the award contingent on the approval of the 2007 Capital Budget.
The lowest bid received, excluding contingencies, when the project was retendered was $2,298,156.00. The 2007 budget for Capital Works project #7454 - Bridges and Culverts Improvement Project has been revised to include $2,428,200.00 for all construction costs associated with the Reesor Road Bridge Replacement. The consulting engineers, Chisholm, Fleming and Associates, believe that the higher than anticipated prices are attributable to current market conditions with respect to the bridge construction industry and the supply of the necessary construction materials.
It is the opinion of staff that a very competitive tendering process has been carried out, based on the number of bids received and the variance in pricing of the top six submissions.
The tender
documents issued by the Town stipulated a construction period of
Advertised |
ETN |
Bids closed on |
|
Number of contractors
picking up bid documents |
28 |
Number of contractors
responding to bid |
7 |
DETAILED PRICING INFORMATION:
Company |
Total |
Dufferin Construction
Company |
$2,298,156.00 |
|
$2,372,940.00 |
Brennan
Paving & Construction Ltd. |
$2,395,689.67 |
Bob
Hendricksen Construction Limited |
$2,555,820.00 |
Dagmar
Construction Inc. |
$2,620,115.49 |
Anscon Contracting Inc. |
$2,675,801.85 |
Elirpa Construction & Materials Ltd. |
$2,974,317.79 |
See attached
The proposed bridge replacement would increase the level of safety for vehicle and pedestrian traffic.
The existing bridge does not have any pedestrian sidewalks. The proposed bridge would have a sidewalk on each side, which would greatly improve accessibility.
The proposed bridge replacement supports the corporate goal related to infrastructure management, which is “to build, renew and strategically manage the Town’s infrastructure to meet the demands and expectations of a growing community”.
The Finance Department has reviewed this report and their comments have been incorporated.
RECOMMENDED
BY: ________________________ ________________________
Steve Andrews, P. Eng. Jim Sales, Commissioner,
Director, Asset Management Community and Fire Services
Attachment “A” – Key Plan