M I N U T E S
BUILDINGS
& PARKS CONSTRUCTION COMMITTEE
2008-02-15
Attendance
Members: Councillor V. Burke Regional Councillor J. Heath Councillor A. Chiu Councillor J. Webster Regrets: Councillor C. Moretti |
Staff: S. Mintz, Deputy Fire Chief A. Seabrook, Commission Lead Sara Sterling, Special Events Coordinator B. Roth, Director, Recreation Services A. Moore, Acting Manager, Purchasing M. Shatil, Project Consultant H. Tse, Project Consultant A. Wolfe, Project Consultant A. Tari, Committee Clerk |
The
DISCLOSURE OF INTEREST
None disclosed.
1. MINUTES
OF BUILDING AND PARKS CONSTRUCTION COMMITTEE MEETING HELD ON
Moved by Councillor A. Chiu
Seconded by Councillor J. Webster
That
CARRIED
2. EVENTS
Sara
Sterling, Special Events Coordinator, distributed a list indicating the
potential 16 parks that are anticipated to open in 2008. The Committee agreed to remove “
Staff
suggested having a sign erected approximately two weeks prior to the scheduled
Park’s opening date to achieve a better attendance for the opening. Staff will work together with the Operations
Department to determine if a standard sign can be produced that would permit
changing the date and be used for each individual opening.
Ms.
Sterling reported the
The
Committee thanked Ms. Sterling for all her contributions to the Town of
Ms. Linda
Briggs, Markham Jazz Festival, addressed the Committee with respect to the use
of the Millennium Band Stand in Unionville.
Ms. Briggs advised that the Markham Jazz Festival takes place on the
third weekend of August. She would like
clarification on whether to submit an application with the Town of
Moved by
Regional Councillor J. Heath
Seconded
by Councillor A. Chiu
That
Staff report back to the General Committee outlining the procedures and policy
regarding the use of the Main Street Unionville Millennium Band Stand.
CARRIED
3. FIRE
a) Cathedral Design Issue - Mr.
Henry Tse, Project Consultant, advised the Committee there is no current update
to report and the design is proceeding.
b) Cornell – no report
4. RECREATION
AND CULTURE
a) EAST
Status Update – Allan Seabrook, Commission Lead, advised that a report will be
presented to General Committee on
b) CENTENNIAL
COMMUNITY CENTRE PROJECT
Construction
Update - Mr. Michael Shatil, Project Consultant, provided an update on the
progress of construction at the Centennial Community Centre project and an
update on the contingency budget (Appendix A).
He advised that since mid January there has been an increase in number
of trades working on site. The
Contractor has also increased the level of site coordination and assigned an
additional supernatant to the project. Mr. Shatil advised that based on the current
progress the Contractor is expected to be 92 – 94% complete by
c) GO TRANSIT PARKING
DECK
Design - Mr. Alan Wolfe, Project Consultant, advised the design work is proceeding and that GO Transit has submitted a site plan application. All the major terms for the Memorandum of Understanding (MOU) have been resolved and are currently with the lawyers to be finalized.
There was discussion surrounding the proposed size of the GO Transit parking deck.
5. CULTURE
a) Museum
Projects
NEXT MEETING
The next
meeting of the
March 28,
ADJOURNMENT
The
APPENDIX ‘A’
Construction
Contingency Report
·
INCREASED
CONTINGENCY AMOUNT $845,300
·
CONTINGENCIES
USED EXTERNALLY* $ 91,000
·
CO
APPROVED TO DATE $681,500
·
CONTEMPLATED
CO (ESTIMATE) $ 48,500
·
CONTINGENCY
REMAINING $ 24,300
* $27,000 of the
contingency spent/committed externally has yet to be back charged through a
credit CO