Report to: General Committee Report
Date:
SUBJECT: Award of Tender
PREPARED BY: Prathapan Kumar, Ext. 2989
Amit Sobti, Ext. 2239
THAT the report entitled “Award of Tender 043-T-08 Steeles Avenue East Watermain Replacement (Phase 2) from Henderson Avenue to Bayview Avenue” be received;
AND THAT the contract for
AND THAT a separate purchase order in the amount of $96,587.75 exclusive of GST be issued for
contingency to cover any additional fees and that the Director of Asset
Management be authorized to approve expenditure of this contingency amount up
to the specified limit in accordance with the Expenditure Control Policy;
AND THAT
staff be authorized to retain a qualified geotechnical consulting firm in
accordance with the Town’s purchasing bylaw to provide geotechnical and
materials testing services during construction for an upset limit of $7,000.00
exclusive of GST;
AND THAT the award be funded from the 2008 Waterworks Department Capital Project 053-6150-8435-005 Watermain Construction/Replacement; in the amount of $1,350,000.00;
AND THAT
upon payment of all the invoices, the remaining funds in the amount of
$280,534.75 be returned to the original funding source;
AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.
The purpose of
this report is to obtain Council approval to award contract 043-T-08, Steeles
Avenue East Watermain Replacement (Phase 2) from
The Town is proposing
to replace the existing aging municipal watermain on
Watermain Improvement
Program to systematically replace and upgrade deficient watermain to improve
supply capacity and reliability. The
existing watermain situated along these areas is one of the older watermain in
the Town of
Advertised |
ETN |
Bids closed on |
|
Number picking up bid documents |
12 |
Number responding to bid |
7 |
DETAILED
PRICING INFORMATION:
Company |
Prices
(excluding GST) |
Hollingworth
Construction Co. |
$ 965,877.50 |
Trisan Construction |
$1,101,262.00 |
|
$1,199,567.43 |
F.C.M. Construction Ltd. |
$1,239,975.00 |
F.D.M. Contracting Co. Ltd. |
$1,322,098.53 |
Finch Paving (1993) Inc. |
$1,555,126.50 |
Co-X-Co Construction Ltd. |
$1,558,192.00 |
Note: Prices are exclusive of
GST and have been verified for accuracy and compliance with the tender terms
and conditions.
Council has approved the Waterworks
Department Capital Project 053-6150-8435-005 Watermain Construction/Replacement
for the construction of the Steeles Avenue East Watermain Replacement (Phase 2)
from
|
The proposed watermain replacement would reduce the number of watermain breaks, which would minimize the risk of water system contamination.
Not applicable
The proposed watermain replacement supports the corporate goal related to infrastructure management, which is “to build, renew and strategically manage the Town’s infrastructure to meet the demands and expectations of a growing community”.
The Finance Department has reviewed this report and their comments have been incorporated.
RECOMMENDED
BY: _____________________ BY: ________________________
Steve Andrews, P.Eng. Peter Loukes, P. Eng.
Director of Asset
Management Commission Lead
Attachment “A” - Key Plan