
Report to: General
Committee Report
Date: May 26, 2008
SUBJECT: Development Charge Transition
Rules
PREPARED BY: Kevin Ross, Ext 2126
RECOMMENDATION:
THAT the report titled “Development Charge Transition Rules” be
received:
AND THAT Council approve a transition policy for implementation of
the proposed development charge by-law amendments, as follows:
- that subdivision applicants
that have submitted all documentation required to initiate the Subdivision
Agreement, as set out in this report, on or before 14 days from the date
of enactment of the 2008 Town Wide Hard and Area Specific Development
Charge By-laws, be charged development charges based on the current 2004
bylaw rates, as indexed;
- that site plans that
have been endorsed by Council on or before 14 days from the date of
enactment of the 2008 Town Wide Hard and Area Specific Development Charge
By-laws, be charged development charges based on the current 2004 bylaw
rates, as indexed;
AND
THAT subdivision applicants that qualify for the 2004 development charge rates
be given until September 30,
2008 to register their subdivisions, failing which the 2008 by-law
rates apply.
AND
THAT site plan applicants that qualify for the 2004 development charge rates be
given until September 30,
2008 to complete the site plan agreement process and obtain a
building permit, failing which the 2008 by-law rates apply.
AND THAT Staff be authorized and directed to do all things necessary
to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
PURPOSE:
The purpose of this report is to seek Council approval for a
transition policy for implementation of the proposed development charge by-law
amendments, allowing subdivision and site plan applicants that have advanced to
a certain stage of development to qualify to pay 2004 development charge rates,
as indexed.
BACKGROUND:
Town staff are
currently in the final stages of a review of the Town Wide Hard (TWH) and Area
Specific Development Charge (ASDC) By-laws with the intention of enacting new Development
Charge (DC) By-laws prior to July
1, 2008. Staff have met with
representatives of the development industry over the course of this review where
requests have been made for the Town to consider implementation of transition
rules as a part of the DC review process.
Industry
representatives expressed concerns regarding the immediate impact of the
increased charge on development that was already sold as it would be difficult
for purchasers to pay for this increase should it be applied to the purchase
price. A transition period is a common
practice among municipalities when implementing a new development charge bylaw.
OPTIONS/ DISCUSSION:
Qualifications
for 2004 Development Charge Rates
After
considering the options, staff are recommending that subdivision applicants
that have satisfied the set of pre-determined requirements (see below and
Appendix A) to initiate a subdivision agreement on or before 14 days from the date
of enactment of the new TWH and ASDC by-laws, be charged the development charge
rates based on the current 2004 By-laws, as indexed. In addition, staff recommend that site plans
that have been endorsed by Council on or before 14 days from the date of
enactment of the new TWH and ASDC by-laws, be charged the development charge
rates based on the current 2004 By-laws, as indexed.
Time-limit on Qualification for 2004
Development Charge Rates
Normally,
once all requirements for a subdivision agreement application have been
completed and submitted, the subdivision agreement is provided to the developer
within 30 days, and executed within a month or so after that. The registration of the subdivision follows,
and generally occurs within a few months of the date of the subdivision
agreement application, although these timelines can vary significantly. Staff is therefore further recommending that subdivision
applicants that qualify for the 2004 development charge rates be given until September 30, 2008 to
register their subdivision, or they are subject to the 2008 by-law rates. Staff
also recommends that site plan applicants that qualify for the 2004 development
charge rates be given until September
30, 2008 to complete the site plan agreement process and obtain a
building permit, failing which the 2008 by-law rates apply.
Staff
is of the view that these timelines are appropriate given that the development
industry has long been aware of the current review of the by-laws. The requirements that need to be fulfilled for
developers to benefit from the current 2004 by-law rates are the submission of
the following (completeness verified by the respective departments), upon
application for a subdivision agreement:
Planning
Department
- Completed application form
- Applicable application fee in
accordance with the Town Tariff of Fees by-law
- Digital copy of Draft M-Plan
- 15 copies of Draft M-Plan with
Final Lot and Block Configuration
- 1 reduced copy of Draft M-Plan
(legal paper size)
- List of residential units &
part lots by unit type and number
- Surveyor’s Certificate including
confirmation of zoning compliance, area of lots and blocks, residential
unit types and numbers and net developable area
- Approved Archaeological Study
- Approved Street Names
Engineering
Department
·
2nd Engineering Submission with draft cost estimates
satisfactory to the Director of Engineering
·
Approved Traffic Study
·
Approved Noise Study
·
Draft R-Plans for internal and
external easements
·
Revised M-Plan to reflect the
latest engineering submission
·
Any special Engineering Conditions as identified at draft plan
approval (i.e., well monitoring, environmental issues)
Urban Design
- Preliminary Streetscape and Open
Space Landscape Plans
- Preliminary Cost Estimates
- Appraisal for cash-in-lieu of
parkland
This transition
period will allow developers whose draft plans have already been approved and
who have advanced the processing towards registration significantly, the
opportunity to finalize their applications for subdivision agreement in order
to benefit from the current (2004 by-law) DC rates. Site plans that have been endorsed will
benefit from the current DC rates as well.
FINANCIAL CONSIDERATIONS
The development charges currently being reviewed (TWH and ASDC) are
collected to recover infrastructure costs required by the Town. By collecting development charges at the current
(2004 by-law) rates for applications that satisfy the requirements set out above,
the Town’s cash flow will be impacted in the short term, but this ultimately
will not result in a loss of development charge revenue.
The Town will collect less revenue from draft plans that are
submitted for subdivision agreements and endorsed site plans during this period,
however this shortfall will be recouped in the next update of the DC by-laws.
ENVIRONMENTAL CONSIDERATIONS:
Not applicable.
ACCESSIBILITY CONSIDERATIONS:
Not applicable.
ENGAGE 21ST CONSIDERATIONS:
Not applicable.
BUSINESS UNITS CONSULTED AND AFFECTED:
Legal Services and Planning Department.
RECOMMENDED BY:
________________________ ________________________
Barb Cribbett Andy Taylor
Treasurer Commissioner,
Corporate Services
Att: Appendix A – Subdivision Checklist