Report to: General Committee                                                        Report Date: April 17, 2007

 

 

SUBJECT:                          East Markham Community Centre and Library – Review of Options for Scope and Location

PREPARED BY:               Alan Seabrooke, Director of Strategic Services

                                            Catherine M. Conrad, Town Solicitor

                                            Barb Cribbett, Treasurer                  

                                            Valerie Shuttleworth, Director of Planning and Urban Design

                                            Meg West, Manager Strategic Initiatives

 

 

RECOMMENDATION:

That the report entitled “East Markham Community Centre and Library – Review of Options for Scope and Location” be received;

 

And that the staff presentation dated April 23rd be received;

 

And that the following recommendations be considered by General Committee at their May 7th meeting:

  • That Option 1A as set out in the report be approved;

 

  • And that the Mayor and Clerk be authorized to execute a Memorandum of Understanding with Markham Stouffville Hospital with respect to land acquisition, design, construction and operating arrangements for the Town’s future East Markham Community Centre and Library and the Hospital’s proposed Health and Wellness facility, on a joint development site, in a form satisfactory to the Chief Administrative Officer and the Town Solicitor.

 

And that Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

This report analyzes three options for the location of the East Markham Community Centre and Library, including the east and west sides of Bur Oak. 

·        Option 1A – Community Centre and Library, integrated with the Hospital’s Health and Wellness Centre, on the west side of Bur Oak.

·        Option 1B – as above plus parking structure on hospital property 

·        Option 2A – Community Centre, Library and two arenas on the east side of Bur Oak.

·        Option 2B – as above plus one sports field

·        Option 2C – same as Option 1A above, located on the east, not west, side of Bur Oak.

·        Option 3A – As in Option 1A, plus 7 acres on the east side of Bur Oak for future arenas.

·        Option 3B – As in Option 3A, plus one sports field.

 

In addition, the report identifies that while any of the Options can be accommodated by the existing DC revenue projections, there will be a significant impact on the DC revenues available to construct the second community centre identified by the Parks, Recreation and Library Master Plan, in the South East.  That community centre will have to be significantly reduced in size or partially funded from tax revenue.

 

Option 1A is recommended by staff:

·        The partnership with the Hospital will deliver a wellness hub that will improve service to the community in responding to changing demographics and enhance the programming provided at both the Wellness Centre and the Community Centre;

·        It is supportive of the Cornell Centre vision, transit supportive densities and new urbanism principles;

·        It is the most cost effective for the establishment of a district heating and cooling system; and

·        It is the most cost effective in terms of land costs in the short to medium term, with access to surface parking at little or no cost, located on the Hospital grounds.

 

FINANCIAL CONSIDERATIONS:

The seven options being described in this report are summarized below.

 

Note:  checkmark indicates that the facility is included in the Option

 

Capital Costs

The estimated cost to acquire land, construct and furnish the East Markham Community Centre and Library in each of these options is outlined below.

 

 

Funding

In each of the options, the estimated cost would be funded 90% from Development Charges and 10% from Non-Development Charge sources with the exception of the land required for the sports field.  The Development Charges Act does not allow for the collection of development charges to fund the acquisition of parkland.  The table below summarizes the funding for this project.

 

 

There are projected to be sufficient funds in the development charge reserves to support the construction of the East Markham Community Centre and Library and to support the sports field in any of the six options above.  The reserve established to fund the 10% non development charge component of capital projects only has sufficient funds to support Option 1A.  All other options would require funding from other non development charge sources.   As discussed further in this report, the development charge funding available for recreation and library purposes is limited.  The option chosen will result in a different balance of funds available future recreation and library facilities within the urban boundary.

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (Environmental, Accessibility, Engage 21st, Affected Units)             6. Attachment(s)

 

PURPOSE:


The purpose of this report is to present options for the scope and location of East Markham Community Centre and Library.

 

BACKGROUND:

Parks, Recreation, Culture & Library Master Plan

In 1997, the Town initiated the first Recreation, Culture & Library Facility Master Plan which was completed in 1999.  This plan was then updated in 2003 and expanded to include a parks and outdoor facilities section.  The Master Plan includes an analysis of the demand for indoor and outdoor recreation opportunities and libraries across the Town.  The timing of the delivery of facilities and services is based on population projections to meet the demands of growth.  The 1999 and the 2003 updated Master Plan identified the need for an East Markham CC & Library.  Specifically, the most recent plan identified the need in the short term planning horizon (2005 – 2010).  This major, multi-purpose facility would include the following amenities:  enhanced (larger) indoor pool, enhanced and larger fitness area, gymnasium, program space, youth and senior space and a library. These amenities will provide an enhanced level of service for families and individuals and it will also provide an enhanced level of service to our aging residents.

 

 

 

 


Report to General Committee                                                                             Report Date: April 17, 2007

Page 4

 

 

 

A second major multi-purpose recreation facility and library is also identified in the medium term planning horizon (2011 – 2016), for which land has already been purchased in southeast Markham.  The Town purchased 28.4 acres of land from Costco in September, 2005, for approximately $9 million.  The Master Plan contemplates that this facility will include some combination of the following amenities; indoor pool, fitness area, gymnasium, program space, youth and senior space, arenas and a library.  The final decision on the combination and size of amenities is to be determined during the preliminary planning process, based on circumstances, opportunities and costs and benefits presented by various delivery options. 

 

Arenas

It should be noted that arenas, in particular, are analyzed in terms of provision on a town-wide population basis not specific to a community or neighborhood.  The current provision standard for arenas is 1 pad per 27,000 population and based on projected population, there is an identified need for one double pad arena to the year 2021. 

Since the completion of the Master Plan, an opportunity to provide indoor arena facilities has surfaced through the Canadian Sports Institute.  The outcome of this opportunity, which is being investigated and will be the subject of a future report to Council, may impact future decisions on the components of the proposed Southeast Community Centre.  Specifically, if the Canadian Sports Institute goes ahead, with its planned complement of four (4) arenas, the Town’s access to two of those arenas would satisfy all of the Town’s arena demand to 2021.

 

Aquatics

The planned aquatics components have been enhanced for the East Markham Community Centre & Library.  Specifically, the facility will accommodate a 25 metre 8 lane competition pool and will feature several aquatic playground “fun” elements (eg. Slide, splash area, spray features), a therapeutic pool, teaching pool and associated support areas such as change rooms, storage, viewing etc.

 

With respect to the therapeutic pool, this will be one of the facilities of most benefit for rehabilitation and therapeutic programming, for the hospital’s patients. The design of this component will be done in a manner that will satisfy all stakeholders, through the public consultation process. In any case, the patients who would use this and other community centre facilities will be screened by the hospital and are individuals that have been discharged and are home or back to work. These individuals are encouraged to begin an exercise/rehabilitation regime in programs to be held in the community centre. The therapeutic pool is also an important element for the Town’s programming, as demonstrated by the success and high usage experienced following the Thornhill Community Centre fitness project expansion.

 

Library

The library model for the Town provides for one large research library in each of the four Parks, Recreation, Culture and Library Planning Areas: Thornhill (Area C), Angus Glen (Area A), Markham Village (Area B) and Milliken (not approved yet) (Area D).  All other branches are community-sized at 20,000 sq. ft. or less.

 

 

 

In September 2001, the Finance Department presented to Council an analysis of Development Charge funding for libraries, it was determined that funding was available for only 50,000 sq. ft. of library space in the Central West (Area A) and Central East (Area B) areas of Markham.  In September 2001, the Library Board presented its service rationale for constructing a 29,700 sq. ft. Angus Glen Library to the Finance and Administrative Committee.

 

Council approved a motion that “the Library facility at Angus Glen be 29,700 sq. ft. and that the East Markham Library be reduced to 20,000 sq. ft. due to its likely proximity to an expanded Markham Community Library”. This adjustment to the 1999 Master Plan facility recommendations was carried forward into subsequent planning.

The Budget Subcommittee of Council approved the Library’s building program of 66,800 sq. ft. of additional space, composed of the following:

 

  • Angus Glen Library 30,000 sq. ft.
  • Expansion of Markham Village Library 10,500 sq. ft.
  • Expansion of Milliken Mills Library 6,300 sq. ft.
  • East Markham Library 20,000 sq. ft.

 

Recognizing a $5.1 million shortfall in the Library’s Building Program, the Budget Subcommittee of Council recommended a new $510,000/year budget allocation commencing with the 2003 Operating Budget to be set aside for 10 years to fund the $5.1 million not recoverable from Development Charges.

 

Twenty thousand sq. ft. of library space has been allocated for Central East Markham in the recommendations of the draft Parks, Recreation, Culture & Library Master Plan 2005 – 2021. 

 

The Markham Public Libraries Board endorsed 20,000 sq. ft. for the library in Central East Markham on May 17, 2004, as part of a motion endorsing a Library Development Strategy based on community need, as listed in the following table:

 

Service Area

    Project

 

Proposed expansion/

new facility

Total Sq. ft.

A

Angus Glen

 

29,516

A

Unionville

 

13,640

B

Markham Village

10,500

31,361

B

Cornell (proposed)

20,000

20,000

C

Thornhill Community

 

25,053

C

Thornhill Village

 

4,283

D

Milliken

6,300

23,165

D

Southeast (14th/48) (proposed)

20,000

20,000

 

In endorsing this Strategy, the Board strove for an equitable distribution of library space across the Town within the context of limited funding available. 

 

When the expanded Markham Village Library opens next year, the service level for Service Area B will be approximately 0.53 sq. ft. per capita, above the 2007 average for the Town of Markham as a whole at 0.45 sq. ft. per capita. 

 

If a 20,000 sq. ft. Library in Cornell opens in 2009 (projected), it will raise the Area B service level for library space to well above the Town service level target of 0.6 sq. ft. per capita.  The population estimates for Area B have been adjusted to reflect the increased projected population estimates for Cornell. 

Sports fields/Outdoor recreation facilities

With respect to parks and outdoor recreation facilities, the Master Plan recommends service provision standards not only for passive parkland, but facilities such as baseball diamonds, basketball courts, cricket, skateboard parks, soccer fields, tennis courts, playgrounds and splash pads.  The following amenities are planned in conjunction with Town owned parkland in Cornell.  Additional facilities on school board sites will also be available.

 

EXISTING FACILITIES

ADDITIONAL PROPOSED FACILITIES

TOTAL FACILITIES PLANNED

3 soccer (2 major and 1 minor)

5 soccer (3 major, 2 minor)

8 soccer

2 waterplay features

2 waterplay features

4 waterplay features

5 playgrounds (plus one stand alone swings)

13 playgrounds

18 playgrounds

 

4 public tennis courts

4 public tennis courts

 

1 half basketball court

1 half basketball court

 

2 secondary school sport fields

2 secondary school sport fields

 

Other communities in the OPA 5 area have included some woodlands and buffer areas as part of their minimum parkland dedication requirement, while in Cornell woodlots are coming into Town ownership in addition to parkland, which has effectively increased the amount of tableland and parkland available for active and passive recreation within Cornell. 

 

The Cornell Community, based on the principles of New Urbanism, is oriented towards people – not cars – with narrower streets, rear lanes and public amenities, generally, within a 5 minute walking distance. Cornell’s interconnected network of streets, parks, and outdoor amenities all contribute to a functional, attractive, safe and pedestrian-friendly public realm. The size, location, and diversity of Cornell’s parks and open spaces contribute greatly to its unique community character, quality of life and overall livability. Consistent with the tenets of new urbanism, Cornell’s enhanced public realm provides for a wide range of connected parks, parkettes, open spaces and natural areas to ensure that each residential neighborhood is cohesive and walkable while at the same time accommodating both passive and active recreation needs.

 

Overall Cornell parkland per population

The draft revised Cornell Secondary Plan increases the population in Cornell from approximately 30,000 persons in 10,000 units to approximately 40,000 persons in 16,000 units.  In May of 2006, Council received a report entitled “Cornell Parkland Dedication Agreement” and endorsed execution of a parkland dedication agreement with the Cornell Developers Group.  The lands to be secured though that agreement are outlined in the table below.

 

 

Parkland / Open Space

Parkland  to be dedicated (includes 2.5 acres for Commercial/Industrial uses)

106.58 acres

Parkland credited through School Site Agreement

  20.00 acres

Woodlot trail lands

    9.23 acres

$650,000.00 infrastructure in lieu of Land

    1.69 acres

Sub-total

137.5 acres

Urban Open Spaces

   6.0 acres

Golden Jubilee Greenway

   6.4 acres

Woodlot and Woodlot Buffer Lands

41.97 acres

Woodlot Expansion Lands

29.66 acres

Cornell Grand Total

     221.53 acres

 

The above dedications will result in 6.94 acres of parkland per 1000 population, based on a population of 32,000 (projection based on current Secondary Plan).  With an increase in population arising from the revised draft Secondary Plan (including Cornell Centre) to 40,000, even without any additional dedications discussed below, the rate will be in the order of 5.54 acres/1000 population.

 

Following Council’s approval of the parks agreement, some residents expressed concern that the parkland to be provided has not been increased in proportion to the additional Cornell Centre population.  Staff then spent a great deal of time with the Cornell Advisory Group reviewing and explaining:

  • Parkland dedication requirements,
  • Planning Act authority to require dedication of land for park;
  • Options regarding collection of cash-in-lieu of parkland; and
  • Previous parkland agreements with prior landowners. 

 

As a result of these discussions and review, staff recommended additional terms for inclusion in the parks agreement.  These additional terms provide for not only cash in lieu of parkland for increased population in the Highway 7 Corridor, but also the option provision of additional parkland or open space facilities. The anticipated rate of cash-in-lieu could equate to another 23 acres of parkland (based on an approximate land value of $500K per acre).  Alternatively, the Town, in consultation with the Cornell residents and developers, will have the option, for example, of having a developer pay for or construct a feature (eg. pedestrian bridge, waterplay, tennis court, gazebo etc.) in an existing park and receive a credit against cash in lieu of parkland owing.  Implementation of this agreement will deliver additional parkland in the Highway 7 corridor or provide additional cash in lieu of parkland which could be used to purchase additional parkland or enhance existing parkland within Cornell. The developers group has agreed to these terms.  Council has authorized the execution of the agreement.

 

It is important to note that other OPA 5 communities are provided parkland at a maximum rate of approximately 4 acres per 1000 population.  Further, the Town’s parkland dedication by-law requires approximately 3 acres per 1000 population.  By comparison, at either 6.94 or 5.54 per 1000 population, Cornell will be better served with parks and open space than any other community in Markham.

 

Markham Stouffville Hospital Wellness Centre

 

On September 20, 2004, Council endorsed in principle the concept of integrating the East Markham Community Centre and Library with the Markham Stouffville Hospital site campus and partnering with the Hospital for the development and operation of the community centre. The staff report indicated that the two organizations share many common goals and the integrated Community Centre/Health and Wellness building represented an innovative model of service provision.  Staff were directed at that meeting, to enter into negotiations with the Hospital to develop the partnership.

 

On June 14, 2005, staff reported to Council on the approvals obtained by the Hospital and the emerging details of the proposal, including a conceptual site plan.  The report outlined the benefits to Markham and Council again endorsed the concept of the integrated facility and directed staff to bring back Principles of an Understanding between the Town and the Hospital as a basis for entering into a land, design, construction and operating agreement.

 

On June 12, 2006, Council authorized the execution of a Memorandum of Understanding with the Hospital and Markham District Energy Inc., with respect to the evaluation of the technical and commercial benefits of the supply of district heating and cooling to the Markham Stouffville Hospital campus, including the proposed East Markham Community Centre and Library.

 

On January 15, 2007,  staff reported to General Committee on the details of a Memorandum of Understanding with the Hospital dealing with land acquisition, site planning and facility design, shared use of facilities, parking and district heating and cooling.  The Committee deferred consideration of the report pending additional information to be provided at a work session.

 

On February 27, 2007, staff presented the project to a work session of Council.  Staff was directed to report back to General Committee and outline different options for delivering the Community Centre and Library in the Cornell Community.

 

FINANCIAL BACKGROUND

The development charge background study identified the construction of one new community centre and library  (approx. 157,000 sq ft) in the ten year period 2004 to 2013, and sufficient revenues are forecasted to construct another new community centre and library (approx 149,000 sq ft) in the period of 2014 to 2021. 

 

Recreation

As outlined in the chart below, the current balance in the development charge reserve for Recreation is approximately $17.6M, and the forecasted revenues to 2021 are $68.9M.  The total projected funding available for the acquisition of land, construction, and furnishings to 2021, is therefore approximately $86.5M for Recreation Services. 

 

Library

As outlined in the chart below, the current development charge reserve balance for Library is approximately $-0.6M, and the forecasted revenues to 2021 are $17.1M.  In addition, Council made a commitment to provide additional funding of $5.1M to the Library capital program from non development charge sources.  This commitment was made in conjunction with the decision to oversize the Angus Glen Community Centre Library to 30,000 square feet. It is therefore forecasted that $21.6M will be available for the acquisition of land, construction and furnishings of library facilities to 2021.

 

 

Financial Background Summary

The land acquisition decision directly impacts the funding available for the construction and furnishing of this community centre, and any future facilities for recreation and/or library purposes, within the current urban boundary.  As discussions pertaining to the South East Community Centre and the Canadian Sports Institute continue, the limitations of development charge funding must be clearly identified and understood.   The financial implications of each of the options described in this report will detail the “projected square footage remaining”.  To place this into context, the chart below outlines the approximate square footage, per amenity, within a community centre.

 

 

The estimated square footage of recreation and library space included in the options below represents the development charge funding available based on current service levels.   Any additional square footage may result in an increased service level and would require funding from non development charge sources.   

 

 

OPTIONS/ DISCUSSION:

Staff has identified three options for delivering the East Markham Community Centre and Library in Cornell Centre.  The three options evaluate the need and opportunity to provide additional facilities, over and above the planned community centre and library and the options also evaluate opportunities to locate the facilities on the east or west side of Bur Oak Avenue in the Cornell Community.  The options are outlined below.  In evaluating the various options, the following assumptions with respect to land requirements were utilized:

 

Acreage Requirements to Deliver Various Facilities:

 

1.

Community Centre & Library With Surface Parking/Future Parking Structure on Hospital Property

7.5 acres

2.

Community Centre & Library With Parking on Town Owned Land

9.2 acres

3.

Community Centre & Library With Parking & Twin Pad Arena

14.5 acres

4.

Community Centre & Library With Parking & Twin Pad Arena & 1 Sports Field

16.2 acres

5

Community Centre & Library With Parking & Twin Pad Arena & 2 Sports Fields

18 acres

 

The lands required to implement the options described below and estimates of the land acquisition costs for each option are as set out in the chart below.  Land values on the west side of Bur Oak are influenced by their inferior size and configuration, the status of the Mattamy lands as remnant parcels,  and the proposed exchanged for the Town owned lands at 16th Avenue and Old Markham By-pass.  The estimated land costs on the east side of Bur Oak, while not discussed with Mattamy, have a higher value due to their designation for medium density development, superior development characteristics and potentially higher Developer Cost Sharing obligations.

 

 

East Markham Community Centre & Library

 

Option 1A

 

Option 1B

Option 2A

 

Option 2B

 

Option 2C

Option 3A

 

Option 3B

Land required

9.2 ac

7.5 ac

14.5 ac

16.2 ac

9.2 ac

9.2ac (west) + 7.0 ac (east)

7.5(west)

+ 8.7 ac (east)

Cost

$5.1M

$4.1M

$10.5M

11.7M

$6.6M

$10.1M

$10.4M

 

Option 1 – Continue to pursue partnership with Markham Stouffville Hospital, locating the community centre & library on the west side of Bur Oak

The Town and the Hospital have established a Steering Committee which meets regularly and which has developed a series of principles which guide each of the Town and the Hospital in their pursuit of an integrated complex comprising of a Community Centre, Library and Wellness Centre.  This option provides for a “Health and Wellness Hub” and allows for one-stop shopping for the community and visitors i.e. combine a visit to the doctor or hospital with exercise class, library visit, pharmacy pick-up etc.  The campus will be an access point for services where people choose to come for outstanding health care and pursue healthy living.  The complex provides a model for health and wellness services in Markham and other Canadian communities.  The integration of the facilities will increase usage of the community centre facilities during traditionally low volume daytime operating hours, maximizing revenues and cost recoveries.

 

Option 1A includes the EMCCL on the west side of Bur Oak, with surface parking on 1.7 acres.  Option 1A assumes, for the financial analysis, that the Town would have to purchase lands for the location of the interim surface parking solution from the hospital.  Option 1B includes the EMCCL also on the west side of Bur Oak, but with the Town’s contribution to the construction cost of the parking structure on hospital lands, rather than the surface parking solution.  The Town will contribute only its proportionate share of the cost of constructing the parking garage ie the Town will pay for 300 of the 800 spaces that may be constructed in the parking structure.

 

Attachment 1 outlines the conceptual location of the Health and Wellness facility and the East Markham Community Centre and Library on the west side of Bur Oak Avenue.  Option 1A is the recommended option for the reasons set out below.  The Town will own the lands on which its community centre and library, and if necessary, the surface parking lands, will be located. The Hospital will own the balance of the lands west of Bur Oak, including the structured parking site.

 

The integration of the Health and Wellness building and the Community Centre and Library allows for the potential sharing of facilities and synergies.

These include food services (café), medical library, meeting rooms, parking, outdoor amenity space, IT support, multi-purpose rooms, exercise programs, fitness centre, pool and hydrotherapy pool.

 

Reduced land required to locate on the Hospital Campus

The land required to locate the community centre and library on the site in association with the hospital would be approximately 7.5 acres.  An additional 1.7 acres could be leased, or if necessary, purchased from the hospital to locate the interim surface parking of approximately 275 to 300 spaces.  Economies of shared facilities and services reduces the land requirements for each component.  Town staff have been negotiating with the owners of the lands required to accommodate Options 1A or 1B and are ready to report on a recommendation for the acquisition of the Mattamy lands and are close to finalizing the terms of an agreement with the other landowner.  Acquisition of the lands can occur quickly, to facilitate design and construction in a timely manner.

 

Allows for more efficient use of resources with respect to land, space, services, capital costs, operating costs, library and meeting rooms. 

Access to shared facilities and services and enhanced use of facilities by the on-site population provides incremental efficiencies to operating costs over time.  There are opportunities for additional programming in conjunction with the Health and Wellness Facility and for additional usage of the community centre facilities for hospital employees during the traditionally low volume day time operating hours.   Facilitating hospital patrons, visitors and employees using the facility during the day when traditionally the community centre use is low maximizes use and revenue and creates additional revenue/cost recovery.  The shift work nature of the hospital staff further provides the potential for extended hours of use with increased demand.

 

The partnership with medical library expertise will improve public access to the best health and wellness information and provides an opportunity to move the library’s health and wellness services to a higher level.  It will improve the library’s role in helping the community to be well informed on health and wellness issues by developing an outstanding health and wellness collection and providing electronic access to high quality health and wellness information 24x7. The MOU to be executed with the Hospital requires the Town and Hospital to enter into agreements for sharing capital and operating expenses of the library and other facilities within the community centre, based on usage.  For instance, the hospital will pay its share of the capital cost of constructing the library (the medical library will be an additional 3,000 sq. ft over and above the 20,000 sq. ft. for the Town’s library) and will pay for its circulation material and the cost of the staff person for the medical library.

 

Opportunity for Markham District Energy

Option 1 provides the best opportunity and a focal point to establish a district heating and cooling system within Cornell, taking advantage of the density, compact urban form and the existing hospital Central Utility Plant (“CUP”).  Some preliminary investigation has been undertaken with respect to the opportunity to use a district energy system to provide heating and cooling to the site and other areas of Cornell.  The existing CUP could be used to:

·            Heat and cool the existing hospital facility and all the future planned expansions;

·            Heat and cool the community centre and library;

·            Heat and cool the adjacent Wellness Centre; and

·            Create a new and viable district energy system in Cornell Centre.

 

A catalyst for structured parking

This option allows for surface parking of approximately 300 spaces to be located in close proximity to the community centre but on the hospital land.  It also facilitates the future provision of a parking structure to serve all of the Markham Stouffville Hospital, the Health and Wellness facility and the Community Centre and Library.

 

Contributes to the Cornell Centre Vision – Lead by Example

The integration of the facilities supports the Town’s policies to promote compact urban form, transit supportive densities and new urbanism principles.  The facility will be located adjacent to Cornell’s main corridor, Bur Oak Avenue, and will provide an urban edge to Bur Oak which is compatible with the emerging Cornell Centre Vision.  Limited surface parking and/or parking in structures will support transit use and enhance the visual presence of the Centre.

 

Provides a unique partnership opportunity

This option provides an opportunity to partner with Markham Stouffville Hospital and demonstrates our leadership in the area of community partnerships and commitment to healthy communities.  The two partners on the campus complement each other in serving a wide range of health and wellness needs across a large and diverse community.

 

 

 

Option 1 Financial Implications

The table below illustrates the financial impact of acquiring 9.2 acres of land in Option 1A and 7.5 acres of land in Option 1B, and constructing a 120,000 square foot Community Centre.

 

 

If Option 1A is approved, sufficient development charge funds should be available for the construction of slightly more than one additional library (26,000 sq. ft) and one community centre (approx. 185,000 sq. ft) for the proposed South East Community Centre off Highway 48.  The cost of purchasing the 1.7 acres for surface parking has been included in the financial analysis of both Options 1A and 3A. 

 

With discussions continuing pertaining to the Canadian Sports Institute and a South East Community Centre, Option 1A has the least impact on the funding available for these two future sites, from a development charge perspective.

 

In the event that Council decided to approve the construction of a 185,000 square foot community centre in the South East, the square footage (16,000) over and above the 169,000 available as set out above, after Option 1B is implemented, would have to be financed from tax revenue at a cost of approximately $4.8M.

 

 

Option 1A Conclusions (Surface Parking on Hospital Property)

This is the recommended option for the following reasons:

·        The partnership with the Hospital will deliver a wellness hub that will improve service to the community in responding to changing demographics and enhance the programming provided at both the Wellness Centre and the Community Centre;

·        It is supportive of the Cornell Centre vision, transit supportive densities and new urbanism principles;

·        It is the most cost effective for the establishment of a district heating and cooling system; and

·        It is the most cost effective in terms of land costs n the short to medium term, with access to surface parking at little or no cost, located on the Hospital grounds.

·        land acquisition can be finalized in the very near future;

·        This option facilitates moving into Option 1B with the parking structure; and

·        the service standards for parkland and outdoor recreational facilities are met or exceeded without additional facilities in Cornell;

 

Option 1B Conclusions (Parking Structure on Hospital Property)

The parking structure is a long term option for the Hospital/Community Centre and Library campus.  The Town would likely only contribute to the capital cost of the facility based on the number of parking spaces required by the EMCCL, (300 spaces @ $25K each, approximately $7.5M). In that event, the Town would likely lease the parking lands in the interim from the Hospital.

 

Option 2 – Locate the community centre and library on the east side of Bur Oak and add two arenas

Attachment 2 outlines a conceptual location of the East Markham Community Centre and Library on the east side of Bur Oak Avenue.  Option 2A is shown on Attachment 2, incorporating the community centre, library, parking, two arenas and landscaped space.  A financial analysis for Option 2B, which adds one sports field to Option 2A, requiring 16.2 acres, is set out below. 

 

Impact on the proposed Secondary Plan and Cornell Centre

Currently there is a 23 acre parcel of land on the east side of Bur Oak across from the hospital lands.  The Separate School Board has identified 15 acres of that site for a future secondary school site.  If the community centre and library and associated additional uses were to locate on the east side of Bur Oak, the implications are:

·                The Town requires at least 14.5 acres to accommodate Option 2. The block on the east side of Bur Oak is currently 23 acres and therefore, could not accommodate both the EMCCL and the secondary school, which requires 15 acres, unless the block is enlarged by changing the configuration of the road network in the area, which would necessarily impact on other landowners. 

·                Alternatively, another site would have to be found for the secondary school.

·                A traditional, stand alone community centre/library facility with associated surface parking is not in keeping with the Cornell Centre vision.

 

Service Levels Impacts for the South East Community Centre

Exceeding planned service levels by providing arenas at this location compromises the Town’s ability to provide the arenas within the time frame and in the location indicated by the Master Plan, the South East Community Centre. 

 

Markham District Energy System

Typically, two factors are required to economically launch a new district energy system: (1) a sizable anchor load and (2) a density of new buildings within a reasonable proximity of the proposed production plant.  Connecting the expanding MSH site to the East Markham Community Centre & Library becomes the anchor load in East Markham, and provides the necessary critical mass for a new system.  MDEI is of the view that (a) connecting the MSH facility and (b) utilization of the MSH existing plant are two critical factors that are necessary for the launch of a district energy system in East Markham.  Construction of the EMCC&L on the east side of Bur Oak could threaten the achievement of this goal. If the district energy system is viable in this scenario, the distribution costs to connect it will be higher with this option.  Estimates are that additional costs are in the range of $150,000 to $300,000, but could be higher.  There would be additional restoration costs due to the installation of the necessary infrastructure across Bur Oak.

 

Option 2 Financial Implications

The table below illustrates the financial impact of acquiring 14.5 acres of land, and constructing a 190,000 square foot Community Centre in Option 2A and #2B and the impact of acquiring 9.2 acres of land, and construction a 120,000 square foot Community Centre in Option 2C.

 

 

If Option 2A or B is approved, sufficient development charge funds should be available for the construction of slightly more than one additional library (approx. 24,000 sq. ft) and one community centre (approx. 109,000 sq. ft) for the proposed South East Community Centre.  In the event that Council decided to approve the construction of a 185,000 square foot community centre in the South East, the square footage (76,000) over and above the 109,000 available as set out above, after Option 2 #A or #B is implemented, would have to be financed from tax revenue at a cost of $22.8M.

 

If Option 2C is approved, sufficient development charge funds should be available for the construction of slightly more than one additional library (approx. 26,000 sq. ft) and one community centre (approx. 182,000 sq. ft) for the proposed South East Community Centre.  In the event that Council decided to approve the construction of a 185,000 square foot community centre in the South East, the square footage (3,000) over and above the 182,000 available as set out above, after Option 2 #C is implemented, would have to be financed from tax revenue at a cost of $0.9M.

 

Option 2B includes land required for a sports field.  The chart above does not include the cost of acquiring the additional 1.7 acres required for the sports field as the Development Charges Act does not allow for the collection of development charges to fund the acquisition of parkland.  These costs could be funded from the Cash-in-lieu of parkland reserve.  The chart below summarizes the total cost of Option 2B and the potential funding.

 

 

 

Option 2 Conclusions:

This option is not recommended as:

  • Options 2A and 2B are more costly than Option 1A, adding approximately $5.4-$7.6M to the land acquisition costs;
  • Funding available for additional library and community centres is significantly reduced, impacting the size of those additional facilities (reducing the 177,000 square foot community centre to an 89,000 square foot community centre)
  • There have been no negotiations for the acquisition of lands on the east side of Bur Oak.  The negotiations will have to include the School Board, whose site will have to be relocated, or alternatively, there will have to be a significant redesign of the road pattern in the area, to achieve a larger block on the east side to accommodate both the Town’s facility and a secondary school.
  • It is anticipated that the move to the east side of Bur Oak will be opposed by the landowner. Negotiating the acquisition of 14.5 acres of developable land will take a considerable amount of time, delaying the design and construction of the facility to well beyond 2009.
  • Servicing by district heating and cooling will be more expensive;
  • Many of the synergies with the Hospital’s Health and Wellness Facility will be lost or reduced in scope;
  • There is no demand for additional rinks until approximately 2014;
  • Service levels for arenas will be exceeded if the CSIO were approved or if arenas were provided in the Southeast Community Centre; and
  • The school board will have to identify another site for its future secondary school or the road pattern in the area will have to be altered, to enlarge the block on the east side of Bur Oak significantly.

 

 

Option 3 – Locate the community centre and library on the west side of Bur Oak Avenue(as per Option 1) and acquire an area for future development of two arenas on the east side of Bur Oak Avenue

Attachment 3 outlines Option 3A, the conceptual location of the Health and Wellness facility and the East Markham Community Centre and Library on the west side of Bur Oak Avenue and two arenas and parking on the east side of Bur Oak Avenue. A financial analysis of Option 3B which adds one sports field to Option 3A, requiring 8.7 acres on the east side of Bur Oak, is set out below. 

 

This option does achieve the objectives for the planned components of the East Markham Community Center and Library while also providing additional land that keeps an option open for the future provision of arenas.

 

Impact on the proposed Secondary Plan and Cornell Centre

The site on the east side of Bur Oak is 23 acres of which the Separate School Board has identified 15 acres for a future secondary school.  That would leave 8 acres to accommodate arenas and/or outdoor fields and associate parking, if future needs dictate.  Under this option, the site is large enough to accommodate both 3A and the school board and their associated uses. Option 3B would require some amendment to the configuration of the Block or a reduction in the size of the secondary school site.

 

This option does not support the vision for Cornell Centre.  A stand alone facility set within a large surface parking lot is contrary to the principles of new urbanism, compact communities, and the transit supportive, pedestrian friendly development that Cornell, and Cornell Centre in particular, promotes.  If this approach is pursued, staff anticipates future difficulties in promoting these principles to the development industry, as the Town is no longer leading by example.

 

Markham District Energy system

This option combines Option 1, with the arenas from Option 2.  The cost of this Option, therefore, includes the costs and savings from Option 1 plus the added costs of the additional facility lands on the east side of Bur Oak.

 

Option 3 Financial Implications

The table below illustrates the financial impact of acquiring 16.2 acres of land for Option3A, and 14.5 acres of land for Option 3B, and constructing a 190,000 square foot Community Centre.  This option varies slightly from Option 2, due to the difference in the cost per acre of land between the east side ($550,000/acre) and west side ($725,000/acre) of Bur Oak.

 

 

If Option 3A is approved, sufficient development charge funds should be available for the construction of slightly more than one additional library (approx. 25,000 sq. ft) and one community centre (approx. 110,000 sq. ft).  In the event that Council decided to approve the construction of a185,000 square foot community centre in the South East, the square footage (75,000) over and above the 110,000 available as set out above, after Option 3A is implemented, would have to be financed from tax revenue at a cost of $22.5M.

 

If Option 3B is approved, sufficient development charge funds should be available for the construction of one additional library (approx. 22,000 sq. ft) and one community centre (approx. 93,000 sq. ft).  In the event that Council decided to approve the construction of a 185,000 square foot community centre in the South East, the square footage (92,000) over and above the 93,000 available as set out above, after Option 3B is implemented, would have to be financed from tax revenue at a cost of $27.6M.

 

Option 3B includes land required for a sports field.  The chart above does not include the cost of acquiring the additional 1.7 acres required for the sports field as the Development Charges Act does not allow for the collection of development charges to fund the acquisition of parkland.  These costs could be funded from the Cash-in-lieu of parkland reserve.  The chart below summarizes the total cost of Option 2B and the potential funding.

 

 

Option 3 Conclusions
This option is not recommended as:

  • Options 3A and 3B increase the land acquisition cost by approximately $5-6.3M to protect for future demand for arenas and sports fields, which may be satisfied by the CSIO proposal or in the alternative, at the Southeast Community Centre site, where sufficient lands have already been acquired to accommodate a variety of recreational uses, including arenas. 
  • There is no demand for additional rinks until approximately 2014;
  • Service levels for arenas will be exceeded if the CSIO is approved or if arenas are provided in the South East Community Centre;
  • The potential for delay in design and construction associated with Option 2 in particular is reduced with Option 3 although not eliminated with this option, as staff can proceed with the facility on the west side, while negotiating for the acquisition of the 7-8.7 acres on the east side of Bur Oak.

 

ENVIRONMENTAL CONSIDERATIONS:

The Town and the Hospital acknowledge the opportunity for environmentally friendly building design, energy consumption and product procurement in the development of the Facility in any of the option scenarios.

 

ACCESSIBILITY CONSIDERATIONS:

The Facility will be designed with regard to ensuring accessibility of its users in any of the option scenarios.

 

ENGAGE 21ST CONSIDERATIONS:

This project aligns with the following key Town of Markham Corporate Goals: Quality Community, Environmental Focus and Infrastructure Management.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Community and Fire Services, Development Services, Strategic Initiatives, and Corporate Services and Legal have been involved in the preparation of this report.

 

RECOMMENDED

                            BY:    ________________________

                                      Jim Baird, MCIP, RPP                      

                                      Commissioner of Development

                                      Services                                            

 

 

                                      ________________________          ________________________

                                      Jim Sales,                                           John Livey,

                                      Commissioner of Community              Chief Administrative Officer

                                      and Fire Services

 

ATTACHMENTS:

Attachment 1 – Option 1 Community Centre & Library on the MSH campus

Attachment 2 – Option 2 Community Centre, Library, parking and arenas on east side of Bur Oak Avenue

Attachment 3 – Option 3 Community Centre & Library on the MSH campus, arenas and parking on the east side of Bur Oak Avenue

Attachment 4 – Hospital Campus Parcel Mapping