Report to: General Committee Report
Date:
SUBJECT: Emergency
Purchases – Winter
PREPARED BY: Paul
Ingham, General Manager,
RECOMMENDATION:
That the
report entitled ‘Emergency Purchases – Winter
That the Finance Department be authorized to increase Purchase Orders and approve purchases as per “Attachment A” in order to be aligned with the emergency invoice payments approval for winter maintenance contracts and supplies for 2007;
And that the over expenditure of $1,412,071 in account 700 504 Winter Controls, be offset by Townwide favourable variances in the 2007 Operating Budget.
And that the
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
This report has been prepared to report
to Council on the over expenditure in winter operations incurred by the
The
When preparing both tender
documents and annual budgets, the
The hired equipment required to respond to winter maintenance operations for 2007 far exceeded the estimates we had established using our four year averages. The total precipitation received in December was greater than any amounts experienced since January 1999. Conversely, the mild weather we experienced through November and December of 2006 resulted in an $ 857,107 favourable variance for winter operations at year end.
The
The winter maintenance demands on Operations staff’s time have resulted in decreased productivity in other areas. Regular activities such as sign maintenance, illumination patrols and mandatory road patrols were delayed in an effort to meet our winter level of service. Our opportunity to collect inventory for the Tangible Capital Asset project mandated by the Public Sector Accounting Board was further impacted by the increase in winter activities.
The following table is a
summary of the financial considerations for this report: |
|
||||
|
Personnel
|
Non-Personnel
|
Revenue |
Total |
|
2007 Operating Budget (Account
# 700-504) |
$
1,328,150 |
$ 4,493,855 |
-$ 601,276 |
$ 5,220,729 |
|
Total 2007 Expenditure/Revenue |
$
1,354,109 |
$ 5,757,598 |
-$ 478,907 |
$ 6,632,800 |
|
Budget Remaining / (Shortfall) |
-$ 25,959 |
-$ 1,263,743 |
-$ 122,369* |
-$ 1,412,071 |
|
*The cancellation of the winter maintenance agreement in November and December 2007 with York Region Transit for bus shelter snow removal resulted in decreased in operating costs and a corresponding revenue shortfall.
Please refer to Attachment A for a detailed schedule of the affected Winter Maintenance accounts and the corresponding Purchase Orders that require increases.
Not Applicable
RECOMMENDED BY:
________________________ ________________________
Paul
Ingham,
General Manager,
Attachment A: Cost Summary – Winter Control Account – Non Personnel