Report to: General Committee Report
Date:
SUBJECT: Consultant Selection RFP# 181-R-07
Detailed
Design and Contract Administration for
PREPARED BY: Allan Arbuckle Manager, Infrastructure & Capital Works, Ext.3120
Gina
Gammarano, Capital Works Engineer, Ext. 4040
RECOMMENDATION:
THAT the report entitled Consultant Selection RFP #
181-R-07, Detailed Design and Contract Administration for
AND THAT staff be authorized to retain the highest
ranked and lowest priced qualified firm UMA Engineering Ltd. for the detailed
design of the project for an upset fee limit of $291,435.00 exclusive of
GST and disbursements ($306,006.75 inclusive of 5% GST);
AND THAT Engineering staff be authorized to retain
the highest ranked and lowest priced qualified firm UMA Engineering Ltd. for
the construction inspection and contract administration for an upset fee of
$233,060.00 exclusive of GST ($244,713.00 inclusive of 5% GST), subject to
the satisfactory completion of the
detailed design phase of the project as described in the RFP document;
AND THAT a contingency amount of 78,674.25
exclusive of GST ($82,607.96 inclusive of 5% GST) be established to cover any additional
costs and that the Director of
AND THAT the awards be funded and pre-approved
from the 2008 Engineering Capital budget project 8299 Rodick Road Extension, in
the amount of $675,549.56 exclusive of GST;
AND THAT upon payment of all invoices, any remaining funds be returned to the original
funding source;
AND THAT staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
1.
Purpose 2. Background 3. Discussion 4. Financial
5. Others
(Environmental, Accessibility,
Engage 21st, Affected Units) 6.
Attachment(s)
The purpose of
this report is to obtain approval to award the consulting contract for the
Detailed Design and Contract Administration for
In order to implement the
recommended solution, the Town initiated a 5 phase project to improve
This assignment represents the fifth
and final phase involving the widening of the existing roadway between
RFP# 181-R-07 was issued in accordance with Purchasing By-law 2004-341. Staff have reviewed the proposals and are satisfied that all terms and conditions comply with the Towns requirements. The evaluation team was comprised of staff from the Engineering Department with Purchasing staff acting as the facilitator. The proposals were evaluated based on the established evaluation criteria as listed in the RFP. The RFP results are summarized below:
Bid Information
Advertised, place and date |
ETN, |
RFP closed on |
|
Number picking up RFP documents |
14 |
Number responding to RFP |
5 |
Detailed Pricing Information
Consultants |
Prices (exclusive of GST) |
Rank |
UMA Engineering Ltd |
$524,495.00 |
1 |
LEA Consulting Ltd |
$567,287.00 |
4 |
URS Canada Inc |
$665,658.00 |
3 |
Earth Tech |
$730,431.00 |
5 |
Totten Sims Hubicki Associates |
$878,095.00 |
2 |
Project Schedule
The Town owned
building located at
A portion of
the building is currently occupied by Markham Fire and Emergency Services who
have agreed to vacate the site in June 2008.
The following project schedule has been developed assuming vacant
possession of the property will occur by
Detailed Design & approvals February 2008 to December 2008
Tender Call-building demolition/site cleanup April 2008
Building demolition & site cleanup July 2008 to November 2008
Tender call road & bridge January 2009
Construction road & bridges May 2009 to November 2010
Funding for this project is currently included in the proposed 2008 Capital Budget, engineering project No. 8299, in the total amount of $1,077,500.00. Total project costs are as follows:
Project Costs (exclusive of GST) |
|
Consultant Detailed Design and Disbursements Fees |
$291,435.00 |
Consultant Contract Administrations and Inspections Fees |
$233,060.00 |
Contingency (15%) |
$78,674.25 |
Engineering Dept. Project Management Fee (12%) |
$72,380.31 |
Total |
$675,549.56 |
The RFP was set up for a two-staged award. Subject to the satisfactory completion of the detailed design phase, the Consultant will be awarded the Contract Administration and Inspection portion of the project. It is anticipated that only the detailed design portion of this project will be completed in 2008; therefore it is recommended that a total amount of $375,368.28 be pre-approved in the 2008 Capital budget as follows:
Detailed Design Costs (exclusive of GST) |
|
Consultant Detailed Design and Disbursements Fees |
$291,435.00 |
Contingency (15%) |
$43,715.25 |
Engineering Dept. Project Management Fee (12%) |
$40,218.03 |
Total |
$375,368.28 |
Not applicable
Not applicable
Not applicable
The Finance, Legal, Asset Management and Fire Departments have reviewed this report and their comments have been incorporated.
RECOMMENDED BY:
_____________________
________________________
Alan Brown, C.E.T. Jim Baird, M.C.I.P., R.P.P.
Director of Engineering Commissioner, Development Services
Attachment A: Rodick Road Phasing