This procedure describes the process for ensuring
sufficient personnel
2.0
Scope
All personnel with identified competencies
that directly affect drinking water, and the activities these personnel are
required to perform are covered under the scope of this procedure.
3.0
Definitions
·
OIC –
Operator-in-charge
·
OIT –
Operator In Training
·
Stand-by
Staff – Staff assigned to be available to respond to emergencies outside of
normal business hours
·
ORO –
Overall Responsible Operator
·
MOE –
Ministry of Environment
·
SLD –
System Level Document
4.0
Procedure
4.1
Waterworks shall have
sufficient staff available to respond to system operations, maintenance and
emergencies 24 hours per day, 365 days per ye
4.2 The Waterworks shall be sufficiently staffed from Monday to Friday during normal business working hours to meet regular system needs.
4.3 Waterworks Operators shall be assigned to stand-by coverage to meet system needs.
4.4 The Overall Responsible Operator (ORO) is designated to be the Operations & Maintenance Manager or the Waterworks Supervisor that has been assigned to stand-by duties. Waterworks Supervisors are assigned to stand-by duties on a rotational basis. The Operations & Maintenance Manager also participates in the Supervisors stand-by rotation.
4.5 During normal business hours the Waterworks Supervisors and Waterworks Working Supervisors are designated as Operator-in-charge. These staff shall be MOE certified at the system level or higher in water distribution.
4.6
Outside of normal business
hours of weekdays
4.7
Waterworks Operators shall be
assigned to stand-by coverage outside of normal business hours (
4.8 Waterworks shall set the stand-by schedule for Waterworks stand-by coverage.
4.9 Stand-by schedules shall be available at the Works Yard and the Waterworks main office.
4.10 Each stand-by shift shall include 3 Operators, one backup Operator, and one Supervisor.
4.11 The backup Operator shall be on stand-by, and shall be available to relieve or assist other Standby Operators as required.
4.12 Completed Standby Change Forms and Absence Report Forms shall be filed by the Operations & Maintenance Staff.
4.13 The standby Supervisor shall be responsible for all related Waterworks activities during after hours, during the standby period.
Emergencies
4.14 After hours emergencies shall be addressed by the designated standby Operator, and responded to, according to the Emergency Management SLD.
4.15
A listing of all critical
contacts and contact information shall be prep
4.16 During the standby period, should the need for additional Operators arise, the Standby Supervisor shall be responsible to call in additional licenced operators, staff or contracted resources.
4.17
Assistance may be provided by
other staff within the dep
Strikes and/or Lockouts
4.18
Strikes and lock-outs shall be
handled as per the Town of
5.0
Associated
SOPs
·
Dispatch
SOP
·
Generating
Stand-by schedule SOP
·
Calling
Additional Resources & Operators SOP
6.0
References
·
DWQMS
Element 11 –
·
Emergency
Management SLD
·
Standby
Change Form
·
Absence
Report Form
7.0
Records
·
Standby
Schedules
·
Completed
Standby Change Forms
·
Completed
Absence Report Forms
8.0
History
of Changes
Revision |
Date |
Description |
By |
|
|
|
|
|
|
|
|