Report to: Development Services Committee                             Report Date: February 3, 2009

 

SUBJECT:                          Master Servicing Plan for Growth Management Strategy -          Consultant Selection RFP #203-R-08

                                             

PREPARED BY:               Brian Lee, Manager, Development Engineering, ext. 4838

                                            Allen Wu, Senior Development Engineer, ext. 2230

 

 

RECOMMENDATION:

THAT the report entitled “Master Servicing Plan for Growth Management Strategy - Consultant Selection RFP # 203-R-08” be received;

 

AND THAT the Request for Proposal #203-R-08 be awarded to the highest ranked, highest priced project team led by Genivar Ontario Inc. for an upset limit of $680,918.30 exclusive of GST ($714,964.22 inclusive of 5% GST);

 

AND THAT a contingency amount of $150,000.00 exclusive of GST ($157,500.00 inclusive of GST) be established to cover any additional costs and that the Director of Engineering be authorized to approve expenditures of this contingency up to the specified limit with the provision that a monthly statement of these expenditures is forwarded to the Town Treasurer;

 

AND THAT the internal engineering fee in the amount of $120,300.00 be approved and funded through development charges;

 

AND THAT the award be funded from the approved 2008 Engineering Capital Budgets account 83-5399-8124-005 (Direct Growth Strategy) and account 83-5399-8394-005 (Thornhill Servicing Study) in the amount of $336,000.00 and $224,000.00 respectively for a total of $560,000.00;

 

AND THAT the additional amount of $391,218.30 (comprising of $120,918.30 consultant cost, $120,300.00 staff salary recovery cost, and $150,000.00 contingencies), exclusive of GST, be increased for the Engineering Department Capital Account 83-5399-8124-005 to cover the additional project cost and be funded from development charges;

 

AND THAT the Director of Engineering and Manager of Purchasing be authorized to negotiate with Genivar Ontario Inc. to incorporate the process of the Environmental Assessment into the Master Servicing Plan if deemed appropriate by the Director of Engineering from a scheduling and costing perspective;

 

AND THAT upon payment of all invoices, any remaining funds be returned to the original funding source;

 

AND THAT staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

EXECUTIVE SUMMARY:

The Town of Markham is in the process of developing a Growth Management Strategy with the vision of developing sustainable communities with effective and efficient transportation and servicing infrastructure to keep pace with growth. A number of policy and master planning exercises are underway to promote intensification and transit oriented development.  However, much of the existing servicing infrastructure (including the sanitary, storm, and water distribution systems in the existing urban areas) has limited capacity to accommodate future development intensification. Therefore, an assessment of the existing servicing infrastructure is necessary to evaluate the capacity of the existing servicing systems and to determine the improvements required to accommodate growth options and alternatives being considered through the Growth Management Strategy.

 

The Growth Management Strategy exercise is focused on containing growth and intensification within the existing urban boundary.  Likewise the focus of the Master Servicing Plan will be on analyzing the servicing infrastructure and intensification requirements in the urbanized areas.  Analysis and recommendations will be coordinated with infrastructure studies and works by the Asset Management Department and the Waterworks Department to eliminate duplication of cost and effort.  Hydraulic models that have been or will be developed by these departments will be used to analyze the servicing requirements for intensification.  The Master Servicing Plan will also analyze and protect for long term servicing requirements for any future expansion of the urban service boundary, but this represents a relatively small component ($35,000) of the total consultant cost of $680, 918.30 for the study.

 

The funding for this project in the amount of $560,000.00 is available in the 2008 Engineering Capital budget from project nos. 8124 (Direct Growth Strategy) and 8394 (Thornhill Servicing Study). Due to the complexity of the works to complete the study as well as the supplementary tasks added to the scope of work, the originally established budget estimate has to be increased to cover the additional cost. Extra consultant cost of $120,918.30, staff salary recovery cost of 120,300.00 and contingencies of $150,000.00 are included for a total project cost of $951,218.30. Staff is requesting Council’s approval to increase the Engineering Department Capital Account 83-5399-8124-005 by $391,218.30 to cover these additional costs.

 

The selection of the consultant for the Master Servicing Plan has been conducted in a two stage process. The Request for Pre-qualification of consultants was released on June 25, 2008. Three (3) consulting firms were pre-qualified and advanced to the Request for Proposal stage. A Request for Proposal was subsequently issued by staff on August 25, 2008 in accordance with the requirements of the Town’s Purchasing By-law.  The Request for Proposal closed on September 19, 2008 and all three pre-qualified bidders submitted a proposal. An evaluation team consisting of staff from Engineering with Purchasing acting as the facilitator, subsequently evaluated the three proposals and ranked them in accordance with the scoring criteria. Genivar Ontario Inc. (Genivar) was ranked with the highest score and is therefore recommended by staff to undertake the study. In comparison with the other consulting firms who submitted the Request for Proposal, Genivar has clearly demonstrated their understanding of the project and their capabilities to undertake this project with the following qualifications.

 

  • Comprehensive work program with extensive work hours assigned to the project and appropriate distribution of the time to the tasks. The total work hours proposed by Genivar and the distribution of these hours to the tasks is appropriate for this project.
  • Extensive experience in project management and study assignments of similar projects for other municipalities.
  • Well qualified staff and sub-consultants with skills and knowledge to complete the Master Servicing Plan and to produce a report with high quality recommendations.
  • As the lead consultant for York Region’s Water and Wastewater Master Plan, Genivar will be able to provide a seamless coordination with the Region on the analysis of both the  Town’s and the Region’s infrastructure and to determine the servicing infrastructure requirements.
  • Excellent working knowledge of the Town’s water system including previous involvements in the Town’s water system modelling.
  • Complete understanding of the assignment and deliverables to be provided to the Town upon completion of the study.
  • Extensive experience in the Master Servicing Planning process.

 

1. Purpose                           2. Background 3. Discussion 4. Financial

PURPOSE:

The purpose of this report is to award the consulting contract for the preparation of the Master Servicing Plan for Growth Management Strategy to Genivar and to secure additional funding in the amount of $391,218.30 (comprising of $120,918.30 consultant cost, $120,300.00 staff salary recovery cost, and $150,000.00 contingencies), for a total amount of $951,218.30 (exclusive of GST) to undertake this study.

 

BACKGROUND:

The Province of Ontario enacted legislation in 2005 entitled the “Places to Grow Act, 2005” enabling the development of the Provincial Growth Plan which establishes growth forecasts and growth management policies for municipalities to comply with. The provincial government released the Growth Plan for the Greater Golden Horse in June 2006. The Growth Plan aims to revitalize the downtown cores in municipalities; to provide greater choice in housing types; to limit urban sprawl; and to reduce traffic gridlock. The Growth Plan requires by 2015, that a minimum of 40% of the new residential development within the upper tier or single tier municipalities must take place in areas that are already built-up and where existing infrastructure is already in place. In accordance with the Growth Plan, all municipal Official Plans must be brought into conformity with the Growth Plan by June 2009.  The Region of York and the Town of Markham are undertaking the necessary studies and analysis leading up to future Official Plan Amendments as required by the Province.

 

The Town is developing a Growth Management Strategy with the objective of achieving sustainable communities with effective and efficient transportation and servicing systems to keep pace with growth. The Growth Management Strategy will identify the locations of growth areas (with an emphasis on intensification within the existing urban boundary), and will provide recommendations for sustainable growth in compliance with the requirements of the Province’s Places to Grow Act and the Growth Plan for the Greater Golden Horseshoe. A preferred growth alternative for the Town will be recommended to Council, and an assessment and evaluation of the existing servicing infrastructure will be completed by the Master Servicing Plan to identify the most effective and efficient servicing scheme to support the future growth.

 

OPTIONS/ DISCUSSION:

Intensification in the developed urban area will present a challenge for the existing servicing infrastructure, as it has a limited capacity and will require improvements to accommodate development growth. The capacity of the existing servicing infrastructure was determined to satisfy the land use and design criteria for the time period when the infrastructure was built.  As the land use and design criteria change, the existing infrastructure may no longer be sufficient to meet future requirements.

 

The Growth Management Strategy exercise is focused on containing growth and intensification within the existing urban boundary. Likewise the focus of the Master Servicing Plan will be on analyzing the servicing infrastructure and intensification requirements in the urbanized areas.  Analysis and recommendations will be coordinated with infrastructure studies and works by the Asset Management Department and the Waterworks Department to eliminate duplication of cost and effort.  Hydraulic models that have been or will be developed by these departments will be used to analyze the servicing requirements for intensification.  The Master Servicing Plan will also analyze and protect for long term servicing requirements for any future expansion of the urban service boundary, but this represents a relatively small component ($35,000) of the total consultant cost of $680,918.30 for the study.

 

The Consultant retained for this study will perform the following tasks:

 

  • Evaluate the condition and the residual capacities of the existing servicing systems (sanitary, storm, water) to accommodate growth options and alternatives being considered through the Growth Management Strategy.
  • Evaluate the servicing requirements and identify improvements required to implement the preferred growth alternative.
  • Estimate the infrastructure costs, including any land acquisition cost for improvements to the infrastructure to accommodate the preferred growth alternative.
  • Consult with the utility companies such as Bell Canada, Rogers Cable, PowerStream and Enbridge Gas, etc. to identify any network expansion required to accommodate the proposed growth as per the Town’s Growth Management Strategy.
  • Coordinate with the Region of York to confirm the capacity of the Region’s sanitary and water trunk and sub-trunk systems to accommodate the Town’s preferred growth alternative. The Consultant will consult with the Region and identify the progress of the Region’s studies and the timeline of implementing the regional infrastructure improvements. The Consultant will also provide appropriate recommendations on improvements to the Municipal and Regional infrastructure in consideration with the Region’s schedule.
  • Establish design parameters and sustainable technologies such as rain water harvesting, grey water recycling, water conservation, water balancing, green roofs, green infrastructure, etc. that future developments are to consider. The Consultant’s review will include preliminary assessment of sustainable technologies, the legislative policy requirements, the operation and maintenance requirements, capital costs, and will provide recommendations on the potential use and application of these technologies within the Town.  A discussion paper will be prepared summarizing the findings and recommendations which will be coordinated with the Town’s “Sustainable Development Guidelines” and the “Community Sustainability Plan (Green Print)”.

 

Integration with the Thornhill Stormwater Flood Remediation Study by Asset Management Department

Asset Management Department is in the process of completing an analysis of the existing infrastructure in the Thornhill area to determine the cause of the flooding during the August 19, 2005 storm event and to determine the options for flood remediation for the area. The Asset Management Department has retained an external consultant (Clarifica Inc.) to carry out this analysis and evaluation. A comprehensive hydraulic model will be developed by Clarifica for evaluation of the existing storm infrastructure in the Thornhill area. To eliminate duplication of effort and cost, the storm hydraulic model developed by Clarifica for the Thornhill area will be used by the Master Servicing Study consultant to evaluate the impact on the existing storm sewer system and to determine the improvements required to accommodate intensification scenarios in Thornhill. 

 

Coordination with Waterworks Department for Analysis of the Sanitary and Watermain Systems

Similar to the coordination with the works by the Asset Management Department, existing hydraulic models for the sanitary sewers and the water distribution system will be utilized to eliminate duplication of effort and cost. The Waterworks Department has completed a hydraulic model on the sanitary sewer system for the area bounded by Warden Avenue to the east, Steeles Avenue to the south, Yonge Street to the west and Highway 407 to the north. Similarly, a hydraulic model for all watermains in the Town is also available. The consultant for the Master Servicing Study will obtain these existing models from the Waterworks Department to evaluate the capacity of the existing sanitary sewer and watermain systems and to determine the requirements needed to accommodate the intensification scenarios.

 

Environmental Assessment Process

The current scope of work for the Master Servicing Plan does not include the complete analysis related to the Environmental Assessment Process. However, if deemed appropriate by the Director of Engineering from the perspective of funding and study timeline, the Master Servicing Plan may be expanded to integrate with the Environmental Assessment process which would follow the “Master Planning Process” as set out in Ontario legislation for Municipal Class Environment Assessments (EA).  The Manager of Purchasing and the Director of Engineering will negotiate with Genivar as a preferred supplier to provide this additional scope of works, if deemed appropriate by the Director of Engineering. The cost of the EA works will be identified and additional funds will be budgeted prior to the start of the EA process. The Master Servicing Plan process would integrate the planning of municipal infrastructure requirements for the existing and future land use with the principles of Environmental Assessment Process and would include the following:

 

·        Consultation with stakeholders and public

·        Consideration of reasonable range of alternatives

·        Identifying and considering the effects of each alternative on all aspects of the environment

·        Evaluating the alternatives systematically to determine their cumulative environmental effects

·        Providing clear, precise and complete documentation of the planning process

 

The Master Servicing Plan will be used to support the future environmental assessments for specific servicing infrastructure improvements especially for the Phase I and II portions of the Class EA process, which focus on identifying needs, opportunities and alternatives.

 

The Master Servicing Plan for the Growth Management Strategy will not require approval under the Environmental Assessment Act. However, individual projects recommended by it must fulfil all appropriate EA requirements and individual EA’s may be required. 

 

Contingencies and Complexity of the Study

Preparation and completion of the Master Servicing Plan for the Growth Management Strategy will be a complex process and will involve a large number of stakeholders, as well as the evaluation of different alternatives for development growth. The scope of work for the Master Servicing Plan requires the Consultant retained for this study to prepare and analyze the detailed servicing requirements for the preferred growth alternative to be determined by Markham Council through the Growth Management Strategy process. However, provisional works are included in the scope of work identifying that analysis of additional growth alternatives and/or additional growth areas may be required if, through the Growth Management Strategy, the Town wishes to explore other development options for growth management. In addition, many of the proposed growth areas are located in areas that have been developed for many years and some of the necessary records and plans will not be available and need to be reproduced. Therefore, in order to complete the evaluation of the servicing infrastructure, field surveys and data collection on site may be required to confirm and verify the information on the plans.

 

Given the size and complexity of the study, the large number of stakeholders, the potential need to carry out additional analysis for other growth alternatives / areas, and the extensive background information required to complete the study, a contingency amount is recommended in the order of $150,000.00. This amount represents approximately 20% of the study estimate, to cover the cost of any additional services such as the items identified below:

 

§         Additional Public Consultation meetings including preparation/analysis, attendance by consultant team, facilitator, meeting reports and documentation, follow-up with public and Council working meetings.

§         Additional analysis and modelling to evaluate municipal servicing requirements for additional alternative growth scenarios.

§         Enhanced project reporting: including additional presentations and/or working sessions with stakeholders and Council.

§         Field survey and data collection on site to verify and confirm the missing information.

 

Any funds remaining at the end of the project will be returned to the respective engineering accounts for use to fund future steps in the Master Servicing Plan.

 

Consultant Selection

The selection of a consultant team to undertake the Master Servicing Plan for Growth Management Strategy has been conducted through a two stage process identified as (i) Request for Pre-qualification (RFQ) and (ii) Request for Proposal (RFP).

 

Request for Pre-qualification (RFQ)

The first phase of the selection process was the RFQ# 134-P-08, in which a public advertisement was posted on www.Biddingo.com. The RFQ process involved the pre-qualification of consultant teams based on the team qualifications, past experience with similar projects, project approach and public consultation program.  Three (3) consultant teams were pre-qualified and invited to proceed to the next stage of the consultant selection with the submission of a detailed proposal.

 

Request for Proposal (RFP)

The RFP# 203-R-08 was issued in accordance with the Purchasing By-law 2004-341 to the three pre-qualified consultants. The Evaluation Team consisted of staff from Engineering and Purchasing reviewed the bid documents and are satisfied that all terms, conditions, bid prices and specifications comply with the Town’s requirements.  The details of the RFP process are summarized below:

 

  Direct electronic mail to three pre-qualified firms

Monday, August 25, 2008

Bids closed

Friday, September 19, 2008

 

Bidders Meetings Prior to Bids Closed

Two group meetings were held with the consultant teams on Friday August 29, 2008 and Tuesday September 9, 2008. The purpose of the meetings was to present existing available information that the Town currently has, to clarify the scope of work of the study and to allow the consultant teams to ask questions on the RFP.

 

Bidders Meetings Subsequent to the Bids Closed

Three (3) separate meetings were held with each of the three (3) consultant teams on Wednesday October 8, 2008. The purpose of the meetings was to provide an opportunity for the Evaluation Team comprised of staff from the Engineering with Purchasing acting as facilitator, to clarify questions that arose from evaluating the proposals submitted by the consultant teams.

 

Proposal Submission

Proposals were received from all three pre-qualified firms and each consultant team was required to respond to the terms of reference with a comprehensive submission outlining the project team, the work plan and required fees. Accordingly, the consultant’s fees reflect each team’s interpretation of the items of work, staff resources and time required to successfully deliver the project and results in a variation in upset fee limits ranging from $ 508,134.00 to $ 680,918.30.

 

 

 

 

Evaluation of Submissions

The proposals were evaluated based on pre-established evaluation criteria as listed in the RFP:  20% Past Project Experience of Consulting Team and Qualifications of the Project Manager; 30% Project knowledge and Study Methodology; 15% Project Delivery and Schedule; 5% Quality Assurance and Safety Programs and 30% Price totalling 100%.  The rank results are listed in the following table:

 

Lead Consultant

Ranking

Total Score

Genivar Ontario Inc.

1

81.4

Cole Engineering Group Ltd.

2

73.4

Stantec Consulting Ltd.

3

70.8

 

 

 

 

 

 

Consultant Selection Ranking

Genivar was identified as the highest ranked submission, even though it is also the highest priced consultant through the evaluation process. In comparison with the other lead consultants’ submissions, the Genivar team demonstrated a thorough understanding of the assignment and assembled a project team with solid technical skills and experience and had previous master planning experience that best matched the scope of work for the Master Servicing Plan study. Genivar’s commitment to complete this assignment also reflected in the work hours they have assigned to the tasks for this project.  In comparison to the other consultants’ submissions and the assignment of the work hours to the project, Genivar has included considerable more work hours for the project and has demonstrated a realistic assignment and distribution of the hours to the tasks. Genivar’s previous master planning experience will be beneficial to completing this study in a timely and effective manner. As a result, Genivar received a considerably higher technical score for its submission.  The factors contributing to Genivar attaining the high ranking score included,

 

 

  • A comprehensive work program with extensive work hours assigned to the project and appropriate distribution of the time to the tasks.
  • Extensive experience in project management and study assignments of similar projects for other municipalities.
  • The team is comprised of well qualified staff and sub-consultants with skills and knowledge to complete the Master Servicing Plan and to produce a report with high quality recommendations.
  • The project manager on the Genivar team is also the lead project manager for the Region of York’s Water and Wastewater Master Plan. As the lead consultant for York Region’s Water and Wastewater Master Plan, Genivar will be able to provide a seamless coordination with the Region on the analysis of both the  Town’s and the Region’s infrastructure and to determine the upgrade requirements for the servicing infrastructure.
  • Excellent working knowledge of the Town’s water system including previous involvements in the Town’s water system modelling.
  • Complete understanding of the assignment and deliverables to be provided to the Town upon completion of the study.
  • Extensive experience in the Master Servicing Planning process.

 

Project Schedule

The current project schedule calls for commencement in February of 2009 and completion of the Master Servicing Plan by February of 2010. Interim reports will be generated to evaluate the capacity of the system under the current condition. The study’s milestone dates are highlighted below. However, completion of the study adhering to this schedule will be dependent on Council direction regarding growth options and identification of the preferred growth alternative for the Town, through the Growth Management Strategy process.

 

 

§   Consultant Retained for the Master Servicing Plan                                      February 2009

 

§   Development Growth Alternative Provided to Consultant                            April 2009

 

§   Interim Report on Preliminary Assessment of the Existing

      Servicing Systems                                                                                      July 2009

 

§ Interim Report on Preliminary Assessment and Analysis of the

Preferred Growth Alternative                                                                      September 2009

 

§ Completion of the Study with Final Report and Presentation to DSC     February 2010

FINANCIAL CONSIDERATIONS:

Funding for this project in the amount of $560,000.00 is available in 2008 Engineering Capital budget from project nos. 8124 and 8394 for Direct Growth Strategy and Thornhill Servicing Study respectively. However, due to the complexity of the works to complete the study as well as the supplementary tasks added to the scope of work, the originally established budget estimate has to be increased to cover the additional cost. An appropriate amount for contingency must also be established to cover the cost of the provisional works such as field survey and data collection, additional coordination and meetings with the stakeholders, additional growth alternatives modelling analysis, and extra growth area analysis. In addition, an internal engineering fee is being assessed to recover the cost of the staff to manage this project. The following tables provide a summary of the project cost and the additional fund required to complete the project.

 

 

Project Costs (exclusive of GST)

Consultant Team Fees

$   680,918.30

Contingencies

          $   150,000.00

Internal Engineering Fee

$   120,300.00

Total Project Costs (A)

          $   951,218.30

 

 

 

 

 

Currently Available Funds (exclusive of GST)

2008 Approved Capital Budget 

Directed Growth Strategy

(Account  83-5399-8124-005)

$   336,000.00

 

Thornhill Servicing Study

(Account   83-5399-8394-005)

$   224,000.00

Total Funding (B)

          $   560,000.00


Shortfall (exclusive of GST)

(A) –(B)

          $   (391,218.30)

 

 

The funding shortfall ($391,218.30) is related to consultant cost ($120,918.30), staff salary recovery ($120,300.00), and contingencies ($150,000.00). In order to finance the shortfall, it is recommended that additional funds in the amount of $391,218.30 (exclusive of GST) for Project no. 8124 be approved and funded by Development Charges.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Planning Department will provide details regarding growth options and the preferred growth alternative selected by Council through the Growth Management Strategy. Preparation and completion of the Master Servicing Plan will be based on the preferred growth alternative to the satisfaction of Council.

 

The Finance Department has reviewed the funding and budget requirements and their comments have been incorporated into this report.

 

RECOMMENDED BY:  

 

 

 

 

____________________                                            ________________________

Alan Brown, C.E.T.                                                      Jim Baird, M.C.I.P., R.P.P.

Director of Engineering                                                                                                 Commissioner, Development Services