Report to: Council Report
Date:
SUBJECT: Award
of Tender
PREPARED BY: Hossein Sharif, Extn 2382
Phoebe Fu, Extn 3010
Amit Sobti, Extn 2239
RECOMMENDATION:
THAT the
report entitled “Award of Tender #042-T-08 John Street Bridge
Superstructure Replacement over East Don River (B02)” be
received;
AND THAT
the contract for #042-T-08 John Street Bridge Superstructure Replacement be awarded to the lowest priced supplier, Marbridge
Construction Ltd, in the amount of $652,510.00, exclusive of contingency and
GST;
AND THAT a
contingency amount of $70, 751.00, exclusive of GST be established to cover any additional
construction and consultant costs and that the Director of Asset Management be
authorized to approve expenditure of this contingency amount up to the
specified limit in accordance with the Expenditure Control Policy;
AND THAT the contract with Totten Sims Hubicki be extended in accordance with
AND THAT the award be funded from the available budget of $
884,354.00 in 2008 Capital Budget account
058-6150-8289-005, John Street Bridge Superstructure Replacement.
AND THAT $58,100 of the remaining balance $106,093.70 in
account 058-6150-8289-005 be used for other project related activities as
identified under financial considerations. The anticipated savings of $47,993.70
will be returned to the original funding source;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
1. Purpose 2. Background 3. Discussion 4. Financial
5. Others (Environmental, Accessibility, Engage 21st, Affected Units) 6.
Attachment(s)
The purpose of this report is to
obtain the Council approval to award contract # 042-T-
The
On April 7, 2008 Town staff conducting routine bridge inspection and
pothole repair discovered severe winter damage that has made the bridge unsafe.
Based on the inspection conducted by a professional structural engineer
on April 9th, it was identified that extensive repair work will be
required to make the bridge safe to be re-opened to traffic. In consideration
of the planned replacement of the deck (originally scheduled to commence in
June), staff recommends that the road remain closed and proceed immediately
with the planned construction. Due to
the condition of the bridge and the immediate need for the replacement of the superstructure,
staff is requesting for Council to award the tender.
Marbridge Construction Ltd. submitted the lowest priced acceptable bid and was therefore recommended for the award. Marbridge Construction Ltd. has successfully completed various similar contracts in the past and staff have verified reference checks to ensure that they will provide satisfactory service that meets, if not exceeds the Town’s expectations.
Retaining of Consultant
Since
Totten Sims Hubicki (TSH) conducted the
Environmental Assessment and the Detail Design for this project, it is
recommended that the firm be retained to provide the site supervision and
contract administration services in accordance with
TSH posses’ significant knowledge of the bridge and it is important to ensure continuity from the design phase to the construction phase. TSH has provided a proposal for the contract administration based on 10 weeks of construction period and includes geotechnical consultant’s fee to carry out material testing. TSH has provided quality service to the Town in past bridge projects ad their estimate is comparable to industry rates for such services.
BID INFORMATION:
Advertised,
place and date |
ETN |
Bids
closed on |
|
Number
of contractors picking up bid documents |
19 |
Number
of contractors responding to bid |
10 |
DETAILED PRICING
INFORMATION:
Company |
Total Price, Excl GST |
Marbridge
Construction Ltd. |
$652,510.00 |
Belor Construction |
$726,543.00 |
Brennan Paving and Construction Ltd. |
$784,190.00 |
Bob Hendricksen Construction Limited. |
$797,681.00 |
G.C. Romano Sons ( |
$824,525.00 |
Anscon Contracting Inc. |
$845,497.18 |
Dagmar Construction Inc. |
$878,217.43 |
Bridgecon Construction Ltd. |
$885,000.00 |
Elirpa Construction & Materials Limited |
$895,831.99 |
Dufferin Construction Company |
$1,060,450.00 |
The following table is a
summary of the financial considerations for this report: |
|||
Original Budget
and Account # |
$885,000.00 |
|
058-6150-8289-005, 2008
Capital - |
Current Budget
Available (unspent) |
$884,354.70 |
|
|
Less: Construction Cost |
($652,510.00) |
|
Awarded to
Marbridge Construction Ltd. |
Less: Contingency –Construction & Consultant |
($ 70,751.00) |
|
|
Less: Consultant Fees for Contract Administration |
($55,000.00) |
|
Awarded
to Totten Sims Hubicki |
Budget
Remaining |
$106,093.70 |
|
|
The
remaining budget available of $ 106,093.70 for account 058-6150-8289-005,
John Street Bridge Superstructure Replacement will be used as follows:
· Bird nest removal prior to construction (Estimated $9,600.00);
· Traffic signage installation and rental from the day of closure to the end of construction (Estimated $35,000.00);
·
Emergency bridge inspection conducted on
· Town administrative costs such as reproduction of drawings, tree pruning and Landscaping etc. (Estimated $10,000.00), and
· Anticipated remaining balance of $47,993.70 will be returned to the original funding source.
Under the Migratory Birds
Convention Act, the birds nests under/on the bridge will be removed prior to
start of construction. Consultant have
obtained a qualified person and are currently completing the removal prior to
To insure that the existing watercourse is not disturbed
during the demolition work, the contractor will install a Debris Collector
System (as per TRCA requirements and Ontario Regulation 166/06) to prevent
any material to fall into the river.
The existing bridge consists of 2 traffic lanes and sidewalk on the south side. The proposed bridge will have sidewalk on both sides which will improve accessibility across the bridge.
Not applicable
The Finance Department has reviewed this report and their comments have been included.
RECOMMENDED
BY: ________________________ ________________________
Steve Andrews Peter Loukes
Director, Commission Lead,
Asset Management Operations and Asset Management
Not applicable