Report to: General Committee Date of Meeting: March 17, 2008
SUBJECT: Status of Capital
Projects as of
PREPARED BY:
RECOMMENDATION:
That the report
dated
And that $6.91M from closed capital projects be transferred to the sources of funding as listed on Exhibit A entitled “Summary of Closed Capital Projects by Account”;
And that projects listed on Exhibit B entitled “Summary of Completed Open Capital Projects Pending Payment of Final Invoices” be closed upon payment of final invoices and any outstanding amount returned to/from the original sources of funding;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
PURPOSE:
To inform Council on the status of Capital Projects as of
BACKGROUND:
As at the end
of December 2007, the Town of
· $212.15M which are projects still in progress
· $ 5.05M which are projects that are substantially completed and awaiting final invoice payment or fully committed (see Exhibit B)
CAPITAL PROJECTS TO BE CLOSED
There are 211 capital projects ($78.40M budget) recommended for closure for a total of $6.91M (Exhibit A).
STATUS OF CAPITAL AWAITING PAYMENT OF FINAL INVOICES
There are 54 open capital projects ($5.05M budget) that are completed but remain open, pending payment of outstanding invoices, as listed on Exhibit B. Upon payment of final invoices, these projects will be closed and any remaining funding will be transferred to/from the original sources of funding.
STATUS OF OPEN CAPITAL
PROJECTS
The total capital budget for open projects under 100% encumbered at
Staff has conducted a compliance review on all open capital
projects. In accordance with the Capital
Budget Control Policy Section 4.1, projects that remain inactive for a period
of twenty-four months or longer are subject to closure. The non-compliant
projects were discussed and reviewed by the business units, of which majority
of these inactive projects are closed and are included in Exhibit A “Summary of
Closed Capital Projects”.
FINANCIAL
CONSIDERATIONS:
CAPITAL PROJECTS TO BE CLOSED – EXHIBIT A
A detailed listing of capital projects with unexpended funds totaling $6.91M, to be closed upon approval of this report, is outlined in the following Exhibits:
Exhibit A “Summary of Closed Projects by Account”
summarizes where the closed capital project balances will be transferred;
Exhibit A-1 “Summary of Closed Capital Projects -
Detail” provides a detailed summary by project where the closed capital project
balances will be transferred;
Exhibit A-2 “Summary of Closed Capital Projects –
Detail, Projects that have been Fully Spent” outlines projects that have been
100% spent and therefore have no balance to return to their original funding
source(s).
Exhibit A shows three transfers to capital contingency projects, $0.23M to the capital contingency project, $0.03M to the Planning DC Contingency project, and $0.01M to the Design DC Contingency project. These transfers are made in accordance with the Capital Budget Control Policy to top-up the capital contingencies to $0.25M, $0.05M and $0.10M respectively.
The
capital contingency is funded from the closure of operating budget and Life
Cycle Replacement & Capital Reserve funded capital projects. Once the capital contingency account is at
the maximum $0.25M, further closures of operating budget & Life Cycle
Reserve funded capital projects in the amount of $0.86M will be returned to the
Life Cycle Replacement & Capital Reserve.
Similarly
to the Capital Contingency, the Planning DC and Design DC Capital Contingencies
are funded from the closure of capital projects in the Planning department to a
maximum of $0.05M and in the Design department to a maximum of $0.10M, of which
$0.03M and $0.01M will be allocated to the Planning DC and Design DC Capital
Contingency accounts respectively.
Exhibit A also includes a repayment of $0.07M
to the developer Townhomes of Thornhill Village, Inc. This relates to Project #
6151, John Street Sanitary Sewer –
In summary, the net amount $6.91M as outlined in Exhibit A to be transferred back to the original source(s) of funding is as follows:
Developer $0.07M
Planning
DC Capital Contingency $0.03M
Design DC Capital Contingency $0.01M
Total $6.91M
The majority of the projects listed in Exhibit A-1 are projects that were completed within budget. Projects that were under spent will have the balance transferred back to the original source(s) of funding. Projects with over expenditures that fall within the guidelines established in the Expenditure Control Procedures will have the necessary funds allocated from other identified closed projects.
Projects listed in Exhibit A-2 are projects that were completed on budget. Therefore, there is no surplus funding from these projects to return to their original funding source(s).
STATUS OF CAPITAL AWAITING
PAYMENT OF FINAL INVOICES – EXHIBIT B
Exhibit B, “Summary of Completed Open
Capital Projects Pending Payment of Final Invoices at
This exhibit identifies projects that are complete but still have outstanding invoices to be paid. The purpose of this Exhibit is to obtain approval at this time to close these projects, upon payment of final invoices. Obtaining pre-approval, at this time, to close fully expended/committed projects will allow for more timely and frequent closing of capital projects in the future which will lead to more efficient use of funding.
As of
The following summarizes the status of open capital:
Open Capital $212.15M
Total Encumbered $120.76M 57%
Unencumbered/Uncommitted $ 91.39M 43%
This indicates that 57% of the total approved open capital project budget is encumbered. Out of the unencumbered/uncommitted amount of $91.39M, $44.50M or 49% represent the remaining balances from the 2007 projects due to the late approval of the 2007 budget in May 2007.
Total Encumbered:
The
total encumbered of $120.76M includes commitments of $23.24M and expenditures
of $97.52M.
Commitments refer to purchase orders (
RECOMMENDED
BY: ________________________ ________________________
Barb Cribbett, Treasurer Andy Taylor, Commissioner
Corporate Services
ATTACHMENTS:
Exhibit A - Summary of
Closed Capital Projects by Account
Exhibit A-1 - Summary of
Closed Capital Projects – Detail
Exhibit A-2 - Summary of Closed Capital Projects –
Detail (Projects that have been fully spent)
Exhibit B - Summary of Completed Open Capital Projects Pending
Payment of Final Invoices at