Report to: General Committee Report
Date:
SUBJECT: The Ontario Ministry of
Environment -
PREPARED BY: Karen Dennison, M. Eng., P. Eng., Ext. 2519
Waterworks, Manager of System Engineering
RECOMMENDATION:
THAT the report “The Ontario Ministry of Environment – Markham Distribution System – Drinking Water System Inspection Report” be received;
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not Applicable
The purpose of this report is to provide Council with an update on the findings of the Ministry of the Environment (MOE)’s inspection of the Markham Water Distribution System for 2007.
The Safe Drinking
Water Act, 2002 (SDWA) states that a provincial officer may at any reasonable
time conduct an inspection for the purpose of determining compliance with
regulatory requirements contained within the Act, or any of the associated
regulations. Traditionally, the MOE has annually conducted an inspection of
The MOE inspection
of the Markham Water Distribution System occurred on
The MOE provided two recommendations,
identifying areas for further improvement of
The MOE Inspector provided the following list of Best Practice Issues and Recommendations. These recommendations are provided by the MOE to identify areas where drinking water quality assurance can be further improved or protected. Please note the “Recommended Actions” convey information that the owner or operating authority should consider implementing in order to improve procedures and policies already in place and are not considered violations.
MOE Best Practice Issues and Recommendations
1. System Efficiencies
Recommendation:
It was estimated that greater than 10 % (approximately 11%) of the total amount of distributed water was not accounted for.
(a)
It is recommended that the Town
of
(b)
It is recommended that the Town
of
2. Procedures
Correction Recommendation:
A review of the
(a) The Waterworks Procedure #101 should be reviewed and modified to clearly reflect the corrective actions as listed in O. Reg. 170/03, Schedule 17-5 and 17-6.
(b) Provide the modified procedure to the issuing officer for review.
(c) After the modified version of the procedure has been provided to the issuing officer for review, provide to the issuing officer records indicating that the operators and other affected staff have been trained/updated with respect to the changes made to the procedure.
Town of Markham’s Response to the Recommendations
The Town has responded to the recommendations from the MOE as follows:
Water Loss:
At the time of the MOE inspection on
We recognize that there is a need for continuous
improvement in order to further reduce water loss and optimize system
efficiencies.
Leakage Identification Programs:
Minimizing leakage, or water loss, improves the
efficiency of the drinking water distribution system and is an important part
of water conservation. To help reduce
existing, unreported leaks in the system,
Leakage Reduction Programs:
Pressure management is planned for
implementation and testing in Management Area P2. The intention is to reduce
pressure during times of low flow thereby reducing the volume of background
leakage from the system.
Watermain failures can result from aging mains, main
breaks, leaks, high system pressures and supply issues. Early indications or warnings of emerging
leaks or problems will minimize this risk and better account for water usage
and losses.
Infrastructure management is accomplished
through various established
Markham
The
The modified
The monthly Operations & Maintenance Meeting was held on
Not Applicable
Not Applicable
Not Applicable
The MOE Inspection Report enhances several key Waterworks service delivery components:
· Proactive and preventative strategies to identify and manage risks to public health;
·
Continuous Improvement of
Not Applicable
RECOMMENDED BY:
________________________
Jerry Klaus,
General
Manager,
________________________
Peter Loukes, P. Eng.
Commission Lead, Operations and Asset Management
Attachment A – Ontario Ministry of the Environment -
Attachment B –