Report to: General Committee Report
Date:
SUBJECT: Award of Tender 018-T-08
PREPARED BY:
Malcolm Hann, Senior Construction Buyer
RECOMMENDATION:
THAT the report entitled “Award
of Tender 018-T-08 Markham Museum Ward Building Rehabilitation” be received;
Previously approved
capital - Museum Ward Renovation $310,000.00
2007 Capital Project # 7589 – Design North Parking Lot & Soil Testing $30,000.00
2005 Capital Project # 6602 –
2008 Capital Project #8001-Accessibility Project $50,000.00
$415,000.00
MECO Funding # 031-2220034 $55,000.00
Life Cycle and Capital Reserve $87,000.00
$142,000.00
AND
THAT the remaining balance of $61,600 to be applied to
architectural fees and disbursements as needed for the Ward building;
AND FURTHER THAT staff be authorized and directed to do all things necessary to give effect to this resolution.
The purpose of this report is to award the contract for the
construction of Markham Museum Ward Building Rehabilitation.
On
This amount will finance the building envelope improvements necessary to prevent water leakage, animal incursions, and energy efficiency and include the following items:
· Upgrade Roof including the addition of R30 insulation and a new white roof membrane
· Remove and replace deteriorated wood siding including R20 foam insulation
· Complete mould abatement work
During the design of the work, a number of additional items, that reflect Council’s priorities of improving energy efficiency, accessibility and maintenance of Town buildings, were incorporated into the project as detailed below:
The cost of this additional work is $247,000. The total cost of the project is $557,000.
The additional work was reviewed and endorsed by the Museum Board and the Building and Parks Committee.
The construction tender 018-T-08 was
issued in accordance with the
The following table is a summary of the financial considerations for this report:
Budget Available |
$ 310,000.00 $ 30,000.00 $ 25,000.00 $ 55,000.00 $ 50,000.00 $ 87,000.00 $ 557,000.00 |
073-6150-7426-005, 2007 073-5350-7589-005 Design North Parking Lot & Soil Testing 031-222-0034 MECO Funding - Deferred Revenue 2056-6150-8001-005 Accessibility Project Life Cycle and Capital Reserve Total Funding Available |
Less Cost of Award |
$ 455,400.00 |
Award to Toryork Contracting |
Less Contingency |
$ 40,000.00 |
|
Budget
Remaining |
$ 61,600.00 |
* |
* The balance of funds will be applied to
architectural fees and disbursements as needed for the Ward building.
Advertised |
ETN |
Bids closed on |
|
Number picking up bid documents |
19 |
Number responding to bid |
6 |
DETAILED
PRICING INFORMATION:
Company |
Prices
(excluding GST) |
Toryork
General Contracting |
$455,400.00 |
Orion Construction Management |
$469,500.00 |
|
$511,400.00 |
Trumbley and Hampton Inc. |
$514,000.00 |
Diciantis Construction Ltd. |
$641,500.00 |
CMF General Contracting |
$938,095.00 |
The tender was evaluated
on the selection of the lowest qualified bid and includes acceptance of
alternates 1 (add ½” glass mat faced gypsum board to exterior walls) and 2
(delete alternate roof design). The bids have been verified for accuracy and
compliance with the tender terms and conditions.
The consultant and Town
staff have checked the references of the lowest bidder and report that this
company has a good reputation in the industry and is qualified to do the work.
PROJECT SCHEDULE:
Subject to Council’s award of this tender, construction of this project is scheduled to commence May 2008 and should be completed by the end of the summer 2008, weather permitting.
None
None
None
The Finance Department has reviewed this report and their comments have been incorporated.
RECOMMENDED BY:
_______________________
Steve Andrews, P. Eng.
Director,
________________________
Peter Loukes, P. Eng.
Commission Lead,
Community and Fire Services