Report to: General Committee                                                          Report Date: June 3, 2008

 

 

SUBJECT:                          Proposed 2008 Town Wide Hard and Area Specific Development Charges

PREPARED BY:               Kevin Ross, Ext 2126

                                           

 

 

RECOMMENDATION:

THAT the report “Proposed 2008 Town Wide Hard and Area Specific Development Charges” be received;

 

THAT the summary responses to the comments from the public and the development community be received for information;

 

THAT the policy excluding local services from the calculation of development charges, with the exception of East Precinct and South Unionville–Helen Avenue be approved;

 

THAT no further public meeting is required under Section 12 of the Development Charges Act 1997;

 

THAT the minutes of the May 27, 2008 Development Charges Public Meeting be approved;

 

THAT Council approve the development charge background study prepared by Hemson Consulting Ltd. dated May 2008;

 

THAT it is Council’s intent to ensure that the increase in the need for services to service anticipated development will be met;

 

THAT it is Council’s intent that infrastructure related to post 2021 development identified in the background study shall be paid for by development charges or other similar charges;

 

THAT Council recognizes that there are operating costs associated with the implementation of the capital program;

 

THAT the Town Wide Development Charge By-law and the Area 4 Don Mills/Browns Corner Industrial Area Specific Development Charge By-law include a clause that sets out the development charges payable by East Markham Non-Profit Housing Inc, at the 2004 by-law rates, indexed to January 1, 2008;

 

THAT the Town of Markham Development Charge By-laws, as amended, be brought forward to the June 10, 2008 Council Meeting for adoption by Council;

 

AND THAT staff be directed to do all things necessary to give effect to this report.

 

 

 

 

EXECUTIVE SUMMARY:

 

Staff commenced the review of the Town Wide Hard and Area Specific development charge by-laws due to the actual costs of property and capital works exceeding the amount the Town was able to recover under the 2004 by-laws.  This imbalance started to erode the development charge reserves and led to the decision to open the by-laws.

 

During this process, it was decided to transfer selected costs from an area specific recovery basis, to a Town Wide recovery basis as it (1) better reflects the benefiting areas and (2) provides a more efficient and fiscally viable method of recovering growth-related costs. 

 

Throughout the review process, staff held consultative meetings with the development industry and responded to their concerns while providing updates to the Development Charges Sub-Committee and General Committee. 

 

The draft Background Study and by-laws have been prepared and the legislated public meeting held on May 27th, 2008 where developers were provided with a forum to raise their concerns about the proposed development charges and policy changes.

 

In staff’s view, the proposed development charges and by-laws are based on Town policies and established existing service levels, and will be defensible at the Ontario Municipal Board should the by-laws be appealed.

  

PURPOSE:

The purpose of this report is to update Council on the proposed changes to the information, assumptions, and rates in the draft May 2008 Town of Markham Development Charges Background Study, and to obtain General Committee’s approval to forward the revised Development Charge rates and Development Charge by-laws to Council on June 10, 2008 for approval.

 

BACKGROUND:

 

The review of the current Town Wide Hard and Area Specific Development charge By-laws commenced in late 2006, in response to increasing expenses for capital works and property costs in excess of that projected, and being collected, in the 2004 Development Charges Background Study.  In the spring of 2007, a Development Charge Sub-Committee was formed, and a number of policy issues and cost implications were reviewed over the course of the summer 2007.  In the fall of 2007, the consultation with the development community began, and through the fall of 2007 and first quarter of 2008, there were 4 updates provided to the Developers Round Table, 4 meetings held with a subcommittee of developers interested in the Town Wide Hard By-law (TWH Developer Subcommittee), and over 32 meetings with area specific developers groups.

 

 

 

Town Wide Consulting Process

 

The TWH Developer Subcommittee, along with their consultants, have participated in a number of meetings with staff to review in detail their issues and comments to the changes in the Town’s development charge recovery process.  In addition, developers participating in the consultative process for the area specific development charges also had questions related to Town Wide Hard (TWH) charges.  Developers were asked to submit final comments on any issues by March 12th, 2008. 

 

The primary issues relating to the TWH development charge recovery process which were subsequently addressed by staff were:

 

  I.      Issues - Pre-Public Meeting Consultations

1)      Initial calculations were done using a growth forecast period to 2021 – The developers suggested using a longer horizon in order to reflect full build-out of the Town within the current urban boundary

2)      The Town utilized 2001 census data to calculate the growth forecast – The developers suggested using the 2006 census data

3)      Relatively high cost of high density units – the distribution of costs driven by the person per unit (PPU) was weighted in favour of the lower density units 

4)      Concern with the transfer of costs from Area Specific to TWH, specifically:

o       Service level equity (i.e. enhanced streetscapes)

o       The allocation of the reserve funds be based on the 2004 bylaws rather than the proposed 2008 costs

o       Treatment of credit agreements outstanding

o       Difficulty in administering current Developers Cost Sharing Agreements

5)      Limited exemption – The developer who qualified for this exemption under the 2004 DC by-laws believes that lot levies paid, the cost of servicing their lands and upgrades to Leslie Street intersections in 1988 should be recognized and continued to the original expiry date of August 31, 2009

6)      Post period benefit – The developers were of the opinion that some of the structures included should be for the benefit of future growth

7)      Administration fee on land acquisition – the quantum of the fees were seen as being too large.

 

Staff Response & Revisions:

Town staff reviewed the issues raised as a result of the consultative process and made the following adjustments to the methodology used in the calculation of the development charge:

1)      The growth forecast was adjusted to 2031 to reflect full build-out within the current urban boundary, which corresponds to the Town’s infrastructure plan.  6,900 housing units are added to the forecast as a result

2)      The 2006 census data which became available during the process was used to calculate the growth forecast

3)      The person per unit (PPU) was calculated using the 2006 census data and resulted in a shift of the cost away from high density units

4)      Concerns with the transfer of costs from the ASDC to Town Wide Hard were addressed by:

·        Retaining cost for increases services within Markham Centre (i.e. enhanced streetscapes - $4M) for service level equity

·        The reserve fund allocation was calculated based on the 2004 bylaws

·        Developers were reassured that credit agreement and other claims related to works completed will be discussed after the passage of the by-law

5)      Staff recommended that the Limited Exemption on Non-Residential Developments continue until August 31, 2009 to coincide with the natural expiry of the 2004 by-laws

6)      Staff reviewed the structures included and applied a post period benefit to selected Highway 404 mid-block crossings

7)      The administration fees were reviewed and reduced to more appropriately reflect the costs of overseeing land acquisitions.

 

These revisions were communicated to the developers and presented to the General Committee on April 21st, 2008. The resolution setting out the direction to staff is attached as Appendix A.  Based on this direction, the mandatory development charge background study was prepared, and the mandatory public meeting scheduled.

 

OPTIONS/DISCUSSION:

On May 27, 2008, a public meeting was held dealing with proposed Development Charge rates and by-laws, in accordance with the Development Charges Act, 1997. A number of written submissions were received, and some verbal presentations were made.  The following is the extract from the Public Meeting:

 

It was noted that this Public Meeting was held under section 12 of the Development Charges Act and that Notice of the Development Charges Public Meeting for this date was published in the Markham Economist & Sun and Thornhill Liberal on May 1, 2008.

 

Committee received a copy of a report titled DC Transition Rules that was approved by General Committee on May 26, 2008

 

Mr. Craig Binning, Hemson Consulting Ltd., provided a presentation on the proposed development charges by-laws. Mr. Binning provided some background on the Development Charges Study and the proposed changes to the Development Charges regime. It was noted that only the Town Wide Hard and Area Specific Development Charges will be impacted.

 

Committee sought clarification on the changes and were advised that some increases to the Town Wide Hard Developments Charges are offset by decreases in the Area Specific Development Charges.

 

 

 

 

 

Comments from the Public

           

The following written submission and deputations regarding the proposed development charges by-laws were provided to Council at the Public Meeting:

 

Written Submissions

a)    Letter dated May 12, 2008 from Matthew Nisker, IBI Group (addressed to Frank J. Spaziani, Angus Glen Development Ltd./Kylemore Communities);

b)    Letter dated May 14, 2008 from Julie Bottos, SCS Consulting Group Ltd;

c)    Memorandum dated May 22, 2008 from Patrick O'Hanlon, President, Angus Glen Development Ltd;

d)    Letter dated May 27, 2008 from M. Filice, Liberty Development Corporation;

 

Deputations

e)    Deputation from Mr. R. Grimes, IBI Group, at the public meeting on May 27, 2008;

f)     Deputation from Mr. P. O’Hanlon, Angus Glen Development, at the public meeting on May 27, 2008;

g)    Deputation from Mr. N. Mracic, Metrus Developments Inc., at the public meeting on May 27, 2008.

 

 

It was noted that the final report on the proposed Development Charges By-law will go to General Committee on June 9, 2008 and to a subsequent Council meeting for adoption.

 

 

Summary of Written and Verbal Comments – Public Meeting May 27, 2008

 

A.           Written Submissions:

a) and c):          Patrick O’Hanlon, President of Angus Glen Development Ltd. commented that the transfer of Area Specific development charges, while done to develop a more efficient and fiscally viable development charge system along with maintaining equitability, will result in Angus Glen having to pay an additional $833,000 in development charges as a result.  Included with the submission was an analysis from the IBI Group detailing the calculation of the additional development charge.  Mr. O’Hanlon also gave a verbal submission which is included below.

 

b)         Julie Bottos of SCS Consulting Group Ltd., representing the Greensborough Landowners Group, requested that the Town consider eliminating the area specific development charge for Area 43 as the only project remaining in the area can be dealt with by the landowners internally.  A meeting was also requested to discuss how the development charge credits now allocated to Town Wide Hard will be handled. 

 

d)         Marco Filice of Liberty Development Corporation stated that he is opposed to the substantial changes being proposed to the current development charge by-laws.

 

Deputations - Verbal Submissions:

e)         Randy Grimes of IBI Group spoke on behalf of the developers in general and his client, The Cathedral Group in particular.  He commented that the financing charge of 6.5% used in the draft Background Study is too high and suggested that a rate in the region of 5% – 5.5% was more appropriate.  Mr. Grimes also suggested that the Town should open the by-laws when the relevant information is obtained under the Places to Grow Initiative regarding growth expected in the Town.  Mr. Grimes said that the changes to the Development Charges regime will increase development costs in some areas and not others. He gave as an example the Cathedral area which he said will see an increase of $1.5M as a result of the transfer of costs from Area Specific to Town Wide Hard.  Mr. Grimes suggested that those areas that are already partially developed be grandfathered and that the new regime apply only to new developments.  This submission is dealt with under Section B of this report.

 

f)          Mr. Patrick O’Hanlon of Angus Glen Developments, spoke to reiterate that the new regime impacts developments differently.  Mr. O’Hanlon requested a 10 year transition plan in order to allow time for higher density development.

 

g)         Mr. Nik Mracic of Metrus Developments Inc., advised that his company was still conducting an analysis of the impacts of the new regime.

 

B.         Staff Responses

 

Item a), c) and f) Submission from Angus Glen Developments        Staff recognize that as a result of the transfers, there will be a cost increase to the Angus Glen area developments estimated to be approximately the $833,464 noted in the letter from Matthew Nisker of IBI.  This is equivalent to an increase of approximately $1,136 per unit. ($833,464 divided by 734 units).

Angus Glen has conditional allocation for 286 of the 734 units in 2011 (conditional on construction of bridge between East and West Village by Dec. 1, 2009).  The transition plan approved by General Committee on May 26, 2008, allows subdivision applicants 14 days after enactment of the DC bylaws to qualify (as set out in the report) for the 2004 indexed by-law rates.  This transition policy will not provide the relief sought by the Angus Glen Area 47 developers for the 286 units noted above.  Mr. O’Hanlon’s request for a 10 year transition plan would have to be extended to all development, and clearly over a 10 year period (and at least 2 more DC by-law periods) would have a significant negative impact on cash flows to the development charge reserves, as well as a potential for shifting a portion of the costs to non-growth, due to the passage of time.

Discussion

In the letter from IBI Group dated May 12, 2008 discussing the impact of the proposed development charge by-laws on the Angus Glen development area,  a number of options to mitigate the increased development charges were reviewed.  Additionally, staff met with Angus Glen Development Ltd. on Friday June 6, 2008 for further review of options. The following is a discussion of several of the options.

 

There options reviewed by staff are as follows:

 

Option 1

Approve the By-laws as recommended.  In staff’s view, the proposed development charges and by-laws are based on Town policies and established existing service levels, and will be defensible at the Ontario Municipal Board should the by-laws be appealed.

 

Option 2

Develop a town wide policy regarding the inclusion of a percentage of the cost of smaller bridges in the TWH DC., and increase the TWH DC to collect these costs. The Angus Glen development includes a bridge crossing at Beaver Creek that is currently considered to be a local cost.  The cost of bridges are higher than a typical 2 lane subdivision road, however the Town does not currently include these smaller bridges in the TWH DC. The current cost of the bridge is estimated to be in the $2 million range. The rationale put forward by Angus Glen for including small bridges in the TWH is that these bridges provide a benefit beyond their own development, and a typical 2 lane local road.

 

If a portion of the bridge is added to the TWH by-law, the DC rate per unit would increase.  In order to be fair and equitable, staff would have to review all local bridges to determine if any other local bridge projects are similar to the Angus Glen bridge, and should also be included as an additional cost in the TWH by-law

 

If Council were to consider this option, in order to fair and equitable, staff would recommend a two step by-law approval.

1.      Enact the TWH by-law with rates that do not include the additional costs for the bridges

2.      Immediately enact an amendment to the TWH (Amended TWH) by-law with a charge (Amended Charge) that include the additional costs for the bridges. 

 

If the developers do not support the inclusion of a portion of local bridges in the TWH Amended Charge, they could chose to challenge the Amended TWH by-law, which will include the higher rates with an estimated cost of the bridges included, without affecting the main (unamended) TWH by-law. 

 

This approach would be transparent and fair to all developers. A policy to determine what the criteria would be for a bridge to qualify for partial reimbursement needs to be developed.  It is very difficult to estimate what the cost of potentially reimbursing developers for a portion of bridges already constructed would be.

 

If this option is adopted by Council, staff recommend that a notional contingency of $1,500,000 be added into TWH rates, in advance of a policy being finalized, and detailed costs being determined.  Until the policy and detailed costs are determined, the degree of cost mitigation available for the Angus Glen development is unknown.

 

Option #2 would result in an increase of 0.5% in the TWH development charge.  The collection of the DC’s would be on schedule, as detailed in the Draft DC Background Study. (See Attachment – Option 2)

 

 

 

Option 3

The IBI Group letter suggests “grandfathering” of areas whose development is mostly complete, or provide a significant transition period.  Grandfathering would mean including specific developers or development areas in the DC by-laws at the current 2004 indexed DC rates.  Determining the definition of “mostly complete” or simply including all developments currently underway, or specifically the Angus Glen development is an arbitrary approach, and could have significant long term cash flow impacts.  A long term transition period (ten years was suggested in the public meeting) would also have a significant cash flow impact, and would provide a market advantage to “grandfathered” developments compared to newer developments not receiving the benefit of the much lower 2004 indexed development charge.

 

Option #3 is not recommended by staff, as the reduced cash flow implications could be significant, precipitating the need for debt financing, and higher DC costs for future development.  The potential for appeal from developers not receiving the benefit is high, as they will have to pay a higher DC rate.

 

Option #4

Option #4 is an option put forward in a discussion with Angus Glen Development Ltd.  The proposal is:

 

“Another possible alternative is to propose some sort of “equalization fund”.  For example a $100 per unit “equalization charge” over 36,000 units would produce a $3.6 million equalization fund to be distributed in an appropriate manner among the “big losers”. Details would have to be worked out further with Staff.”

 

An equalization fund such as that described could not, in staff’s view, be included in the development charges.  It is not a service that qualifies for inclusion in development charges, therefore would be very difficult to defend in front of the Ontario Municipal Board.  A program whereby developers made voluntary payments into such a fund outside of the development charge by-laws could be implemented, and staff are willing to assist in administering such a program, but question whether it would be feasible.

 

Option #4 would be a fund outside of development charges that the Town could administer on behalf of developers, but cash flows would be dependent on voluntary payments being made by the developers.

 

Proposed Revision

No revision proposed

Item b)  Submission from SCS. SCS was advised by staff that no area specific by-law will be passed for area 43 and that meetings regarding credit agreements will be held over the months following the enactment of the 2008 by-laws.

Proposed Revision

There will not be an area specific by-law for Area 43 – Greensborough

 

Item d)  Submission from Marco FiliceComments from Mr. Filice are general in nature. 

Proposed Revision

      No revision proposed

 

Item e)  Submission from Randy Grimes of IBI Group  - Question regarding the financing cost of 6.5% used in the draft Background Study.  Mr. Grimes suggested that an appropriate charge may be within the range of 5% - 5.5%.   Mr. Grimes also discussed the increases in the Cathedral area, and the suggestion that grandfathering of areas that are partially developed.

Proposed Revision:

Staff has reviewed this submission and are recommending a change to the financing costs to 5.75% for borrowing costs (from 6.50%) and 4.00% for investment returns (from 4.50%).  The effect of this recommendation is a less than 1.04% reduction in the development charge rates which are shown in the “Financial Considerations” section of this report.  These decreases in rates reflect the lower yields currently seen in the market.

 

Staff do not recommend grandfathering of some development areas into the by-laws, as discussed under Item a), c) and f).

 

 

 

Area Specific Consultative Process

In the past few months, staff have met with the majority of the Area Specific Development Charge (ASDC) developers, twice in some instances, to discuss the capital projects to be included in their respective charges.  Town staff also advised developers in these meetings, that discussions on the recovery of credits will be undertaken after the enactment of the 2008 by-laws.  These developers were advised of the availability of the draft Background Study that detailed their proposed charges.   The revised Area Specific Development Charge rates are attached – see Appendix B.

 

Additional Revisions / Staff Recommendations

Council has already reviewed and passed a resolution on some policy changes regarding the development charge calculation in the meeting of April 29th, 2008 (see Appendix A).   Additionally, the following changes are being proposed:

 

 

1.      Revised detailed TWH and ASDC capital programs are attached.  The revisions to the capital projects have slightly lowered the TWH but not the Area Specific development charges.  The charges are discussed under “Financial Considerations”.

 

2.      The Council resolution on April 29th included that all local services be excluded from the calculation of development charges.  In the East Precinct and South Unionville-Helen Avenue areas, the Town upfronted the cost of local infrastructure and hence these costs are included in the respective area specific development charge calculation.  

 

3.      Removal of the Exhibition Creek realignment and restoration project from area 43 – Staff have reviewed the request from SCS Consulting Group on behalf of the Greensborough Landowners Group and recommends that since the landowners will allocate these costs internally there is no need for its inclusion.  This will result in no area specific charge for area 43 as this was the only project captured in the charge.

 

4.      A staff report recommending a grant equivalent to development charges payable for the affordable rental housing project proposed by East Markham Non-Profit Housing Corp. (EMNHC) will be provided to General Committee on June 16, 2008.  In order to provide stability to the rates, and in recognition of the lengthy process required to bring forward this affordable rental housing application, staff recommend that the new development charge by-laws include a clause that sets out the Town Wide Hard and Area Specific (Area 4) development charges payable by East Markham Non-Profit Housing Inc, at the 2004 by-law rates, indexed to January 1, 2008.

 

5.      The wording of Section 2 (2) of the TWH by-law dealing with the methodology for charging mixed use development has been clarified to reflect existing practice.  In a mixed use development, the residential units pay TWH charges on a per unit basis.  Normally, non-residential space is charged based on the land area (per hectare), but in the case of mixed use, as the residential units are paying the full TWH charge, the non-residential development in the same building is charged based on the building footprint, as a proportion of the total land area charge.  The wording in the TWH by-law is simply being clarified to reflect this practice. 

 

 

 

 

 

 

 

 

FINANCIAL CONSIDERATIONS

 

Revised Development Charges:

 

The chart below outlines the current Town Wide development charges, the proposed Town Wide charge before and after the transfer of ASDC costs and the relevant variances.  The proposed charge differs from the charge included in the draft background study due to revisions made as a result of issues raised in the public meeting (i.e. change in financing rates). 

 

 

 

Non-Growth Share:

The hard services non-growth share is not a legislated percentage and is based on the benefit the infrastructure will provide to the existing population.   Consistent policies are applied to all hard service capital projects to determine the non-growth share.  The amount to be funded from non-development charge sources for hard services equates to approximately $151 million over the twenty-three year period (2008-2031), of this amount $79 million is to be funded by the developers (local costs) and $72 million from the Town through non-development charge sources (e.g. taxes, reserves etc.) 

 

Implementation of Capital Program:

The Development Charges Act requires Council to indicate that it intends to ensure that the increase in the need for service attributable to the anticipated development will be met.  Therefore, the enactment of the development charge by-laws commits Council to ensure that the capital program is undertaken as outlined in the development charge background study.

 

The capital program included in the background study anticipates a large portion of the infrastructure will be installed in advance of development.  The Town will be required to borrow internally and/or externally to meet this capital program.  The borrowing costs associated with the front-loading of the capital program has been included in the development charge.  This places an increased commitment on Council to ensure that the capital program is implemented as outlined in the background study.

 

Operating Costs:

In approving the development charge by-laws, Council is also committing to the costs associated with the ongoing operation and maintenance of the assets included in the capital program.  The operating cost impacts of the expanded municipal infrastructure are anticipated to be fully funded from additional tax revenues generated by the growth-related increase in the property assessment base.  Furthermore, the new households will generate additional utility rate revenue that will be utilized to fund any incremental water and sewage servicing operating costs.

 

 

ENVIRONMENTAL CONSIDERATIONS:

Not applicable.

 

ACCESSIBILITY CONSIDERATIONS:

Not applicable.

 

ENGAGE 21ST CONSIDERATIONS:

Not applicable.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Legal Services and Engineering Department.

 

RECOMMENDED BY:

 

 

 

 

________________________                                    ________________________

Barb Cribbett                                                               Andy Taylor

Treasurer                                                                      Commissioner, Corporate Services

 

 

Att:   Appendix A – Council Resolution of April 29, 2008

         Appendix B – Revised Executive Summary – 2008 Development Charge Background Study

         Appendix C – Minutes of the Development Charges Public Meeting – May 27, 2008

         Appendix D – Capital Program

Appendix E – Option 2

Letter from IBI Group dated May 12, 2008