Report to: Development Services Committee Date of Meeting:
SUBJECT: RECOMMENDATION REPORT
Application for Site Plan Control Approval
Ruland Properties Inc. – Phase 1
8110
and 8130 Birchmount Road
SC 08 123736
PREPARED BY:
Extension 6588
RECOMMENDATION:
That the Recommendation Report titled “Application for Site Plan Control Approval Ruland Properties Inc.– Phase 1, 8110 and 8130 Birchmount Road” be received;
That
the application for site plan control approval by Ruland Properties for two apartment
buildings be
endorsed in principle, subject to the conditions attached as Appendix A;
That
site plan approval be delegated to the Director of
That prior to final site plan approval, the Owner provides a release from the Trustee for the Markham Centre Landowners Group recommending servicing allocation for the 376 units within this project, and confirming that the applicant has met their financial obligations to the Group with respect to these lands;
That Council authorize the enactment of a by-law to remove the Hold (H)
provision on the subject lands upon execution of the Site Plan Agreement to the
satisfaction of the Commissioner of Development Services and the Town
Solicitor; and
That Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
FINANCIAL CONSIDERATIONS:
Not applicable
1. Purpose 2.
Background 3. Discussion 4.
Financial
5. Others (Environmental,
Accessibility, Engage 21st, Affected Units) 6. Attachment(s)
The purpose of this report is to
discuss and make recommendations on an application for site plan control
approval by Ruland Properties Inc. for two apartment buildings (Buildings ‘E’
and ‘F’) at the northwest corner of the Civic Mall and
The vacant, 0.745 hectares (1.84 acre)
property is located within the Remington Group’s project, on the west side of
the future extension of
Two mixed-use buildings are Proposed
Buildings ‘E’ and ‘F’ are located within the Remington Group’s project and represent the first two mixed-use buildings within phase one of the future retail core. Located on a vacant site on the west side of the Birchmount Road extension north of the Civic Mall, these two buildings continue the built form programme initiated through the previous approvals of the Rouge Bijou and Verdale apartment components of the plan (Figure 1). Both buildings include retail/commercial uses on the ground floor.
A total of 376 units are proposed
within the two buildings, including a mix of 2 bedroom (39) and 2 bedroom plus
a den (81) units. Approximately 3,274
square metres (35,242 square feet) of grade-related retail is proposed,
oriented towards
Building materials consist of a
mix of brick and precast concrete with glass railings (Figure 6). The buildings are proposed to be linked by a
glass-enclosed walkway on the second level.
Both buildings will have through lobbies with pedestrian access from the
The second floor units within both
buildings will feature a high floor to ceiling height and their exterior design
is intended to reflect the commercial base of the buildings. Certain of these units could transition to
live/work units over time. There will
also be a limited number of 2-storey units, with terraces at the 9th
floor level of Building ‘E’ oriented towards
A single access drive is proposed
off
At the
Public Meeting on the zoning amendments for the additional height, Committee
suggested staff discuss with the applicant the nature of the window displays of
the proposed retail units. The applicant has advised that the
configuration of the retail space will remain somewhat flexible until the units
have been leased. They further advise
that there is a strong interest on their part in regulating the display areas
through the condominium documents to ensure a coordinated and appropriate look
for the space as it will influence the development of the balance of their
retail core. The Town’s Sign By-law will
further control the signage and displays within the retail units.
Official
Plan and Zoning
The vacant lands are designated
“Community Amenity Area” by the
The Building Department has identified potential variances relating to loading space location, and certain setback conditions. Second parking spaces have been identified for the larger (2 bedroom plus den) units within the project which would also require relief to the by-law. Additional information has been requested to better determine project compliance. Appropriate zoning relief (if required) is a condition of Site Plan Approval. The Hold (H) would be lifted upon the issuance of Site Plan Approval.
Applicant has addressed Massing Issues
Following discussions with staff during the zoning amendment process, the applicant’s architect has incorporated a number of design elements into the elevations which includes stepping at the ninth and penthouse floor levels. The design of the southerly building ‘E’ also introduces stepping along the westerly elevation to reflect the height of the adjacent Bijou buildings which are under construction (Figure 5).
Departmental / Agency Comments
The Fire Department has no
objections, but has identified a number of specific requirements which must be
shown on the final plans, including
The Engineering Department advises that the site was pre-serviced as part of the subdivision process. Stormwater Management and Site Servicing reports have been submitted for review and the noise study requirements will need to be implemented. Comments have also been provided relating to a possible Shoring Encroachment Agreement, hydrological investigation, utilities and flow control contribution.
A Functional Traffic Design Study has been submitted and is being reviewed. Staff will explore opportunities with the applicant to provide a secondary access lane adjacent to this site to Verdale Crossing.
Servicing Allocation is Available
Through the processing of zoning
amendments and draft plan approval, the Town previously granted a servicing
allocation of 800 units to Ruland Properties Inc. Since then, an additional allocation of up to
612 units has been identified for the applicant through the Landowners Group
Agreement. To facilitate completion of the
balance of Phase 1, the applicants have also amended the Holding provisions for
another project at Highway 48 and Steeles in order to transfer approximately
301 units of allocation to Markham Centre, for a total of up to 1,713
units. To-date 1,057 units have been
accounted for through the earlier approvals of the town homes and apartment (Rouge
Bijou and Verdale) site plan applications.
Consequently, allocation is available for these buildings, subject to
confirmation from the Trustee for the Landowners Group.
Markham Centre Advisory will be Consulted
A preliminary overview on this
proposal was given to the Advisory by the applicant on
Public Art Opportunities
With the commencement of the construction of the retail core and given the interface with the adjacent Civic Mall linear park, there is an opportunity to introduce a public art component within or adjacent to this project. Staff have had initial discussions about possible public art opportunities and will continue to explore the options with the applicant.
FINANCIAL TEMPLATE:
Not applicable
ENVIRONMENTAL CONSIDERATIONS:
The applicant advises, similar to other projects within their first phase, that they will be seeking a ’Silver’ L.E.E.D. ranking. Specific comments or additional requirements which may be identified through further review by the Markham Centre Advisory will need to be addressed as a condition of Site Plan Approval, including connecting to the District Energy network.
ACCESSIBILITY CONSIDERATIONS:
There are no accessibility implications for the
Town in this report.
ALIGMENT WITH STRATEGIC PRIORITIES:
The proposed application aligns with the Town’s strategic priority of Growth Management.
BUSINESS UNITS CONSULTED AND AFFECTED:
The application has been circulated to applicable departments and agencies for comment, and their requirements have been addressed as conditions to approval.
RECOMMENDED BY:
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P. Director of |
|
Jim
Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Figure
1: Site Location
Figure
2: Area Context and Zoning
Figure
3: Air Photo
Figure
4: Site Plan
Figure
5: Elevations
Figure
6: Coloured Rendering
Appendix A – Conditions of Site Plan Approval
Q:\Development\Planning\Teams\Markham
Centre\Coordinator\Remington\Birchmount Buildings\Site Plan\Birchmount Site
Plan Report.doc
APPENDIX
A – CONDITIONS OF SITE PLAN APPROVAL
1. That prior to final site plan approval the Owner revise the site plan to comply with the applicable zoning, or shall obtain variances for by-law relief to accommodate the building programme;
2. That prior to final site plan approval the Owner provide easements respecting public access and servicing connections through the subject lands (if required) to the satisfaction of the Commissioner of Development Services and the Town Solicitor;
3. That prior to final site plan approval, the Owner shall submit final drawings including, but not limited to, site plans (which include transformer locations) and elevation drawings, an underground parking layout plan, grading, servicing and engineering drawings that comply with all requirements of the Town and authorized public agencies, to the satisfaction of the Commissioner of Development Services;
4. That prior to final site plan approval the Owner shall submit a Landscape Plan, including a detailed lighting submission, prepared by a Landscape Architect, having O.A.L.A. membership for approval by the Commissioner of Development Services;
5. That the Owner enter into a Site Plan Agreement with the Town, containing all standard and special provisions and requirements of the Town and other public agencies, prior to final site plan approval;
6. That the Owner satisfy any cash-in-lieu of parkland obligations for the apartment buildings, to the satisfaction of the Commissioner of Development Services.
7. That the Owner pay its proportionate share of development charges in accordance with Area Specific Development Charge By-laws;
8. That the location, size and construction of all refuse storage areas and recycling facilities, and arrangements for waste collection be to the satisfaction of the Town of Markham Waste Management Department;
9. That provisions for Fire Routes, yard hydrants, Siamese connections and other emergency access requirements be to the satisfaction of the Fire Department;
10. That provision for snow removal and storage, sidewalk alignment and maintenance be to the satisfaction of the General Manager of Operations and Director of Engineering;
11. That the Owner provide and implement a detailed stormwater management plan, including quality control measures/devices, as well as provide noise studies to the satisfaction of the Director of Engineering;
12. That the Owner comply with all requirements of the Town and authorized public agencies, to the satisfaction of the Commissioner of Development Services;
13. That the Owner provide confirmation
that height and lighting of the buildings meets the requirements of Transport
14. That the Owner provide and implement a TDM plan which clearly identifies above and below grade bike parking, and any other measures to promote alternative modes to the single occupant vehicle;
15. That the Owner respond to comments made by the Markham Centre Advisory and provide and implement a comprehensive Green Infrastructure plan, including connections to the District Energy network, to the satisfaction of the Commissioner of Development Services;
16. That the Owner participate in the enhanced hoarding programme, and that staff be authorized to enter into a Hoarding Agreement with the Owner;
17. That the Owner continue to
work with staff on an appropriate public art component for this project;
18. That this endorsement shall lapse and site plan approval
will not be issued after a period of three years commencing