Report to: General Committee                                           Date of Report  December 10, 2007

 

SUBJECT:                          Centennial Community Centre Sustainability Study – Green Technology Upgrades

PREPARED BY:               Mavis Urquhart, Manager, Environmental Leadership

                                            Viive Sawler, Manager, Markham Energy Office

                                            Alan Wolfe, Project Manager, Asset Management           

 

RECOMMENDATION:

THAT Markham Staff report, Centennial Community Centre Study, dated December 10, 2007, be received;

 

THAT the “Centennial Community Centre Sustainability Study" prepared by Oleson Worland_Taylor Smyth Architects be received;

 

THAT Council approve the installation of a Solar Water Heating System for Centennial Pool and replacement boilers and Domestic Hot Water (DHW) tanks instead of a green roof at Centennial Community Centre;

 

THAT Council approve tendering of the seasonal Solar Water Heating Unit for Centennial Pool and the replacement of its 2 existing gas-fired boilers and DHW tanks and associated works by Asset Management staff;

 

THAT funding, not to exceed $226,500, that was identified for Green Roof installation from the Markham Environmental Sustainability Fund (capital project #6789 - $101,500) and the Gas Tax funds (capital project #7326 - $125,000) be used for the installation of this equipment;

 

THAT the other technological improvements for energy savings for arenas and pools identified in the Study be referred to Manager, Community Centre Operations for assessment and potential future  installation in Centennial Community Centre and other community centre facilities;

 

THAT energy savings of all these retrofits be tracked by the Markham Energy Conservation Office;

 

AND THAT staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

 

 

 

 

 

 

 

FINANCIAL CONSIDERATIONS:

In 2005, Markham Council approved $125,000 from the Markham Environmental Sustainability Fund for a Green Roof on the Civic Centre. An additional $125,000 was approved for a Green Roof and/or other green technologies from gas tax funding. Current available funding is $226,500. This Staff report recommends that these funds be used for the proposed installation of a Solar Thermal Water Heating Unit for the Centennial Pool together with replacement of 2 existing gas-fired boilers and DHW tanks. Projects using 2005 the gas tax funds must be completed and receipts submitted by 2009. The total cost of the project is estimated to be $221,000 and the estimated total cost saving would be $29,293 per year. The combined simple payback of these two measures would be 7.5 years.



PURPOSE:


To report back on the installation of a green roof and/or solar panels on Centennial Community Centre, as requested by Council.


 

BACKGROUND:


In April 2006, staff reported to General Committee on the options of installing a Green Roof demonstration project at Centennial Community Centre and the Civic Centre. It was recommended that installation of a green roof on the 2nd floor of the Civic Centre (southwest wing) be the preferred option for a Green Roof. Council considered this matter and resolved:

 

“…that Town Staff engage the services of a consultant to prepare a Request For Proposal (RFP) on a green roof for the Centennial Community Centre pool area and that Town Staff also report back on costs to analyze the benefits of alternatively or in conjunction with installing solar panels in the same location”.

 

In September 2006, the Town co-hosted a Green Roof symposium with Green Roofs for Healthy Cities to find out more about green roofs and the green roof industry. One ongoing challenge with the installation of this technology has been the return on investment particularly for retrofit projects, such as Centennial Community Centre.

 

To assess the benefits of green roof and solar panel installations, as well as other “green” technologies on the Centennial Community Centre Staff retained the architects, Oleson Worland_Taylor Smyth. They prepared a sustainability report entitled “Centennial Community Centre Sustainability Study”, (Appendix 2), which contains recommendations on how Centennial Community Centre can be made a model of sustainable design and energy efficiency. These sustainable systems can be applied to other municipal facilities as well.

 

 

 

 

 

 

OPTIONS/ DISCUSSION:


In the Study, a number of potential sustainable design systems have been considered and analyzed from the perspective of practicality and “simple payback period” (time for technology to pay for itself). Energy consumption records for electricity and gas for Centennial have been reviewed to provide a context for potential cost savings. The study evaluates the environmental/energy and financial benefits for all of the following sustainable technologies and operational improvements:

 

·        Green roof

·        Photovoltaic Roofing System

·        Solar Water Heating for the Pool

·        Boiler replacements for Domestic Hot Water and Space Heating

·        Drain Water Recovery

·        Variable Speed Pump to Circulate Coolant in arena

·        Variable Speed Fan for Arena Condenser

·        Gas-fired Desiccant Dehumidifier

·        Dehumidification System for Pool

·        Flood water purification system

·        Geothermal Heating

·        Solar Wall

·        Desuperheater

·        Dry-O-Tron Dehumidifier system for Pool

 

The Savings Summary from the feasibility study (Appendix 1) compares financial/environmental benefits of these technologies at Centennial  Community Centre, including: cost of retrofit, estimated annual utility savings, annual cost savings, emissions reductions and payback. The Study states that if all the systems investigated were applied to the Centennial Community Centre, the total capital cost would be in the range of $2.0 million and the energy savings would be in the range of 45% and a reduction in the CO2 emissions in the range of 36.8%.

 

Recommended Technology

            Recommended Options

 

The study identifies options for retrofitting Centennial based upon the analysis and a payback period of less than 10 years, as follows:

 

1.                  Pool

·            Solar Water Heating for the Pool (Seasonal)

·            Replace Pool Dehumidification system at scheduled time

 

 

2.                  Arena

·            Variable Speed Pump to circulate coolant in the arena

·            Variable Speed Fan for Arena Condenser

·            Gas-Fired Desiccant Dehumidifier

·            Incorporate a Flood Water Purification System

 

3.                  General

·                        Boiler replacement for Space Heating

 

The best emission savings and financial return on investment comes from the following combination of improvements:

 

·      installing seasonal solar heating system for the Swimming Pool water

·      a new condensing boiler system to heat swimming pool water and DHW and a forced draft high efficiency boiler to heat pool area and health club

 

This technology has proven to be cost effective with a simple pay back period of 6.7 - 8.4 years with emission reduction of 154.8 tonnes of CO2.

 

 Green Roof

This study concludes that due to structural considerations only an “extensive” green roof (light weight, shallow depth, and limited variety of planting material) can be installed at Centennial Community Centre. As a result, the energy savings would be minimal. It also concludes that: the existing roof membrane is not designed for green roof insulation; the total area of the roof is not large enough to significantly effect the overall environment; and an extensive green roof on a slope provides less storm water management benefits than an intensive green roof system. Finally, Centennial Pool roof will require renovations in the near future that could affect a green roof installation. The architects conclude that investment in other comparable technologies would provide more tangible benefits, but that the green roof should still be reconsidered when the existing roof membrane is replaced.

 

Asset Management Staff advise that there are potential opportunities for a Green Roof on the new collections building at the Markham Museum, the new fire station and the Markham East Community Centre and Library.

 

In the meantime, this Staff report recommends that the Green Roof not proceed on Centennial roof at this time and that the funds identified for the Green roof be used for the proposed installation of a seasonal Solar Water Heating Unit for the Centennial Pool, together with boiler system retrofits and new DHW tanks to promote energy and Greenhouse Gas savings. Projects using the 2005 gas tax funds must be completed and receipts submitted by 2009.

 

Operational Improvements to improve Energy Consumption for the Pool and for Centennial Arena

Further, there is also an opportunity to update mechanical systems at Centennial with new technology as they reach their replacement point which will reduce energy consumption and would pay for itself in 3 to 9 years. The recommended options identified in the study include:

·        Replace Pool Dehumidification system at scheduled time

·        Variable Speed Pump to circulate coolant in the arena

·        Variable Speed Fan for Arena Condenser

·        Gas-Fired Desiccant Dehumidifier

·        Incorporate a Flood Water Purification System

 

These have been reviewed by the Manager, Community Operations and will be individually assessed for potential installation in the Centennial Community Centre and other community centres. Selected improvements could be funded through the Markham Energy Conservation Office.

 

Other Improvements for Future Consideration in Other Municipal Facilities

Some other technologies that are identified in the study that could be considered for Town facilities include:

 

·        Green Roof

·        Photovoltaic Roofing System

·        Geothermal heating

·        Solar Wall

 

Asset Management Staff will give consideration to these options for future facilities.

 

CONCLUSIONS:

The Centennial Community Centre Sustainability Study provides a comparison of sustainable technologies and energy saving improvements that can be made to Centennial Community Centre. Based upon the assessment of various technologies staff recommends that a seasonal Solar Water Heating Unit for Centennial Pool and replacement of existing gas-fired boilers and DHW tanks be undertaken. The total cost of the project is estimated to be $221,000 and the estimated total cost saving would be $29,293 per year. The combined simple payback of these two measures would be 7.5 years.


 

FINANCIAL TEMPLATE:


N/A


BUSINESS UNITS CONSULTED AND AFFECTED:

The following Business Units have been consulted:

·        Manager, Community Centre Operations

·        Finance Department

 

RECOMMENDED

                            BY:

                                      ______________________

                                      Allen Seabrooke

                                      Director, Strategic Services (Commission Lead)

 

 

                                      ______________________                         

                                      Peter Loukes

                                      Director, Operations (Commission Lead)


 

 

ATTACHMENTS:


Appendix 1                Savings Summary

Appendix 2                Centennial Community Study


 

 


 

 

APPENDIX 1

 

Savings Summary

 

 

Ref. No.

Description of Energy Saving Measure

Estimated Annual Utility Savings

Estimated Annual Cost Savings

Cost of Retrofit

Simple Payback (Years)

GHG Reduction (Tonnes)    CO2

Electricity

Gas

Electricity

Gas

Total

kWh

M3

$

$

$

4.1

Green Roof

 6,057

 

 $540

 

$540 

$290,000

 

*2.5

4.2

Photovoltaic Roofing Systems

92,160

 

$38,707

$0

$38,707

$990,000

25.6

28.0

4.3

Solar Water Heating for the Pool

 

39,994

 

$14,395

$14,395

$121,000

8.4

76.1

4.4

Replace Gas-Fired Boilers with Condensing Boilers for DHW & Pool and High Efficiency Boilers for Space Heating

 

41,392

 

$14,898

$14,898

$100,000

6.7

78.7

4.5

Drain Water Heat Recovery for Ice Melting

 

 

 

 

$0

 

 

 

4.6

Install a Variable Speed Pump to Circulate Coolant

22,491

 

$2,000

 

$2,000

$7,700

3.5

6.8

4.7

Install a Variable Speed Fan for Condenser

16,869

 

$1,500

 

$1,500

$7,700

5.1

5.1

4.8

Gas-Fired Desiccant Dehumidifier

328,000

-31,000

$29,167

-$11,158

$18,009

$150,000

8.3

40.7

4.9

Install Dry-o-Tron Dehumidification System for the Pool

 

93,823

 

$33,769

$33,769

$358,000

10.6

178.5

4.10

Incorporate a Flood Water Purification System

39,644

 

$3,525

 

$3,525

$31,000

8.8

12.1

 

SUB-TOTAL

 

 

 

 

 

$2,055,400

-- 

-- 

Rebate: Enbridge Gas

 

 

 

 

 

-$19,071

-- 

-- 

Total Estimated Savings

505,221

144,209

$75,439

$51,904

$127,343

$2,036,329

13.1

428.5

Annual Baseline Utilities (at same rates as savings) **

2,054,915

284,114

$182,729

$102,258

$284,987

Energy Only

 

27.5%

 

Percent Reduction

24.6%

50.8%

41.3%

50.8%

44.7%

 

 

 

 

 

 

 

 

 

 

 

Greenhouse Gas Emissions Summary

Electricity

Gas

 

Total

% Reduction

 

CO2 Baseline (tonnes)

625

540

 

1,165

 

 

CO2 Reduction (tonnes)

95.2

333.3

 

428.5

36.8%

 

 

 

 

 

 

 

 

 

 

* Calculations for GHG Emission Reduction for the Green Roof is based upon electricity reduction only and does not include CO2 displaced by vegetation

** Annual baseline utilities indicate how much energy  used in an average year. The estimated cost of baseline utilities is calculated using the same method as in the RATES USED FOR CALCULATIONS SAVINGS SUMMARY (next page)

                                                                                                                                               

 

 

APPENDIX 1 con’t

 

RATES USED FOR CALCULATIONS IN

SAVINGS SUMMARY

 

The hydro rate used for the savings calculations is $0.089 per kWh. This rate is calculated using Metrix™ software. It is a blended rate that accounts for consumption, demand and non-competitive energy charges.

 

There is one exception. The savings for the Photovoltaic Roofing Systems are cal­culated at $0.42 per kWh as the Ontario Power Authority will purchase renewable electricity under Ontario’s Standard Offer Program at this rate for 20 years.

 

The natural gas rate used for the savings calculations is $0.360 per m3. This rate is also calculated using Metrix™ software. This rate accounts for commodity delivery and supply load charges.

 

It should be noted that these prices reflect current energy rates. Therefore, as the rates increase in the future, the payback period will decrease.

 

CO2 and green house gas emissions have been calculated in accordance to the Canadian GHG Challenge Registry Guide to Entity & Facility-Based Reporting - v. 5.0 - April 2007.

 

Retrofit cost estimates are based on current dollars. A factor has been included for contractor’s overhead and profit. As costs may vary depending on the site conditions, a 10% construction contingency should be included for budgeting for installation.

 

The calculations of the simple payback periods for the various technologies are based on a number of assumptions and should be considered as order of magnitude only. A thorough analysis of the selected technologies will be required to determine the actual payback periods.