Report to: General Committee Report
Date:
SUBJECT: Award of RFP #172-R-08
PREPARED BY: Prathapan Kumar, Ext. 2989
Phoebe Fu, Ext. 3010
RECOMMENDATION:
THAT the report entitled “Engineering Services related to Bullock
Drive widening at the intersection with McCowan Road” be received;
AND THAT staff be authorized to retain the highest ranked and second lowest priced bidder Morrison Hershfield Limited for detailed design and preparation of tender documents for an upset fee limit of $95,789.00 inclusive of disbursements and exclusive of GST;
AND THAT a
contingency amount of $10,000 exclusive of GST be established to cover any
additional design and that the Director of
AND THAT staff be authorized to retain the highest ranked and second lowest priced bidder Morrison Hershfield Limited for contract administration and construction inspection services for an upset fee limit of $56,300 inclusive of disbursements and exclusive of GST subject to satisfactory completion of the detailed design phase of the project as described in the RFP document;
AND THAT a
contingency amount of $8,000 exclusive of GST be established to cover any
additional contract administration services and that the Director of
AND THAT the award be funded from the
available budget of $2
AND THAT $7
AND THAT the tendering process for the relocation of existing utilities including design review and construction coordination services, be waived in accordance with Purchasing By-Law 2004-341, Part II, Section 7 (2);
AND THAT staff be authorized to issue
Purchase Orders to various utilities companies for the relocation of their
existing services up to a total value of $7
AND THAT the award and the purchase order release of RFP# 172-R-08 Engineering Services related to Bullock Drive widening at the intersection with McCowan Road be subject to finalization of Memorandum of Understanding (MOU) between Town and GO Transit;
AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.
EXECUTIVE SUMMARY:
Not Applicable.
PURPOSE:
The purpose of
this report is to obtain Council’s authorization to proceed with the detail
design, and construction tendering of the
In September 2005, Council endorsed a
general strategy for the construction of a GO Transit parking structure on the
Centennial Community Centre site. In
September 2006, GO Transit and Town staff presented to Council the design of
the parking structure. In February 2008,
a site plan application was submitted by Earth Tech Canada on behalf of GO
Transit to the Town for a proposed 3 storey (ground plus 2) parking structure
with an approximate Gross Floor Area of 10,171.25 square metres (109,
To support the increase traffic from the GO
parking structure, intersection improvements will be required at
Advertised |
ETN (Electronic
Tendering Network) |
Bids closed on |
|
Number picking up bid
documents |
10 |
Number responding to
bid |
5 |
Consulting Firm |
Price
(excl. GST) |
||
Design Fee |
Contract Administration |
Total |
|
Wardrop |
$86,620.00 |
$52,180.00 |
$138,800.00 |
Morrison Hershfield
Limited |
$95,789.00 |
$56,300.00 |
$152,089.00 |
Cole |
$109,268.80 |
$70,007.70 |
$179,276.50 |
Stantec Consulting
Ltd. |
$190,062.72 |
$100,338. |
$290, |
iTRANS Consulting
Inc. |
$209,876.00 |
$109,975.00 |
$319,851.00 |
The
evaluation team was comprised of staff from the Asset Management Department
with purchasing staff acting as the facilitator. The evaluation was based on pre-established
evaluation criteria as listed in the Request for Proposal: 20% for past
experience of consulting firm, 20% for qualifications and experience of the
lead consultant and project team, 30% for project delivery and 30% for price,
totalling 100%, with resulting scores as follows:
Consulting Firm |
Score (out of 100) |
Rank Results |
Morrison Hershfield
Limited |
90.4 |
1 |
Wardrop |
86.0 |
2 |
Cole |
80.2 |
3 |
Stantec Consulting
Ltd. |
70.3 |
4 |
iTRANS Consulting
Inc. |
69.0 |
5 |
Although
the bid price from Wardrop
A consultant was retained to complete the
preliminary design of the widening of
Property is required on the north side
of
In the 2007 Capital Budget process, a
preliminary construction estimate of $6
Upon completion of the preliminary design work, the cost of the detailed design and construction is estimated to be $1,000,000. This may result in a funding shortfall of $360,000. Upon completion of the detail design and construction tendering, the actual project cost will be determined. If the actual project cost exceeds the current capital project estimate of $640,000, Staff will initiate discussions with Region of York to explore opportunities to increase their share of the total project costs.
At the preparation of this report, Town received initial commitment from GO Transit that the MOU between the Town and GO will be finalized. GO Transit indicated that they will be committing $375,000 for the intersection improvement project.
Based on the information above the cost sharing between Region of York, GO Transit and the Town is as follows:
|
Estimates as identified
in Capital Project #7613 |
|
Revised Estimate |
||
|
Costs |
Comment |
|
Costs |
Comment |
Total Estimated Costs |
$
640,000 |
Based on preliminary design
estimate |
|
$ 1,000,000 |
|
Region of |
$
150,000 |
|
|
$
150,000 |
Staff
to pursue additional funding |
GO |
$
245,000 |
Assumed
50/50 Cost sharing |
|
$
375,000 |
|
Town |
$
245,000 |
Assumed
50/50 Cost sharing |
|
$
475,000 |
Capital
Budget request #9232 $1,000,000 (including Carry forward #7613 for $640,000) |
Total Funding |
$ 640,000 |
|
|
$1,000,000 |
|
GO Transit has indicated that the construction of the parking structure will start in the spring of 2009 with anticipated completion in the fall of 2009. Therefore, the intersection improvement to support the opening of the parking structures has to be completed in summer 2009.
|
ALIGNMENT WITH STRATEGIC
PRIORITIES:
The increase of
GO Transit parking spaced at the Centennial CC will increase the service level
for alternative mode of transportation within
DEPARTMENTS CONSULTED AND AFFECTED:
The Legal Department and Finance Department have been consulted, provided input and reviewed this report.
BY:
__________________________ ____________________
Steve Andrews, P.Eng. Brenda Librecz
Director of
Attachment ‘A’ - Preliminary Design of eastbound dual
left turn lanes at
Attachment ‘B’ - Region of York Transportation and
Works Committee Report dated
Q:\Commission Share\Operations and Asset Management\Reports\2008\Asset
Management\ROW\Award of RFP #172-R-08 Engineering Services related to Bullock
Drive widening at the intersection with McCowan Road_FINAL.doc