| Quality Management System Implementation Progress | |||||
| DWQMS Element | Documentation Completed | Implementation | Target Date to complete | ||
| Partial | All | Partial | Full | ||
| 1. Quality Management System | P | P | June 2008 | ||
| Document a QMS that meets the requirement of the DWQMS | |||||
| 2. Quality Management System Policy | P | P | Completed | ||
| Document a QMS Policy that provides the foundation for the QMS | |||||
| 3. Commitment and Endorsement | P | P | Completed | ||
| Contain a written endorsement of its contents by Top Management and the Owner | |||||
| 4. Quality Management System Representative | P | P | Completed | ||
| Identify a QMS Representative | |||||
| 5. Document and Records Control | P | P | Completed | ||
| Document a procedure for document and records control | |||||
| 6. Drinking-Water System | P | P | Completed | ||
| Document to provide a description of the drinking-water system | |||||
| 7. Risk Assessment | P | P | Completed | ||
| Document a risk assessment process that identifies hazardous events | |||||
| 8. Risk Assessment Outcomes | P | P | Completed | ||
| Document the identified hazardous events & identified control measures | |||||
| 9. Organizational Structure, Roles, Responsibilities and Authorities | P | P | June 2008 | ||
| Document the org. structure including respective roles, responsibilities and authorities, and | |||||
| communicate this information to Operating Authority personnel and the Owner | |||||
| 10. Competencies | P | P | June 2008 | ||
| Identify and arrange for necessary training for all personnel whose work affects drinking water quality | |||||
| 11. Personnel Coverage | P | P | June 2008 | ||
| Ensure that sufficient personnel meeting the identified competencies are available for duties that | |||||
| directly affect drinking water quality | |||||
| 12. Communications | P | P | June 2008 | ||
| Describes how the relevant aspects of the QMS are communicated between Top Management and | |||||
| Owner, Operating Authority personnel, Suppliers and the Public | |||||
| 13. Essential Supplies and Services | P | P | June 2008 | ||
| Identify all supplies and services essential for the delivery of safe drinking water, and to ensure the | |||||
| quality of essential supplies & services in as much as they may affect drinking water quality | |||||
| 14. Review and Provision of Infrastructure | P | P | June 2008 | ||
| Document the annual review of the adequacy of the infrastructure necessary to operate and maintain | |||||
| the subject system | |||||
| 15. Infrastructure Maintenance, Rehabilitation and Renewal | P | P | June 2008 | ||
| Document a summary of the Operating Authority's infrastructure maintenance, rehabilitation and | |||||
| renewal programs for the subject system | |||||
| 16. Sampling, Testing and Monitoring | P | P | June 2008 | ||
| Document sampling, testing and monitoring activities throughout the drinking water system | |||||
| Quality Management System Implementation Progress | |||||
| DWQMS Element | Documentation Completed | Implementation | Target Date to complete | ||
| Partial | All | Partial | Full | ||
| 17. Measurement & Recording Equipment Calibration & Maintenance | P | P | June 2008 | ||
| Document the activity for calibration and maintenance of measurement and recording equipment | |||||
| 18. Emergency Management | P | P | June 2008 | ||
| Being prepared for emergency situations that could result in the loss of the ability to maintain the | |||||
| supply of safe drinking water to consumers; Identify what could happen in the system to cause an | |||||
| emergency, and have processes and procedures in place to prepare and response | |||||
| 19. Internal Audits | P | P | September 2008 | ||
| Document and perform internal audits that conform to the requirement of QMS at least one every | |||||
| twelve months | |||||
| 20. Management Review | P | P | October 2008 | ||
| Document and conduct management review that evaluates the continuing suitability, adequacy and | |||||
| effectiveness of the QMS at lease once every twelve months - Top Management must ensure the | |||||
| review is performed identified deficiencies, and reports the results to the Owner | |||||
| 21. Continual Improvement | P | P | June 2008 | ||
| Continually improve the effectiveness of its QMS through the use of corrective actions | |||||
| Documentation Status | |||||
| Partial - Not all the required documentations for the element have been completed | |||||
| All - All required documentations for the element have been completed | |||||
| Implementation | |||||
| Partial - Only part of the documentation and activity for the element have been communicated to staff, and limited practice been put in place | |||||
| Full - All completed documentations and activities for the element have been communicated to staff, and all practice been put in place | |||||
| * During the internal audit process, verification will be carried out in order to determine the effectiveness of the implementation of each element | |||||