Report to: General Committee – Community & Fire Services             Report Date: Oct 3, 2008

 

SUBJECT:                     East Markham Community Centre & Library – Schematic Design

PREPARED BY:          Henry Tse, P. Eng., Project Manager

 

RECOMMENDATION:

 

THAT the report titled “East Markham Community Centre & Library – Schematic Design” be received; and,

 

THAT the presentation by Shore Tilbe Irwin & Partners highlighting the architectural and aesthetic features of the proposed building and associated parking garage structure be received; and,

 

THAT Council approves the recommended schematic design for the building and the associated parking garage structure; and,

 

THAT Council authorizes staff to proceed with detailed design phase of the project; and,

 

THAT Council authorizes the Mayor and the Clerk to execute an Agreement of Purchase and Sale, in a form satisfactory to the CAO and the Town Solicitor and all related documents and take any action necessary to give effect to the acquisition of approximately 4.51 acres of land from Markham Stouffville Hospital together with an option to purchase an additional 0.75 acres of land at the south-west corner of Bur Oak Avenue and Church Street; and

 

THAT the property acquisition costs be funded from account #070 6200 7369 005; and

 

THAT the Architectural/Engineering Services fee for Shore Tilbe Irwin and Partners be increased by $591,480 to account for additional project scope, primarily related to the parking garage structure; and

 

FURTHER THAT staff be authorized and directed to do all things necessary to give effect to this resolution.

 

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (Environmental, Accessibility, Engage 21st, Affected Units)             6. Attachment(s)

PURPOSE:

 

The purpose of this report is to seek Council’s approval of the recommended schematic design for the East Markham Community Centre & Library (EMCC&L) and the associated parking garage structure, to proceed with the detailed design phase of the project, and to finalize the acquisition of necessary land from Markham Stouffville Hospital (MSH) for the project.

 

 

 

 

 

 

BACKGROUND:

 

Staff, together with Shore Tilbe Irwin and Partners (STIP), presented design concept options to Council at their General Committee meeting on June 16, 2008.  Council, subsequently at their June 24 meeting, passed a resolution endorsing/approving the following:

 

  • Building Design Option 3
  • Link Option B interface with MSH
  • Construction of a parking garage structure to manage all parking requirements for the EMCC&L
  • Allocation of programming space as outlined in the presentation, including a viewing gallery for the aquatic area
  • Further development of the conceptual/schematic design to the detailed design phase of the project

 

Council also directed staff to report back in the fall regarding:

  • The cost implication if the parking garage structure is designed to accommodate potential future additional parking levels
  • An update on the potential relocation of the helipad from its present location, and with options for providing a public plaza space in the northeast corner of the project site.

 

OPTIONS/ DISCUSSION:

 

STIP conducted in July and August, separate micro-planning exercises with staff from Recreation and Library.  Comments and suggestions from those meetings have been considered in the development of the interior space layout.

 

In early September STIP presented to staff their initial recommended conceptual/schematic design, including preliminary architectural renderings of the exterior elevations.  The associated construction cost estimate was also presented.  Subsequently, several staff/STIP working sessions were convened to provide feedback as part of the evolution of the design process.

 

Staff/STIP also met with MSH and their architectural consultant (B+H) in early October as part of our on-going communication between the two teams.  They support the recommended conceptual/schematic design as presented.

 

With the adoption of a parking garage structure, which requires less land than for surface parking lot, the project requires approximately 4.51 acres of land from MSH, in addition to the former Mattamy parcel (2.1 acres) to the east, totalling 6.61 acres.  With Council’s approval, staff will finalize the agreement with MSH.

 

Council has requested that staff report back in the fall of 2008 with an update on the process for relocating the Markham Stouffville Hospital helipad and with options for providing a public plaza space in the northeast corner of the project site. 

 

MSH has not finalized a process for relocating the Helipad but advises that it is willing to accommodate the Town’s request for a public plaza at the south-west corner of Church Street and Bur Oak Ave., provided that the Town can demonstrate that MSH is left with a suitably sized development parcel on the south side of Church Street, west of the proposed public plaza, within the present helipad site.  Staff and MSH have determined that a 0.75 acre (approximate) plaza at the corner provides MSH with an appropriate development parcel that maintains view-lines to the EMCC&L. 

 

The Town will secure the ability to acquire this public plaza site by way of an option in the Agreement of Purchase and Sale, at the same price as the EMCC&L lands together with a proportionate share of Developer Cost Sharing Costs.  This option will remain in effect for a period of 2 years.  If exercised by the Town, the closing of the acquisition will be the later of 2 years from the date of exercise and 30 days following the date when MSH is no longer using the option lands for the purpose of the Heliport and has vacated the option lands.  This option, together with the long closing at today’s price, is considered favourable to the Town.

 

Council has requested information about the cost premium for the garage structure if the final design is to include the provision for additional parking levels in the future.  Foundation and columns for the structure will be impacted.  The construction cost premium to accommodate each additional parking level in the future is estimated at $155,000 per level, or $310,000 for two (2) levels.  However, construction cost would be progressively more costly (i.e. no longer linear) for a higher capacity structure, which would necessitate a more in-depth analysis.

 

With Council’s concurrence to the recommended conceptual/schematic design for the building and the associated parking structure as presented, staff intends to proceed with detailed design. 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE:

 

COST ESTIMATE:

 

Assuming the contract to be awarded in December 2009, the total project cost estimate for the East Markham Community Centre & Library project remains at $70.4 m, as presented to General Committee on June 16, 2009.   

 

Cost estimate for the land component is now at $4.6 m.  The cost has been reduced to reflect less land (by 2 acres) being required for a stand-alone multi-storey parking structure in place of the original all at-grade parking option.

 

The estimated total cost of construction, including the link with the hospital and the parking structure, is $53 m.

 

Internal costs, which include architectural and engineering consulting fees and other miscellaneous costs, have been estimated at 10% of construction cost. 

The scope of work for the project has increased for the retained architects, STIP, primarily due to the stand-alone parking garage structure.  Other less significant Council-approved project scope changes include: dedicated children’s playground, special needs room, and upgraded multi-use room to rehearsal space.  An increase of $591,480 in consulting fee is required for the additional Architectural/Engineering Services.  This supplemental cost is included in the internal cost item mentioned above.

 

The estimated cost for furniture, equipment and IT remains at $7.4m.

 

Town of Markham

EMCC&L Cost Analysis Comparison

 

 

 

 

 

 

COST ESTIMATE

General Committee Presentation

 

 

16-Jun-08

 

 

28-Oct-08

 

 

 

 

 

 

 

Land

$6,300,000

 

 

$4,600,000

 

 

 

 

 

 

 

Construction (including parking structure and construction contingency)

$51,400,000

 

 

$53,100,000

Note 1

     Note 1: Includes reallocated land cost of $1.7 m to parking structure

 

 

 

 

 

 

 

 

 

 

Internal cost at 10% of Construction Cost

 

 

 

 

 

     STIP (Architectural/Engineering Consulting Services)

$2,127,600

 

 

$2,127,600

 

     STIP (project scope changes, including parking structure)

 

 

 

$591,480

 

     Other internal costs

$3,172,400

 

 

2,580,920

 

 

 

 

 

 

 

FF&E / IT cost

$7,400,000

 

 

$7,400,000

 

 

 

 

 

 

 

Total Cost Estimate

$70,400,000

 

 

$70,400,000

 

 

 

BUDGET STATUS:

 

To date three capital projects have been approved totaling $55,905,412 for land acquisition, architectural services and construction.  An additional $14,494,588 has been requested in the 2009 capital budget.

 

PROPOSED FUNDING SOURCES:

 

Historically, Recreation/Library facilities excluding Recreation IT costs have been funded from 90% Development Charges and 10% non-growth source.  It is anticipated that this approach will be used for this project as well as a contribution from MSH for costs related to hospital initiatives.

 

A refined cost estimate with corresponding funding sources will be provided to Council prior to construction tendering.

 

ENVIRONMENTAL CONSIDERATIONS:

 

The East Markham Community Centre and Library will incorporate an environmentally friendly building design, energy consumption and product procurement in the development of the facility.  It will achieve at least the basic LEED certification level, with an aim to achieve the next higher level of certification, i.e., LEED Silver. 

 

A LEED “Score Card” is attached to this report.

 

ACCESSIBILITY CONSIDERATIONS:

 

The facility will be designed having regard for the accessibility requirements of all its users.

 

ENGAGE 21ST CONSIDERATIONS:

 

The project aligns with the following Town of Markham corporate goals:  Infrastructure Management, Economic Development, Quality Community and Environmental Focus.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

 

Recreation Services

Markham Public Library

Planning & Urban Design

Financial Services

Real Property

Strategic Initiatives

 

 

 

 

 

 

 

 

 

 

 

 

 

RECOMMENDED BY:

                                     

 

 

 

 

__________________            _____________________            _____________________

Barbara Roth                            Catherine Biss                                Steve Andrews, P.Eng.

Director,                                   Chief Executive Officer                   Director,

Recreation Services                  Markham Public Libraries               Asset Management

 

 

 

 

 

 

________________________                                   

Brenda Librecz                

Commissioner                

Community and Fire Services                                       

 

 

ATTACHMENTS:

Attachment A: East Markham Community Centre and Library – Presentation from Shore Tilbe Irwin & Partners

Attachment B: LEED “Score Card”

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q:\commission share\operation & asset management\reports\2008\asset management\facilities\EMCC&L GC Report Schematic Design– 2008-10-20.doc