Report to: Development
Services Committee Report
Date: June 17,
2008
SUBJECT: RECOMMENDATION
REPORT
St. Mark’s Coptic Church
– Phase 1
455
Ferrier Street
Site Plan application to
permit a three-storey cathedral to be used as a place of worship with
recreational and educational facilities and other related uses.
File No. SC 08 110712
PREPARED BY: Stacia
Muradali, ext. 2008
Planner, Central District
RECOMMENDATION:
That the report dated June 17, 2008 titled “RECOMMENDATION
REPORT, St. Mark’s Coptic Church – Phase 1, 455 Ferrier Street, Site Plan
application to permit a three-storey cathedral to be used as a place of worship
with recreational and educational facilities and other related uses” be
received;
That the application for Site Plan
approval (SC 08 110712) be endorsed in principle, subject to the conditions
attached as Appendix ‘A’;
That Site Plan approval be delegated to the Director of Planning and Urban Design,
or her designate, to be issued following execution of a Site Plan Agreement.
Site Plan approval is issued only when the Director has signed the Site Plan;
And that Staff be authorized and
directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
A
Site plan application has been submitted by St. Mark’s Coptic Church to permit
a three-storey cathedral at 455 Ferrier Street (the “subject property”) which is located on the
north side of Steeles Avenue, west of Warden Avenue. The cathedral will be used as a place of worship
with recreational and educational facilities, and other related uses. The
proposal is Phase 1 of a larger multi-phase campus type development which is
projected to develop over the next 14 years, based on a preliminary phasing
plan provided by the applicant.
The applicant has
submitted several technical studies in support of the proposed
development. A Stormwater
Management Report, Traffic Impact Study, Grading and Servicing Plans and a
Concept Master Plan are currently under review. Preliminary comments have been
received and are being addressed by the applicant. The applicant has been
working with staff to implement appropriate sustainable development and traffic
demand management practices for the proposed development.
The proposed development
is generally acceptable, subject to the resolution of the outstanding issues
identified in this report. The applicant has revised and upgraded the site plan
in response to comments from staff. There is a parking shortfall of approximately
211 parking spaces for the proposed
development. The applicant will be exploring alternative methods of addressing
the parking shortfall including the implementation of travel demand management
practices (TDM), shared parking with adjacent property owners and other
appropriate measures which can assist in mitigating the parking shortfall.
The purpose of this report is to recommend approval of the
site plan application to permit the construction of a three-storey cathedral
for the purposes of a place of worship and community centre.
Subject property and area context
455 Ferrier Street (the
“subject property”) is a vacant lot which occupies the entire block bounded by Steeles Avenue, Acadia
Avenue and Ferrier
Street with a lot area of 4.88 hectares (12
acres) (Figure 1).
The subject property is bounded to the south by Steeles Avenue with single
family detached dwellings reversed to the south side of Steeles Avenue. There is commercial
development with a gas station, grocery store, restaurants, retail and other
commercial uses to the east, at the north west corner of Warden
Avenue and Steeles Avenue. Two
commercial developments, Metro
Square and New Century Plaza, are located
to the west of Ferrier Street. To the
north across Acadia Avenue are office
buildings and a place of worship (Figure 2).
Proposed cathedral to be used as a place of worship
with recreational and educational facilities
St. Mark’s
Coptic Church is proposing to construct a three-storey cathedral (Figure 5). In
total, the cathedral will include five floors (two levels will be located below
grade). The two lower levels will consist of offices associated with the place
of worship, a church hall, bakery, gift shop and recreational and educational
facilities (including a gymnasium, class rooms, fitness rooms and library). The
ground floor and two gallery levels above will function primarily as a place of
worship. There is an anticipated 1,394 seat capacity for the place of worship
which is expected to increase to approximately 1,820 seat capacity in the
future.
The total
gross floor area of the cathedral is 7,077 square metres
(76,176 square feet). The place of worship and accessory uses will comprise
approximately 70% of the proposed building with the remaining 30% dedicated to
recreational and educational facilties. 395 surface
parking spaces are provided. The location of the parking spaces will occur to
the rear of the cathedral along Ferrier
Street and Acadia
Avenue (Figure 4).
There is a
centrally located open space to the north of the cathedral and an exterior main
plaza to the west of the building. Both are illustrated on the attached site
plan (Figure 4). The open space area to the north will be utilized for
ceremonial events including weddings and funerary services. The main plaza to
the west will also be used for ceremonial purposes, as a fire access route, and
for temporary drop-off. The applicant has worked with staff to enhance the
design of this space by discouraging vehicular access and improving pedestrian
connectivity and circulation through the balance of the site.
Vehicular
accesses are proposed on Steeles Avenue, Ferrier
Street and Acadia
Avenue. The Town is generally satisfied
with the proposed accesses on Ferrier
Street and Acadia
Avenue subject to some improvements which
are currently being addressed. The proposed Steeles Avenue access will
require approval from the City of Toronto and TTC.
Each of the proposed accesses is designed with right-in, right-out movements.
The applicant is proposing a dedicated right-turn lane on Ferrier
Street which is recommended by the Traffic
Impact Study submitted by the applicant to provide a higher degree of
accessibility to the site. The proposed driveway and dedicated right-turn lane on
Ferrier Street will impact
existing on-street parking on Ferrier
Street. Town staff have
determined that the right turn lane is not mandatory and prefer if it is removed
from the site plan as its primary function is to accommodate peak demand which
will occur for a short period of time on Sunday mornings. It would also have a
visual impact and detract from the pedestrian urban environment. The site plan
should be revised to show removal of the dedicated right-turn lane and show
impact of the driveway on Ferrier
Street. This is a condition of site plan
endorsement (Appendix ‘A’). Some of the displaced on-street parking on Ferrier
Street may be accommodated on Acadia
Avenue however, this requires further
evaluation.
Master Concept and Phasing Plans
The applicant
has provided a master concept plan and phasing plan to assist with the review
of this site plan application (Figure 6). The anticipated phasing includes the
proposed cathedral (2008), an office building (2012), a day care centre and a seniors residence (2014), a private school (2015), a
community centre (2017), a museum and papal quarters (2019), a small place of
worship (2020) and a theatre (2022).
The site plan
application review and technical studies conceptually take into consideration
the future contemplated uses and overall functioning of the master concept
plan, including, but not limited to, the servicing of the multiple components,
traffic impacts and the provision of adequate parking. Site plan approval will
be required for each subsequent phase of development. Revised technical studies
will be required as part of any future site plan approval process.
The applicant
is proposing to construct an underground parking structure as future phases are
developed and there is an increased demand for parking. Ultimately, all of the
parking for the overall campus type development will be provided underground.
Official Plan and Zoning By-law amendment
applications approved in 2003
In 2003,
Council adopted an Official Plan amendment (OPA No. 111) and Zoning By-law
amendment (2003-199) to accommodate the cathedral and the future campus development.
OPA 111 redesignated the subject property from Industrial-Business Corridor Area to Commercial-Community Amenity Area which provides for the place of
worship as the primary use, and the future uses functioning as a part of the
religious campus. The intent of the Community
Amenity Area designation is to provide for a multi-use centre offering a
diverse range of services, such as community, institutional and recreational
uses and to function as a significant and identifiable focal point for the
area.
By-law
2003-199 rezoned the subject property from Business
Corridor (BC) to Community Amenity
with a Hold provision [CA(H)] (Figure
2). The site-specific CA(H) zone permits the proposed cathedral
which will function as a place of worship and community centre. The proposed Phase
1 site plan application meets the site-specific development requirements.
However, the proposed site plan does not comply with the Town’s parking
requirements (discussed further below). 606 parking spaces are required to
accommodate the place of worship and associated facilities within the
cathedral. The applicant is proposing 395 surface parking spaces. The applicant
will be exploring alternative methods of addressing the parking shortfall. A
minor variance application will be submitted once the parking shortfall is
addressed in a manner satisfactory to the Town.
The Hold provision appended to the zoning of
the property can only be removed if Traffic, Parking and Servicing studies have
been completed and a site plan agreement executed to the satisfaction of the
Town. The applicant is required to apply to lift the Hold provision. Staff will bring forth a By-law for consideration
to lift the Hold once the required
conditions have been satisfied.
OPTIONS/
DISCUSSION:
Parking shortfall of 211 parking spaces
In 2003,
Council adopted a By-law (2003-301) to deal specifically with parking
requirements for places of worship. Parking for the place of worship, including
any accessory uses (including the recreational and educational facilities) is
calculated at 1 parking space per every 9 m2 of the net floor area of the
worship area and any accessory uses. Based on this standard and the information
provided by the applicant, 606 parking spaces are required. The applicant is
providing 395 parking spaces.
A parking
analysis was submitted as part of a Traffic Impact Study provided by the
applicant. However, the parking analysis was based on a blended parking
calculation of 1 space per 4 seats of the worship area capacity and 1 space per
40 square metres for the community centre uses. The
parking analysis based on this interpretation of the By-law, has resulted in a
parking shortfall of 211 parking spaces.
The applicant
is providing 395 parking spaces on the surface which occupies a large portion
of the site. Increasing the extent of the surface parking area is less than
desirable from an urban design perspective. The Town has requested that the
applicant explore alternative methods of addressing the parking shortfall
including the implementation of travel demand management practices (TDM),
shared parking with adjacent property owners to accommodate peak demand,
providing a portion of the parking underground and/or any other appropriate
measure which can assist in mitigating the parking shortfall. A combination of some of these methods should be
examined and implemented to the satisfaction of the Town. The Traffic Impact
Study should be revised to address the proposed measures and parking shortfall
to the satisfaction of the Town before submitting a minor variance application
to permit a reduction of the required parking and before execution of a site
plan agreement (Appendix ‘A’).
Implementation of Travel Demand Management (TDM)
The applicant
has recently provided a memorandum to the Town summarizing the proposed TDM
implementation strategy. The Town has become more active in promoting and
supporting the implementation of TDM strategies to new development. The subject
property is ideally located within close proximity to major arterial roads (Warden
Avenue and Steeles Avenue) and
existing frequent transit services such as TTC along Steeles Avenue with
connections to the Finch subway station.
The TDM memorandum
prepared by Giffels recommends that the St. Mark’s
Coptic Church become a member of the “smart Commute 404-7 Markham, Richmond
Hill” Transportation Management Association (TMA) and implement TDM measures
such as a commuter rideshare program which involves preferential carpool
parking and a ride-matching program, promotion of transit use, provision of
shuttle service to transit nodes, and facilitation of a pedestrian-friendly
environment. The implementation of a TDM strategy to assist in mitigating the parking
shortfall to the satisfaction of the Town will be included in the site plan
agreement. The TDM strategy must be provided to the satisfaction of the Town
prior to the submission of a minor variance application.
Traffic Impact Study
A Traffic
Impact Study has been submitted and is under review by the Town and City of Toronto. Preliminary
comments have been received and are currently being addressed. The Town has
identified the need for a more detailed review of existing and future
intersection operations and the type of control measures recommended at the
intersection at the north east portion of Acadia
Avenue. The Town has also requested that
the Traffic Impact Study provide a more detailed review of pedestrian and
vehicle accesses, particularly as they relate to adjacent developments. The
Town has also indicated that the site plan should be revised to reflect removal
of the dedicated right-turn lane on Ferrier
Street as it accommodates peak demand which
occurs for a short period of time on Sunday mornings, impacts existing
on-street parking and diminishes the pedestrian and urban environment. The
Traffic Impact Study should be revised to address removal of the right-turn
lane. The City of Toronto has reviewed
the study and has indicated that the proposed entrance on Steeles Avenue may impact
the existing TTC bus stop. Additional details and review of siting
issues related to the proposed entrance and the existing bus stop need to be
provided and discussed with the TTC. The submission of a revised Traffic Impact
Study to address the parking shortfall and mitigating measures, removal of the
dedicated right-turn lane on Ferrier Street, implementation of a TDM strategy and
any other issues identified by the Town, City of Toronto and TTC, to the
satisfaction of the Town is required prior to submission of a minor variance
application and is a condition of site plan endorsement (Appendix ‘A’).
Implementation of sustainable development practices
NORR Limited
Architects and Engineers have proposed several sustainable design building
practices and ecological landscaping strategies which will be applied to the
proposed development. Some of the proposed initiatives are as follows:
Appendix ‘A’
includes a commitment to the implementation of sustainable development
practices in the site plan agreement as a condition of site plan endorsement
(Appendix ‘A’).
Building design and landscaping
The unique
design of the cathedral will provide a landmark built form in a prominent
location. All exterior walls will be brick and light tan in colour.
Most walls and some windows will be capped with tan coloured
precast concrete. The west façade which serves as the
main ceremonial entrance will feature oak wood doors with tall wood transoms
above. The roof membrane will be a light tan colour
to match the brick. Reflective or colour tinted glass
will not be used due to the possible future introduction of stained glass. A coloured rendering is attached to this report.
The applicant
has provided the Town with a landscape plan for review and approval. The
landscape plan concentrates tree and shrub planting towards the front of the cathedral,
along Steeles Avenue and around
the west main plaza. A low decorative stone wall, shrub
planting and an urban plaza space all create a focal point at the
south east corner of Steeles Avenue and Ferrier
Street. Details must be provided on the
proposed design approach for this open space area. The design must incorporate
soft and hard landscaping and a well designed pedestrian connection to the
cathedral. The proposed stormwater facility at this
corner must be well integrated in the overall design scheme. Landscaped islands
and tree planting are incorporated into the landscape plan.
The landscape
plan does not reflect any treatment or tree planting along Acadia
Avenue. Town staff have
requested that additional tree planting be introduced along the entire perimeter
of the site with enhanced landscaping around the open space at the north side
of the building as this space will remain in the long term and represent an
integral central open space area within the campus type development. Revisions
to the landscape plan to the satisfaction of the Town and additional
information on the proposed hard landscaping, signage, outdoor furniture and lighting
must be provided as a condition of site plan endorsement (Appendix ‘A’).
Conclusion
Staff are of the opinion that the proposed site plan and
building elevations are generally acceptable subject to further revisions
identified in this report. The design of the cathedral represents a unique and
attractive built form. The applicant has worked with staff to provide a more
pedestrian-friendly environment with improved pedestrian connectivity and
exterior open spaces and plazas which will create an appropriate development
for the subject property with the high prominence which the St. Mark’s Coptic
Church is seeking.
Not
applicable.
Not
applicable.
The proposed
development will incorporate a travel demand management strategy and implement
sustainable development practices to assist in minimizing the impact of the
development on the environment. The travel demand management strategy will
promote transit usage. The proposed development introduces an urban plaza at
the north east corner of Steeles Avenue and Ferrier
Street which will create an attractive
public space.
All Town
departments and external agencies have been circulated with this application
and all comments have been addressed and incorporated into the site plan.
RECOMMENDED BY:
______________________________ ________________________________
Valerie Shuttleworth,
M.C.I.P, R.P.P Jim Baird, M.C.I.P., R.P.P.
Director of Planning & Urban Design Commissioner of Development
Services
Figure 1-
Location Map
Figure 2-
Aerial Photo
Figure 3-
Area Context/Zoning
Figure 4-
Site Plan
Figure 5-
Building Elevations
Figure 6-
Master Concept Plan
Appendix ‘A’-
Conditions of Site Plan Endorsement
AGENT/CONTACT
INFORMATION
Paul
Noskiewicz
Project Manager
Norr Limited
Architects & Engineers
175 Bloor Street East
15th Floor, North Tower
Toronto, ON, M4W 3R8
Tel: (416) 929-0200
Fax: (416) 929-3635
APPENDIX ‘A’-
CONDITIONS OF SITE PLAN ENDORSEMENT
1.
That the owner enters into a site plan agreement with
the Town, containing all requirements of the Town, City of Toronto, TTC and other
public agencies, including providing any financial securities and conveyances
of land required;
2.
That this endorsement shall lapse and site plan
approval will not be issued, after a period of three years commencing June 17,
2008, in the event that the site plan agreement is not executed within that
period of time;
3.
That prior to approval of the site plan, the owner
shall address any concerns identified by the Town, City of Toronto, TTC and any
other external agencies resulting from a review of the Traffic Impact Study, Stormwater Management Report, Servicing Plans and other
studies, or revise the studies accordingly, to the satisfaction of the Town and
any other authorized public agencies;
4.
That prior to approval of the site plan, the Owner
shall submit final drawings, including but not limited to, site plan and
elevation drawings, landscape plans, grading and servicing plans, and lighting
plans that comply with all requirements of the Town, City of Toronto, TTC and
any other authorized public agencies, to the satisfaction of the Town;
5.
That the grading plans and engineering drawings be
revised to show sidewalks along Ferrier Street and Acadia Avenue to Town
standards, removal of burming in the Town’s
right-of-way and any additional requirements by the Town and City of Toronto;
6.
That the landscape plan be revised to incorporate
additional tree planting along the perimeter of the entire site and around the
open space on the north side of the Cathedral, to the satisfaction of the Town;
7.
That the owner provide additional information on
proposed hard and soft landscaping, signage, outdoor furniture and lighting,
and details of the urban plaza at the north east corner of Steeles
Avenue and Ferrier Street to the satisfaction of the Town;
8.
That the owner covenant and agree in the site plan
agreement to implement a travel demand management strategy to the satisfaction
of the Town;
9.
That the owner covenant and agree in the site plan
agreement, to implement sustainable development practices to the satisfaction
of the Town;
10.
That prior to approval of the site plan, the owner
provides a written submission and revised Traffic Impact Study outlining proposed
alternative methods to address the parking shortfall to the satisfaction of the
Town;
11.
That prior to approval of the site plan, the owner submits
a revised Traffic Impact Study and obtains Committee of Adjustment approval for
any parking shortfall;
12.
That the proposed Steeles Avenue access be approved
by the City of Toronto in
consultation with the TTC;
13.
That the site plan be revised to show the impact of
the driveway on existing on-street parking on Ferrier Street and removal of the
dedicated right-turn lane; and
14.
That the owner covenant and agree in the site plan
agreement to pay all applicable charges including but not limited to
development charges, cash-in-lieu of parkland and recoveries.