Report to: General Committee Report
Date:
SUBJECT: Grid Tied Solar Photovoltaic (PV) Pilot Project
PREPARED BY: Viive Sawler, Manager, MECO
RECOMMENDATION:
THAT the Report titled, “Grid Tied Solar Photovoltaic (PV) Pilot Project” be received.
THAT Council authorize the installation of a 10 kW grid-tied solar PV installation at the Civic Centre that includes web-enabled software to promote the educational and awareness building value of this project.
THAT Council authorize funding for this project to an upset cost of $100,000 through MESF and up to $25,000 for design/feasibility work through MECO.
THAT
1. Purpose 2. Background 3. Discussion 4. Financial
5. Others (Strategic, Affected Units) 6. Attachment(s)
The purpose of this pilot project is to increase
This Pilot Project concept was brought forward as a staff
application for funding through the Markham Environmental Sustainability Fund –
Fall funding cycle. Implementing a pilot
solar PV project at a
The proposed project is to grid-tie the system which would
mean that green energy generated would be sent back into
Economic
While on the economic side, the payback period is longer
term, the maintenance and operational costs are very low. Once installed, solar panels require little
upkeep other than an inspection now and then to ensure they are kept clean and are
operating optimally. Approximately,
$5000 per year in revenue will be generated under the RESOP contract and this
may increase over the term of the contract depending on the Province’s decision
to adjust the incentive level. An
application will also be made to the Ministry of
Environmental
From an environmental perspective, solar energy has many benefits. It is plentiful, renewable and producing power from solar PV panels displaces the need for generating power through fossil fuels, thereby contributing to reduced GHG emissions and a reduced carbon footprint for the Town. Solar energy does not interfere with the natural environment and provides quiet, clean and low maintenance generation while enhancing local energy self reliance and contributing to a diversified energy supply mix.
Social
From a social perspective there are also many benefits in that solar energy provides quiet, clean power. It contributes to local energy self reliance and represents an opportunity to contribute to a more integrated urban energy system. Grid-tying the system would provide experience that we could then replicate at other Town facilities in the future. Also, there are a number of Markham based companies in the ‘solar business,’ which means this project would serve to promote local economic development and contribute to job creation and security.
There are a number of options that may be pursued from both a location and a design point of view. Potential locations to site the solar PV panels are described below in Options 1 and 2 but to ensure optimal performance should primarily be south facing. There are also a number of design options ranging from basic roof top installations to more complex and creative options such as solar ‘awnings’ or solar ‘trees.’ Solar panels designed as awnings could serve as shade providers which may increase the benefits of the solar installation by reducing hot spots and glare which in turn would reduce the Town’s air conditioning load during the summer months. This may add some cost to the installation. The second option entails mounting solar panels on poles. However, there are security and vandalism issues associated with this ‘tree’ type of design plus an added complexity and cost associated with under grounding the wiring required for connection purposes.
Option #1
The preferred option is to install
the 10 kW solar PV system at the Civic Centre.
This building represents a high profile location that can be modeled as
a beacon of innovation, in line with promoting
Option #2
Due to the modular nature of solar
PV panels, it would be possible as a second option to split up the 10 kWs and spread
them across two or more locations. Some
could be installed at the Civic Centre, while others could be installed at one
of the community centres such as Milliken Mills, or even at a smaller facility
such as a stand-alone library. The
implication of pursuing this option is a 10 – 20% increase in cost due to the
various connections, additional inverters that would be required at separate
sites, etc.
Following the completion of the proposed pilot project and after ample time is given for measuring and monitoring success, the Town could consider investigating additional solar PV installations at several other Town owned buildings depending on availability of funding support.
This project would support
“Building Markham’s Future Together” goals and in particular is well aligned to
the “Environment” area of strategic focus.
In addition, it would complement the efforts and commitment to the
BY: ________________________ ________________________
Viive
Sawler, Manager, John
Livey,
MECO
MESF Project Application – Grid
Tied Solar PV Pilot, V. Sawler presentation to EIC,
Photovoltaic Systems, Generation
PV presentation to EIC,