Report to: Development Services Committee Report Date:
SUBJECT: Box Grove Community Fund Distribution
PREPARED BY: Biju Karumanchery, Development Manager, East District, ext. 2970
RECOMMENDATION:
That the remaining funds from the
Box Grove Community Fund (Capital Budget account 80 6900 6805 005) in the
amount of $401,858 be allocated towards street lighting improvements within the
Box Grove area and improvements to the Box Grove Community Centre;
And that a 2008 Engineering
Department Capital Budget be established for the Box Grove Street Lighting
Improvements at a cost of $306,780 exclusive of GST to be funded from the Box
Grove Community Fund;
And that $30,000 exclusive of GST
be allocated to Asset Management’s Lifecycle Reserve from the Box Grove
Community Fund in order to top-up funding available for the Box Grove Community
Centre Sewage Line Connection;
And that a 2008 Urban Design
Capital Budget be established for Box Grove Community Centre Landscaping and
Site Improvements at a cost of $65,078 exclusive of GST to be funded by the Box
Grove Community Fund;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
1. Purpose 2.
Background 3. Discussion 4. Financial
5. Others
(Environmental, Accessibility,
Engage 21st, Affected Units) 6.
Attachment(s)
The purpose of this report is to
identify, for Committee’s consideration, potential public projects that may be
eligible to receive a portion of the remaining Box Grove Community Fund
contributed by the Box Grove developers, and to make recommendations with
respect to this matter. Staff recommends that the remaining funds be
applied toward the Box Grove Community Centre (sewer line connection and
landscaping/ site improvements) and street lighting in the area.
The Box Grove developers entered
into a Memorandum of Understanding with the Town of
A portion of the funds have been allocated to certain projects
As part of Council’s approval of
the 2003 budget, a total of $98,092 was allocated for works in the Cedar Grove
Area, which was to be paid out of the $500,000 contribution by the Box Grove
developers. Specifically, $38,066 was
allocated for parks upgrades and $60,026 was allocated for lighting for the Cedar
Grove Baseball Diamond.
Eligibility of various projects was investigated with respect to the remaining
funds
Various projects in and around the
Box Grove area were identified as potential candidates for receiving a portion
of the remaining Box Grove funds. These
included the following:
Improvements to the
Through previous
studies/assessments it has been determined that improvements to the basement of
the Rouge River Community Centre on Rouge Bank Drive in the Legacy Community,
involving approximately 186m2 (2000 ft2), will increase
both programmable space and programmable hours at that facility. The total estimated cost of these
improvements in October 2000 was approximately $496,000 and is expected to have
increased since that time. Community Services
staff recommended at the time, and still maintain, that the benefits associated
with the proposed improvements to the basement did not justify the considerable
expenditure, or the serious disruption to the Community Centre basement tenants
(the Army Cadets), required to proceed with the improvements.
Urbanization and enhanced
streetscaping of the portion of 9th Line in Box Grove
9th Line in the Box
Grove area between the railway tracks to the south and
Sidewalk along the north side
of
A significant public expenditure
that was contemplated by the Infrastructure and Capital Works Group in the Box
Grove area involves the construction of a sidewalk along the north side of 14th
Avenue between Roxbury Street and Legacy Drive (west of 9th
Line). There are a number of significant challenges to
constructing this sidewalk including insufficient right-of-way width along 14th
Avenue, between the Rouge River and Legacy Drive, to accommodate the sidewalk
and associated grading, the potential requirement to construct retaining walls
to accommodate grading and the need to construct a new pedestrian bridge or to
widen the existing roadway structure in order to cross the Rouge River. Excluding property costs the estimated cost
of constructing this north sidewalk range from about $520,000 to $610,000. An expenditure of this magnitude may not be
warranted given that a continuous sidewalk is available on the south side of
Contribution towards sanitary
sewage facilities for Box Grove hamlet residents
Asset Management staff have been
exploring opportunities
Water connection rebate for
properties on 9th Line north of
When the Legacy subdivision to the
west of 9th Line was constructed the developer, in 1998, provided
the opportunity for water connections for residents on 9th Line
north of
When the Box Grove community
developed, as per the 2002 Memorandum of Understanding noted above, the
developers provided the residents who lived on
Improvements to the Box Grove
Community Centre
The Box Grove Community Centre
building on 9th Line south of
Item |
Improvements |
Estimated Costs |
1 |
Sewage Line connection |
$30,000 to top up the lifecycle reserve to $70,000 |
2 |
Landscaping and site
improvements |
$65,078 |
|
Total Estimated Costs |
$95,078 |
Currently there are no street
lights serving the old Box Grove area, including 9th Line within Box
Grove and
Section No. |
Location |
Existing Conditions |
Minimum Improvements |
Estimated Cost |
1 |
9th Line – |
Hydro poles on the east side – no streetlights |
Add 13 lights and related wiring to existing poles incl. connection to
distribution system |
$30,800 |
2 |
9th Line – 14th to |
Hydro poles on west side – no streetlights |
Add 9 lights and related wiring on existing poles incl. connection to
distribution system |
$24,250 |
3 |
9th Line – south of |
Hydro poles on west side – no streetlights |
Add 6 lights and related wiring on existing poles incl. connection to
distribution system |
$21,000 |
4 |
|
Existing hydro poles – no streetlights |
Install new aerial streetlighting system (poles, luminaries &
wiring) |
$152,000 |
5 |
|
Hydro poles on south side – no streetlights |
Add 11 lights and related wiring on existing poles incl. connection to
distribution system |
$27,600 |
|
Estimated Construction Cost |
$255,650 |
||
|
|
$51,130 |
||
|
TOTAL ESTIMATED COST |
$306,780 |
Staff recommend that the remaining funds be applied towards street
lighting in the area and the Box Grove Community Centre
It is felt that the Box Grove
Community Fund should be applied to projects with a clear public benefit. Since the Local Improvement costs for
sanitary services in the area, as well as water connection costs for certain residents
on 9th Line, are considered to have more of a private than public
benefit, these projects are not recommended to qualify for the Community Funds.
Moreover, as discussed above, a
sidewalk along the north side of
It is staff’s recommendation that
given the safety factor related to street lighting the remaining Box Grove Funds
be applied first to street lighting in the Box Grove area and the balance of
the funds be applied to Box Grove Community Centre improvements, as discussed
above.
This report identifies potential
uses to which the remaining Box Grove Community Fund residing in Planning
Capital Budget account 80 6900 6805 005 in the amount of $401,858 can be
applied.
Staff recommends the dollars be
allocated as follows:
Box Grove Community Centre
Not applicable.
Not applicable.
The
recommended use of the Box Grove Community Fund will assist with the implementation
of the following key Town of
This matter has been discussed
with the
RECOMMENDED BY:
Valerie
Shuttleworth, M.C.I.P., R.P.P. Director
of |
|
Jim Baird, M.C.I.P., R.P.P Commissioner, Development
Services |
Appendix ‘A’ - Correspondence from
Box Grove residents
Q:\Development\Planning\APPL\SUBDIV\03
115555_BoxGroveHill\Suggested uses for Box Grove community fund.doc