Repor
SUBJECT: Award of Tender
PREPARED BY: Hossein Sharif, Extn 2382
Phoebe Fu, Extn 3010
Tony Casale, Extn 3190
RECOMMENDATION:
THAT the report entitled “Award of Tender #106-T-08
19th Avenue Bridge Replacement over the Little Rouge Creek (East of
Highway 48, B19)” be received;
AND THAT the contract for #106-T-08 19th
Avenue Bridge Replacement be awarded to the lowest
priced supplier, Bob Hendricksen Construction Ltd., in the amount of $754,930.00,exclusive
of contingency and GST;
AND THAT a contingency amount of $50,000.00, exclusive
of GST be established to cover any additional construction and consultant costs
and tha
AND THAT the award cost of $754,930 and $50,000
contingency be funded from the allocated budget of $810,000.00 in 2008 Capital Budget
account 058-6150-8287-005, Replacement of
AND THAT the remaining balance $5,070 in account
058-6150-8287-005 be used for other project related activities as identified
under financial considerations.
And that Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not applicable
The purpose of this
report is to obtain Council’s approval to award Contract # 106-T-
The
The Town retained
Totten Sims Hubicki Associates (TSH) in 2006 to undertake a Class Environmental
Assessment (EA) Study for the replacement of the existing bridge. Following the EA approval in January 2008, TSH
completed the detail design and construction tendering for the bridge
replacement.
A formal application
for a permit under
Upon the Council’s approval, the project is anticipated to commence
beginning of July and completed by end of September. The section of
Bob Hendricksen Construction
Ltd submitted the
lowest priced acceptable bid and was therefore recommended for the award. Bob Hendricksen Construction Ltd has successfully completed
various similar contracts in the past and staff have verified reference checks
to ensure tha
BID INFORMATION:
Advertised, place and date |
ETN |
Bids closed on |
|
Number of contractors picking up bid documents |
11 |
Number of contractors responding to bid |
3 |
DETAILED
PRICING INFORMATION:
Company |
Total Price, Excl GST |
Bob Hendricksen Construction Ltd |
$754,930.00 |
Elirpa Construction &
Materials Ltd. |
$769,450.10 |
Brennan Paving &
Construction Ltd |
$777,837.93 |
The following
table is a summary of the financial considerations for this report: |
|||
Original
Budget and Account # |
$ 860,000.00 |
|
058-6150-8287-005,
2008 Capital - Replacement of |
Current
Budget Allocated to Construction |
$ 810,000.00 |
|
|
Less: Construction Cost |
($754,930.00) |
|
Awarded
to Bob
Hendricksen
Construction Ltd |
Less: Contingency –Construction |
($ 50,000.00)
|
|
|
Budget
Remaining |
$ 5,070.00 |
|
|
The remaining budget available of $5,070.00 will be used for project signage and reproduction of drawings.
The construction will require in-water work (footing construction) and the work must adhere to fishing timing window of July1 and September 15 of any given year as stated in TRCA’s regulations.
To insure tha
To comply with the Migratory Birds Convention Act, vegetation removals should take place between August 1 and April 14 of any given year.
The existing bridge consists of 2 narrow traffic lanes and no sidewalks. The proposed bridge will have sidewalk on both sides which will improve accessibility across the bridge.
Not applicable
The Finance Department has reviewed this report and their comments have been included.
RECOMMENDED
BY: ________________________ ________________________
Steve Andrews Peter Loukes
Director, Commission Lead,
Asset Management Operations and Asset Management
Not applicable
Q:\Commission Share\Operations and Asset Management\Reports\2008\Asset
Management\ROW\Award of Tender #106-T-08 19th Avenue Bridge Replacement over
the Little Rouge River (East of Highway 48, B19)-FINAL.doc