Report to: General Committee                                      Report Date:  May 26 , 2008                  

                                                                                                                                                 

 

 

SUBJECT:                          BIA Streetscape Services

PREPARED BY:               Mark Ingwersen, District Manager, Operations

                                            Andrea Tang, Manager, Financial Planning

 

 

RECOMMENDATION:

 

THAT the report dated May 26, 2008 entitled “Streetscape Services” be received;

 

AND THAT the report dated May 5, 2008 entitled “Streetscape Services” be disregarded and be replaced with this report;

 

AND THAT the 2007 Markham Village and Unionville BIAs financial statements reflect payments of the streetscape services as approved in the 2007 budget in accordance with the tax levy by-law;

 

AND THAT the Treasurer be directed to work with the BIAs to develop a repayment schedule extended beyond the current year, if required;

 

AND THAT in the event that the Markham Village and Unionville BIAs request the current service level, Staff recommend that Option 4 b) be adopted with BIAs subsidizing the cost of materials over and above the current streetscape average service level provided for in the Yonge Street and Victoria Square areas;

 

AND THAT the 2008 streetscape fee for the Markham Village BIA be $14,685 and the Unionville BIA be $9,955 which reflects 100% recovery for the costs of additional materials; 

 

AND THAT the recoveries from the BIAs be subject to annual CPI inflationary increases and adjusted as required during annual Budget review;

 

AND THAT the Operations/Parks Department 2009 revenue budget be reduced by $7,800 to reflect this whole year adjustment;

 

AND THAT should Council approve a service level resulting in a reduction in the number of units on the BIA Main Streets, the surplus units for 2008 be disposed of as provided for in the Purchasing Bylaw;

 

AND THAT the Operations 2009 Budget be adjusted to reflect the approved service level;

 

AND THAT Staff will meet with the BIAs in the fall of 2008 to discuss the 2009 Streetscape program;

 

AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

The Markham Streetscape program started in 1978 at the Markham Village Main Street and similar program started at the Unionville Main Street in 1984.  Since then, the program has expanded to include other areas in the Town.

 

The BIAs had been partially subsidizing the Streetscape program by contributing $22,000 from the Markham Village BIA and $10,440 from the Unionville BIA towards the costs of materials.  Other related costs, such as the labour for planting, costs to grow and maintain were included as part of the Town’s annual operating budget totaling to approximately $78,800.

 

Staff prepared a report to General Committee dated May 5, 2008 entitled “BIA Streetscape Services”.  The May 5, 2008 report was deferred to allow Staff to meet with the BIAs to discuss and review each party’s position. The meeting took place on         May 9, 2008.  As a follow-up to the meeting, both BIAs had emailed the Town outlining their views on the Streetscape Services.

 

In the event that the Markham Village and Unionville BIAs request the current service level, Staff recommend that Option 4b be adopted with BIAs subsidizing the cost of materials over and above the current streetscape average service level provided for in the Yonge Street and Victoria Square areas.  Staff will meet with the BIAs in the fall of 2008 to discuss the 2009 Streetscape program. 

 

In the event that the Markham Village and Unionville BIAs request an increase in service levels, BIAs will subsidize 100% of all costs incurred by the Town over and above the approved standard service level.

 

In addition, the BIAs are requesting that the Town write-off the 2007 Streetscape Services charges of $22,000 to the Markham Village BIA and $10,440 to the Unionville BIA.  It is recommended that the Treasurer be directed to work with the BIAs to develop a repayment schedule extended beyond the current year, if required.

 

PURPOSE:

To prepare an information report to General Committee detailing the history, rational and funding options for the existing charges for streetscape baskets/barrels/planters to the Unionville Main Street BIA and Markham Main Street BIA.

 

BACKGROUND:

A Markham Streetscape program was initiated in 1978 with Markham Main Street and has expanded to include a variety of other areas over time. In recent years, staff has received an increasing number of requests for horticultural streetscape enhancements, resulting in a total number of 2,652 baskets/barrels/planters (Appendix A) in 2007. The following is a brief overview of how the program has expanded:

 

·        1978 - The Streetscape program was initiated on Markham Main Street because of lack of space for shrub/annual beds. The cost of the materials was subsidized by the BIA and continues to be today

·        1984  - The Unionville Main Street Streetscape was initiated and the cost of materials was subsidized by the BIA and continues to be today

·        1984 - The Thornhill Main Street Streetscape Program was implemented on Yonge Street. Until 2002, the cost of the materials and maintenance on the west side of Yonge Street was subsidized by the City of Vaughan. Currently, the City of Vaughan is responsible for the supply, installation, and maintenance of the streetscape on the west side of Yonge Street, while the Town of Markham continues to supply, install and maintain the east side.

·        1994 - The Milliken Streetscape Program was implemented on Kennedy Road to beautify the Milliken Mills area.  For several years the streetscape was subsidized approximately $1500 yearly from an annual compost sale organized by the local Ward Councillor.  The Town has not hosted this compost sale event since 2002.

·        1999  - Community Centres were included in the program at the request of the Recreation Department

·        2000  - 2002  The Milliken Streetscape Program was expanded including Denison Street and Kennedy Road

·        2003  - Town Streetscape Program was expanded with units being added in Milliken Mills and implemented in Victoria Square

·        2004  - A total of 2,180 basket/barrel units in the program

·        2005 - 472 baskets/barrels added to Milliken area – Ward 7 on Denison and on Middlefield Road at a cost of  $128,000

·         2005 – report to Council resulted in direction to Development Services Staff to initiate a Milliken Main Street Study and that no additional baskets or barrels be considered until the study was completed and presented to Council

·        2008 – inventory is unchanged from 2005 at 2,652 barrels/baskets/planters

 

Through the 1980’s the Town responded to requests and provided additional barrels and baskets for Unionville BIA with no additional charges for materials which is reflected in the inequity of current charges to each BIA for this program.

 

MARKHAM VILLAGE & UNIONVILLE BIAs COMMENTS

 

Below is an excerpt of the email from the Markham Village BIA that outlines the Markham Village BIA’s proposal on the Streetscape Services:

 

“At the meeting a number of issues were discussed, and I believe everyone made a sincere effort to understand each other's positions. We appreciate now the history of the program extending back to 1978, the year after the Markham BIA was founded, how the program grew over the years, often in an informal manner, to the final expansion of 472 units in 2005 to its present level of 2,652 units. The report also lists other service items which the town provides within the BIAs. On the other hand the BIAs feel that many items have not been mentioned in the report which would emphasize the contribution that the BIAs have brought to the community, and the economic and cultural life of the Town. Also, the dramatic growth of the town since 1978 has created significant challenges for the businesses in the existing BIA heritage areas, and the funds that the BIA receives are raised through a specific tax levy on the business properties in the BIA for the BIA's use in promoting the area.

 

Primarily however,  it simply comes down to this – the BIAs feel that it is not fair for the BIAs to pay for a service that is being provided for free, in much larger quantities, in other areas of the Town of Markham where there is no BIA. The report details in fact even heighten the sense of unfairness that the BIAs feel, because the BIAs were the original partners in this program and agreed, in the beginning to pay for it out of their BIA levy. However, all of the expansions in the service that occurred over the years have been funded by the Town. At present, the BIAs receive less than 30% of the service, yet are the only paying customer. This is what is unfair, especially since 2002 when other funding sources dropped out. In June 2005 the UBIA raised this issue in council, and have appeared at budget meetings since then, and they have been rebuffed. We could go on forever about the quantities, history, when, why, how, etcetera, yet the fact remains that the BIAs feel they have not been treated fairly and no amount of discussion or lecturing is going to change that. There is also a significant power and financial imbalance that the BIAs are at a disadvantage in.

 

We therefore appreciate the opportunity to present an option that the BIAs will accept, and that the Town can financially handle, and that deals on a going forward dynamic, in a good faith effort to avoid having the matter escalate to a level that will benefit no-one. Hopefully this option can not only be included in the report to council but can be endorsed. 

 

Option:  

1.      MBIA and UBIA will not budget for any botanicals for 2008. We are prepared to let the town determine what an appropriate level of service is for these two heritage areas.  

2.      That the Town forgives the Botanical charge for 2007 to the BIAs. In this event, the BIAs will not seek reimbursement for years prior to 2007, in order that we can all focus on the future. While many in the BIAs may feel we should be entitled to go back to prior years, this option only deals with the one year that payment has not been specifically authorized for. It is important to remember that nobody is getting  everything they want

3.      That the town direct staff to meet with the BIAs onsite early in the fall of 2008 - before the flowers are removed - to discuss and negotiate the streetscape program for 2009, as with most businesses relationships.

4.      That the town establish a committee with representatives from various town departments - culture, economic development, BIAs, parks & roads, council, and the community, for example, that is charged with assessing the roles and relationships of a BIA within the town of Markham, and with providing recommendations on how those roles can be improved. It is my own view that the Town is missing opportunities to use the BIA structure in other business areas, not only in heritage areas but in brand new developments as well. A BIA can be used to enhance the service levels that the town provides in those areas from street visuals to security, and can encourage the creation of distinct commercial areas and communities.”

 

Below is an excerpt of the email from the Unionville BIA that outlines the Unionville BIA’s proposal on the Streetscape Services:

 

“Firstly, the Unionville BIA would like to thank the Town of Markham and its staff for the incredible work done in beautifying our Town. In particular, we feel that Markham’s annual flower program creates an unforgettable visual highlight for visitors to our Town and is a source of pride for all citizens. However, the Unionville BIA would like to advise the Town of some problems with the program which need to be addressed.

 

Since flowers were originally placed along Main Street Unionville in 1984, the Unionville BIA has contributed to the Town flower program in the understanding that everyone was contributing for flowers in their respective areas. In 2005, however, the Unionville BIA discovered that this was not the case. The Town's flower program had expanded with new flowers in other areas of the Town, which were paid for as part of the Town’s flower budget. The Unionville BIA raised this matter before Council in 2005 when Council was approving another expansion of its Town-wide flower program, and again, at the beginning of the 2007 budget year, but had not received any reports back on this issue until this year. In the meantime, the Unionville BIA has continued to make its annual contribution to the Town-wide program.

 

The Unionville BIA discovered that this unfairness has actually existed from the onset (since 1984) when the business section along Yonge Street in Thornhill received Town flowers at Town expense with no contributions made from local businesses or associations. Currently, flowers are distributed, at Town expense, to other wards across Markham in numbers which dwarf those distributed in Ward 3, let alone the Unionville BIA district. Given the quantities provided in other areas, it is also clear that Unionville's Main Street does not receive an augmented flower treatment. Furthermore, it is now apparent that the Unionville BIA has also been "billed" for flowers placed well outside the Unionville BIA district.

 

Regardless; because this has grown to become a Town-wide flower program; and, because this has become a regular Town expenditure across Markham; and, because the Town does not receive contributions from any other associations for flowers in other parts of the Town; it is unfair for the Unionville BIA and the Markham BIA to continue to subsidize this town-wide program.

 

To remedy this unfairness, the Unionville BIA could seek repayment of our contributions made since the Town first started paying for flowers in other areas. However, in working with our "sister" BIA in Markham, we ask instead that the Town simply return the amount taken from our BIA accounts to subsidize the Town-wide flower program in 2007; and, that from 2008 forward, the Town place flowers in Unionville and Markham Village with whatever flowers that Town staff deem appropriate at Town expense, as is the case in all other parts of Town.

 

The Unionville BIA is eager to quickly remedying this matter so that we may all continue to admire the incredible work done by the Town in beautifying Markham in a fair and equitable manner.”

 

OPTIONS/ DISCUSSION:

Baskets and barrels are one of the most expensive way to improve the aesthetics of any area.  They were originally implemented on the 3 Main Streets (Unionville, Markham and Thornhill) because there was no room to do anything in the way of traditional flower beds.  Because of the popularity of the program, a number of Councillors asked for it to be expanded into their wards, and these requests were approved by Council.  As most of the current baskets and barrels outside of the 3 traditional main streets are on residential and backlotted streets, there is really no way to extract funding from any one group to cover the costs. 

 

The BIAs have traditionally paid for the cost of the materials, although the fees charged to the BIAs have not increased since the inception on a per unit basis.  The Markham BIA pays $22,000 and the Unionville BIA pays $10,440 toward the cost of materials.   The cost to the Town to supply, plant and maintain these two Main Streets’ streetscapes is approximately $78,800.00 (Appendix B-2 for detailed calculation).  This includes labour for planting, costs to grow them, placing them out and removing them from the Main St., weeding, deadheading and daily watering during the growing season.

 

 

Location

Streetscape Area (lineal metres)

Total number of units

Average Spacing of units (lineal metres)

 

Main StMarkham

(both sides)

930

405

8.2

Main St – Unionville (both sides)

871

274

8.6

Denison / Kennedy / Middlefield                         (one side)

8260

1256

58

Yonge Street                (one side)

630

176

17.4

Victoria Square

(both sides)

1592

216

33

 

.

 

 

 

Average Spacing based on:

(lineal metres)

Main Streets – Markham & Unionville

8.5

Denison/Kennedy/Middlefield, Yonge Street & Victoria Square (Non Main Street)

36

Yonge Street & Victoria Square

25

 

The Main Streets’ baskets and barrels are placed in greater densities and directly benefit the businesses, and that is why they originally requested them and agreed to pay a portion of the costs.  The average spacing between baskets/barrels on the two BIA Main Streets is 8.5 metres apart.  In the streetscaped areas other than the Main Streets the average spacing is 36 metres apart.

 

In addition, the Main Streets get an additional barrel at each pole (3 instead of 2), as well as pole boxes/bridge boxes.  They also get a large number of standards (tall grafted plants in the centre of the barrels such as solanum or fuchsias) in the barrels.  The Main Streets also receive a higher standard of maintenance than the streetscapes outside the traditional Main Streets which includes increased litter and garbage cleanup and the baskets and barrels are weeded and deadheaded more often.  

 

The current cost for materials is $37.00 for a hanging basket and $72.00 for a barrel for an average cost of $55.00 per unit (Appendix B-1).  On a per unit basis, there is an inequity in the amount that Unionville Main Street and Markham Main Street pays.  Main Street Markham BIA pays approximately 98% (actual total costs $22,275 vs. recovery from BIA $22,000, Town subsidizing $275) of the current cost of materials (Appendix B-3 for detailed calculation).  However, in the case of Main Street Unionville, the BIA is paying only approximately 69% (actual total costs of $15,070 vs. recovery from BIA $10,440, Town subsidizing $4,630) of the cost of materials (Appendix B-4 for detailed calculation).

 

Staff considered the following options when preparing this report.  All options assume the BIAs will reimburse the Town for the costs of materials only.

 

 

 

 

 

 

 

 

 

 

 

Option 1: Status Quo

The Main Streets will continue to partially subsidize the Streetscape Program at traditional levels, however this will continue to foster the existing financial inequity between these 2 Main Streets.  The Town would continue to pay a portion of the unsubsidized material costs and 100% for the cost to grow and maintain.

 

Service Level:                           Maintain

Change in number of units:        No change

Financial Impact to BIA:           Markham BIA $22,000 (no change)

                                                Unionville BIA $10,440 (no change)

Financial Impact to Town:         No budget impact; however, the Town will continue to subsidize $4,905  for the cost of materials ($275+$4,630) (Appendix B-5)   

 

Option 2:  BIAs to pay the full cost of all materials based on current inventory and market price

The costs of materials to the BIAs have not increased since inception.  Based on the current market price, the revised costs to the BIAs would be $22,275 for Markham Village and $15,070 for Unionville.  The Town would continue to pay 100% for the cost to grow and maintain.

 

Service Level:                           Maintain

Change in number of units:        No change

Financial Impact to BIA:           Markham – cost increase of $275

                                                (from $22,000 to $22,275)

Unionville – cost increase of $4,630

(from $10,440 to $15,070)

Financial Impact to Town:         Increase in revenue by $4,905

 

Option 3 a):  Provide Service Level based on average of Non Main Street spacing The Operations Department would provide two baskets and two barrels per pole, spaced 36 metres apart based on the Town wide average for all other streetscaped areas, at no cost to the BIA. 

 

Service Level:                           Decrease

Change in number of units:        Markham - Reduce by 304 units (from 405 to 101)

                                                Unionville – Reduce by 205 units (from 274 to 69)

Financial Impact to BIA:           Markham – cost reduction of $22,000

                                                Unionville – cost reduction of $10,440

Financial Impact to Town:         Reduction in revenue by $32,440 ($22,000+$10,440)

                                                Potential reduction in operating costs by $62,995

(cost of materials – 509 units x $55/unit = $27,995)

(greenhouse lease $35,000)

 

 

Option 3 b):  Provide Service Level based on average of Yonge Street/Victoria Square spacing

The Operations Department would provide two baskets and two barrels per pole, spaced 25 metres apart, as in the average spacing in the Victoria Square/Yonge Street streetscaped areas, at no cost to the BIA.

 

Service Level:                           Decrease

Change in number of units:        Markham – Reduce by 267 units (from 405 to 138)

                                                Unionville – Reduce by 181 units (from 274 to 93)

Financial Impact to BIA:           Markham – cost reduction of $22,000

                                                Unionville – cost reduction of $10,440

Financial Impact to Town:         Reduction in revenue by $32,440 ($22,000+$10,440)

                                                Potential reduction in operating costs by $54,640

(cost of materials – 448 units x $55/unit = $24,640)

(greenhouse lease $30,000)

 

*Potential reductions in operating costs identified in Options 3a & 3b assume that program has not commenced.

 

*Currently five (5) crews water approximately 530 units daily.  If a threshold reduction target of 450 units is achieved, further reductions in Operating costs possible through elimination of one watering crew.

                                               

Option 4 a):  Provide current Service Level and invoice based on Non Main Street average spacing

The service level noted in Option 3 a) will be provided by the Town with no cost to the two BIA’s.  Should the BIAs require the current service level, the BIAs will pay the full cost of materials for the additional units.  The additional units represent an increase of approximately 4 times the density of Town wide average outside these Main Streets.  Based on current pricing, this would result in total costs of approximately $16,720 to the Markham BIA and approximately $11,275 to the Unionville BIA for 2008.  These recoveries will be subject to annual CPI inflationary increases and adjusted as required in subsequent years.  The Town would continue to pay 100% for the cost to grow and maintain.

 

Service Level:                           Maintain

Change in number of units:        No change (at the discretion of the BIA in determining the number of units, currently assumes the same number of units)

Financial Impact to BIA:           Markham – cost reduction of $5,280

                                                Unionville – increase of $835

Financial Impact to Town:         Decrease in revenues by $4,445

                                                No change in operating costs

 

 

 

Option 4 b):  Provide current service level and invoice based on average of Yonge Street/Victoria Square spacing

The service level noted in Option 3 b) will be provided by the Town with no cost to the two BIAs.  Should the BIAs require the current service level, the BIAs will pay the full cost of materials for the additional units.  The additional units represent an increase of approximately 3 times the density of Town wide average outside these Main Streets.  Based on current pricing, this would result in total costs of approximately $14,685 to the Markham BIA and approximately $9,955 to the Unionville BIA, for 2008.  These recoveries will be subject to annual CPI inflationary increases and adjusted as required in subsequent years.  The Town would continue to pay 100% for the cost to grow and maintain.

 

Service Level:                           Maintain

Change in number of units:        No change (at the discretion of the BIA in determining the number of units, currently assumes the same number of units)

Financial Impact to BIA:           Markham – cost reduction of $7,315

                                                Unionville – cost reduction of $485

Financial Impact to Town:         Decrease in revenues by $7,800

                                                No change in operating costs

 

 

Summary

The Operations Department recommends that option 4 b) be adopted by Council for both the Markham and Unionville BIA’s.  This option will provide each BIA with the average level of service established in both Yonge Street and Victoria Square free of charge.  The full cost recovery for the additional units will remedy the current inequity between what the two BIA’s are currently charged for the streetscape program and allow them to continue to enjoy the greater intensification of units than currently provided in other areas of the Town.

 

Regardless of the option considered, staff recommends that the basket and barrel inventory be capped at the current number of units and that no additional baskets/barrels be considered on the Main Streets. 

 

In the event that the Markham Village and Unionville BIAs request an increase in service levels, BIAs will subsidize 100% of all costs incurred by the Town over and above the approved standard service level.

 

Disposal of 2008 Surplus Units

Should the level of service approved by Council result in a reduction in the number of units required for 2008, staff be authorized to dispose the 2008 surplus units as provided for in the Purchasing Bylaw.

 

In addition, the Operating Budget for 2009 will be adjusted to reflect the Council approved level of service in the Markham and Unionville BIA districts.

Other In-Kind Services provided by the Town

In addition to the maintaining and growing of the baskets and barrels, the Town of Markham also provides the following enhanced services for the Main Street Markham and Unionville BIAs:

·        Street Sweeping – both Main Streets are swept once per week from May to October, compared to average of 4 times per year for all other Town roads.

·        Special EventsOperations staff time, equipment and materials to support special events including; litter pick-up/disposal; traffic control signs and barricades; boulevard flushing; etc.

·        Garbage and Litter – litter is picked daily during the summer and 3 times/week at other times and waste receptacles are emptied  3 times/week, compared to once every 2 weeks for litter pickup and once per week for waste receptacles across Town.

·        Snow Removal – all snow on entire sidewalks and boulevard systems within the two Main Streets.  This is done using small loaders and all snow is hauled away in dump trucks at a cost of $5,000 per occasion for Unionville and $8,900 per occasion for Markham.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

Based on Staff recommendation in adopting option 4b, the 2008 streetscape fee for the Markham Village BIA is $14,685 and the Unionville BIA is $9,955 which reflects the 100% recovery for the costs of additional materials.  The Operations/Parks Department 2009 revenue budget be reduced by $7,800 to reflect this whole year adjustment.

 

Staff recommends that the 2007 Markham Village and Unionville BIA financial statements reflect payments of the streetscape services as approved in the 2007 budget in accordance with the tax levy by-law; therefore, the cost of streetscape services for the Markham Village BIA be $22,000 and Unionville BIA be $10,440.  It is recommended that the Treasurer be directed to work with the BIAs to develop a repayment schedule extended beyond the current year, if required.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Not Applicable

 

 

 

 

 

 

 

 

 

 

 

 

 

RECOMMENDED BY:  

 

 

________________________                                                ________________________

Paul Ingham,                                                                             Peter Loukes,

General Manager, Operations                                                   Commission Lead, Community and Fire Services

 

 

________________________

Joel Lustig,                                                                              

Director, Financial and Client Services

 

 

ATTACHMENTS:

Appendix A – Streetscape Inventory 2008

Appendix B – Total Town Costs in providing Streetscape Services to BIAs & % Material Recovery from BIAs

 

 

 

Q:\Commission Share\Operations and Asset Management\Reports\2008\Operations\Parks