Report to: DEVELOPMENT SERVICES COMMITTEE              Report Date: June 23, 2009

 

 

SUBJECT:                          Design, Construction and Financing of Parks in Angus Glen West Village by Angus Glen Development Ltd.

PREPARED BY:               Linda A. Irvine, Manager Parks and Open Space Development

 

 

 

RECOMMENDATION:

1)   THAT the report dated June 23, 2009 to Development Services Committee, entitled “Design, Construction and Financing of Parks in the Angus Glen West Village by Angus Glen Development Ltd.” be received;

 

2)   AND THAT Council approve the request by Angus Glen Development Ltd., to finance the cost of design, construction, and contract administration of the parks identified as Plan 1, Block 139 (0.5318 ha / 1.314 ac) in draft plan of subdivision 65M-4085 and Plan 2, Block 47 (0.5648 ha / 1.395 ac), Block 48 (0.0408 ha / 0.10 ac), Block 49 (0.0777 ha / 0.1919 ac), Block 50 (0.0383 ha / 0.0946 ac) and Block 51 (0.4030 ha / 0.9957 ac) in draft plan of subdivision 65M-4086, subject to the following conditions:

 

A.     That Angus Glen Development Ltd., finance the cost of the design, construction, and contract administration of these parks to a minimum value of $165,000.00 per acre based on 1.656 ha / 4.092 acres of parks which totals approximately $675,180.00 inclusive of all applicable taxes but exclusive of GST;

 

B.     That, subject to compliance with these terms and conditions, the Town of Markham reimburse Angus Glen Development Ltd., up to a maximum of $675,180.00, plus GST, towards this project from development charges for park development under the understanding that Angus Glen Development Ltd., may contribute additional funds above this amount which will not be reimbursable by the Town, towards the development of these parks;

 

C.     That subsequent to collection of sufficient Development Charges for park development at the building permit stage for residential lots within the Angus Glen West Village, the Town shall reimburse Angus Glen Development Ltd., for invoices paid for approved costs associated with the design, construction, and contract administration, for park development. No interest on such invoices shall be payable by the Town. Reimbursement terms are as follows:

 

a.       Angus Glen Development Ltd. may only invoice the Town for 80% of approved costs provided that:

                                                               i.      at least 45 days from the date of publication of Substantial Performance has transpired;

                                                             ii.      proof of publication has been submitted with the invoice;

                                                            iii.      no liens have been registered in regard to this contract;

                                                           iv.      the constructed work has reached Total Completion to the Town’s satisfaction after which the two year warranty period shall begin;

                                                             v.      the landscape architect has issued to the Town a Total Completion certificate.

 

b.      the remaining 20% of Town approved costs shall be retained by the Town for a minimum of two years from Total Completion and shall be paid to the Developer upon the Developer invoicing the Town for the remaining 20%, provided the following has occurred in the order listed here:

                                                               i.      two years has passed from the date of Total Completion;

                                                             ii.      that the two year warranty inspection has occurred with the Town;

                                                            iii.      that all noted deficiencies at the two year warranty inspection have been completed to the Town’s satisfaction to the point of total performance;

                                                           iv.      that Final Acceptance has been granted by the Town;

                                                             v.      that the landscape architect has issued a certificate certifying the warranty period has expired and further that noted deficiencies have been completed in general conformance to the plans and specifications;

                                                           vi.      that any liens registered in regard to the contract have been released and/or paid by the Developer;

                                                          vii.      and further, that the two year maintenance obligations had been performed during the warranty period, failing which, the Town shall use the remaining funds at its sole discretion to compensate for the unfulfilled obligations.

 

c. or alternatively, Angus Glen Development Ltd. may invoice the Town for 100% of approved costs two years after the date of Total Completion provided items b, i through vii, as listed above, have occurred to the Town’s satisfaction.

 

D. That Owners/Developers within the Angus Glen West Village Community, including Angus Glen Development Ltd., not receive any credit towards park development charges and continue to pay the park development charge at the building permit stage for all present and future development phases of subdivisions within the Angus Glen Community;

 

E. That Angus Glen Development Ltd. hire a landscape architect who is a Full Member of the OALA having custody and use of the Association seal, approved by the Town, to provide professional design, contract document, and contract administration services, to the satisfaction of the Town as outlined in Schedule A;

 

F.      That Angus Glen Development Ltd. follow the Town’s standard Park and Open Space approval process which includes development of several design concepts, holding community input meetings, presentation to selected Standing and Advisory Committees as applicable, as well as review and approval by the Planning and Urban Design Department in consultation with the Parks Operations Department;

 

G.     That Angus Glen Development Ltd. tender out the construction of the park works to a minimum of three bidders to the satisfaction of the Town including providing the Town with a copy of all bids submitted within 24 hours of tender close. The successful bidder will be responsible to construct and maintain the park in from the time park construction is begun until Final Acceptance by the Town;

 

H.     That, notwithstanding the requirement noted above in Condition (G), Angus Glen Development Ltd. shall tender and award a maintenance contract for the park to Town standards.  The maintenance contract for the park must be tendered and awarded at the same time as the construction contract and cover a minimum period of 2 years detailed maintenance as outlined in Appendix ‘C’ (“Developer Obligations: Two Year Maintenance Activities”) to the Town’s satisfaction and that maintenance of the park shall continue until Final Acceptance of the park.  Costs for the 2 year (minimum) maintenance contract are the responsibility of Angus Glen Development Ltd. The Town will not reimburse Angus Glen Development Ltd. for costs associated with this additional maintenance obligation for the park;

 

I.        That these parks be included in the Urban Design, Development Services Commission, Capital Budget submission in 2011 which will include the amount to be reimbursed and the internal consulting fees.

 

3) And that staff be authorized and directed to do all things necessary to give effect to         this resolution.

 

 

EXECUTIVE SUMMARY:

Not Applicable.

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (HR, Strategic, Affected Units)                                   6. Attachment(s)

 

PURPOSE:

This report seeks approval for Angus Glen Development Ltd. to finance the costs of design, construction, and contract administration associated with the development of parks identified as Plan 1, Block 139 (0.5318 ha / 1.314 ac) in draft plan of subdivision 65M-4085 and Plan 2, Block 47 (0.5648 ha / 1.395 ac), Block 48 (0.0408 ha / 0.10 ac), Block 49 (0.0777 ha / 0.1919 ac), Block 50 (0.0383 ha / 0.0946 ac) and Block 51 (0.4030 ha / 0.9957 ac) in draft plan of subdivision 65M-4086 in the Angus Glen West Village.  

 

BACKGROUND:

As part of the overall parks and open space master for the Angus Glen West Village, there is a hierarchy of parks to be developed on the west and east sides of Angus Glen Boulevard. The parks on the west side extend generally in a north-west direction from Angus Glen Boulevard to Glengordon Crescent and are primarily passive parks linked by a pedestrian walkway. The park on the east side extends generally from Stollery Pond Crescent to the river valley and is intended as more active neighborhood park with playground facilities and a shade structure.   

 

OPTIONS/ DISCUSSION:

In a letter dated August 14, 2008, Mr. Michael Montgomery, Project Manager, Angus Glen Development Ltd. requested permission from the Town to allow Angus Glen Development Ltd. to proceed with the design and construction of these parks in Angus Glen West Village in advance of the Town’s projected schedule of 2011 as identified in the DC Background Study. Angus Glen Development Ltd. is motivated to build these parks early for marketing and promotional reasons. Staff anticipates that the design of these parks will likely proceed through the summer of 2009, and the requisite community meeting will occur in the fall of 2009, that the parks will be tendered over the winter in time to allow for a spring 2010 construction start.

 

In consideration of this request, this report seeks Council’s approval for the early delivery of these parks by Angus Glen Development Ltd. in accordance with the recommendations noted herein. The 5 year park capital program will be adjusted to reflect the early delivery of these parks.

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

In the year that these parks are assumed by maintenance by the Town, additional resources may be required in the Parks Operation s budget. Implications to the tax rate (10% of $675,180.00) will occur in the 2011 when the Capital budget is approved. When designing the park, staff will consider the long-term maintenance, operational and capital replacement cost implications.

 

HUMAN RESOURCES CONSIDERATIONS

Not applicable.

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

This work aligns with the following areas of strategic focus: Growth Management and Parks, Recreation, Culture and Library Master Plan. 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Finance Department has been consulted in the development of this report.

 

 

RECOMMENDED BY:  

 

 

________________________                              ________________________

Ronji Borooah, OAA, MCIP, RPP                         Jim Baird, MCIP, RPP

Town Architect                                                       Commissioner of Development Services

 

ATTACHMENTS:

Appendix ‘A’: Letter from Mr. Michael Montgomery

Appendix ‘B’: Landscape Architect’s Scope of Work

Appendix ‘C’: Developer Obligations: Two Year Maintenance Activities

Appendix ‘D’: Location Map – Block 139

Appendix ‘E’: Location Map – Blocks 47, 48, 49, 50, 51

 

 

 

Q:\Development\Design\linda\Parks\DSC Angus Glen June 23 Report.doc

 

 


 

APPENDIX B: LANDSCAPE ARCHITECT’S SCOPE OF WORK

 

Landscape architectural services shall include typical full scope of services.  The items below are intended to assist the consultant to ensure that, at minimum, the items listed are included in the scope of services provided.  This list is not intended to be exhaustive.

 

PART A: DESIGN SERVICES

1.      Undertake data collection and base plan preparation.

2.      Hire surveyor under surveyor allowance, and prepare an up to date topographic survey, if necessary.

3.      Hire sub-consultants (under the sub-consultant allowance) to include, as required by the design: a mechanical engineer to certify flow rate for purposes of water meter sizing; a structural engineer to certify design of all proposed and as-built structures inclusive of footings to be structurally sound as well as provide BCIN; an electrical engineer to certify electrical work and obtain ESA (Electrical Safety Authority) certificate; a civil engineer to certify the proposed and as-built civil works have been designed and constructed properly, and; an irrigation consultant to design and certify the work has been designed and installed properly and in accordance with the plans.  The landscape architect shall include surface grading and drainage as well as sub-drainage where required as part of the full scope of landscape architectural services.

4.      Contact development engineer to obtain composite utility plans (above and below ground) including any easements which may affect the design or installation for inclusion on landscape plans.

5.      Undertake detailed analysis of site and context.

6.      Undertake schematic design work for review by Town staff.

7.      Meet with Town staff as needed to develop a minimum of 2 alternative concepts.

8.      Prepare and submit cost estimates complete with signed OALA seal, to ensure design concepts can be built within the allotted budget.  Amend plans if required to meet budget.

9.      Undertake public consultation meeting with area residents (one evening meeting) including the presentation of the two rendered park concept alternatives.  Evening meeting shall include display panel boards (at either 24”x 36” or 36”x 48” sized for future Town storage) as well as prepare a PowerPoint presentation of the boards for the evening meeting.

10.    Amend/combine concepts as required, to develop a preferred design concept in preparation for developing working drawing package.

 

PART B: WORKING DRAWINGS AND TENDER DOCUMENT SERVICES

1.      Prepare working drawing package of the preferred design.

2.      Meet with Town staff to refine working drawings as required, until approved by Town.

3.      Submit revised cost estimates complete with signed OALA seal, to ensure design concepts can be built within the allotted budget.  Amend plans if required to meet budget.

4.      Secure all necessary permits and agency approvals for the work as required.

5.      Prepare final working drawings, specifications, tender documents, cost estimates and contract documents to Town standards for competitive bidding of the work.

6.      Provide the Town with 12 sets of tender documents (specifications and drawings) for tender.

7.      Attend bidders meeting and document questions arising from the meeting.  Provide answers to the Town for questions arising.

8.      Assist the Town in its tendering process and be responsible for technical inquiries and/or clarifications, preparing draft addenda for issue by the Town regarding bid documents requirements.

9.      Review bids for accuracy and provide recommendations.

 

PART C: CONTRACT ADMINISTRATION AND WARRANTY SERVICES

1.      Undertake Contract Administration to Final Completion.

2.      Arrange and host pre-construction meeting.

3.      Undertake periodic construction meetings as required including weekly site meetings during active construction.

4.      Prepare and distribute all meeting minutes with contractor.

5.      Review project schedule on an ongoing basis and assist the contractor in resolving matters affecting the contractor’s schedule.

6.      Review contractor’s construction layouts, provide recommendations to Town staff and obtain Town approval.

7.      Provide recommendations to Town staff and obtain approval from Town for additional work or work deleted from contractor contract.  Prepare Change Orders and obtain Town authorized signature. The landscape architect shall provide an ongoing spreadsheet listing all items included for all contemplated changes, all Town agreed to changes, any previously issued change orders, and the remaining funds in the contingency.

8.      Provide recommendations to Town staff and obtain approval from Town for additional work or work deleted from contractor contract.  Prepare Change Orders once approved and obtain Town authorized signature on all Change Orders.  With each contemplated change, the landscape architect shall provide an ongoing spreadsheet showing the impact of the contemplated change on the budget.  The spreadsheet shall include all contemplated changes, all Town agreed to changes, any previously issued change orders, and the remaining funds in the contingency.

9.      Review shop drawings, contractor requested plant and other substitutions or changes, provide recommendations to Town staff and obtain Town approval prior to directing contractor or proceeding with the works.

10.    Review on-going construction to ensure compliance with the contract drawings and specifications.  If construction is not compliant with documents, note deficiencies and discuss with Town for review and direction.  Issue instructions to contractor as required.

11.    Visit the site each time the contractor makes a claim for payment to review the work performed.  Town’s policy does not permit acceptance of ‘redlined’ invoices.  Return invoice to contractor for revision with current date, amount claimed, proper purchase order number, etc if invoiced incorrectly by the contractor. 

12.    Provide Progress Payment Certificate to the Town signed with an OALA seal within 10 business days of receipt of an acceptable invoice from the contractor. 

13.    Be responsible for keeping track of all dates of each milestone listed herein, and perform on site inspections for same, including a follow-up certificate for each of; substantial performance, total completion/start of warranty (showing anticipated end of warranty), one year warranty, two year warranty, and final completion/end of warranty.  Include necessary follow-up inspections to ensure contractor compliance with inspections as required.  Perform final certification to the Town by way of a final completion certificate identifying that all the work has been completed in general conformance to the plans and specifications and that the warranty has now ended.

14.    Provide the Town with a maintenance manual after Substantial Performance which includes the following:

·        as-built drawings (landscape architect is responsible to obtain one full size set and one reduction to 11”x17” from the contractor)

·        park manual including statistics and maintenance items:

o        Legal description (also include this item on tender set)

o        Park location (also include this item on tender set)

o        Total area (also include this item on tender set)

o        CSA certification of as-built playground(s) (may be obtained from the contractor or the playground supplier or installer).  An independent playground inspector is not required with the exception of the rubberized surfacing where the landscape architect is responsible to obtain testing results for rubberized surfacing where it is being used.

o        ESA safety certificate for electrical works (may be obtained from the contractor or electrical sub-consultant)

o        Number of coniferous & deciduous trees, shrubs, and groundcovers.

o        Recommended maintenance schedule of park including watering schedule, turf cutting schedule, etc.

o        Linear length of pathways

o        Identifying all park facilities (soccer fields and their sizes, tennis court and their sizes, water play facilities, Junior and/or Senior Playgrounds etc) 

o        Start and targeted end of warranty period

o        End of Warranty and Certification of works by Landscape Architect certifying that the works have been completed in general conformance to the landscape plans and specifications, and that all deficiencies and warranty obligations have been completed.  The certificates shall be affixed with the full member’s OALA seal signed and dated.

 

 

Definitions:

 

“Construction Period” shall mean the time required to construct the park, commencing once the construction contract is awarded through to Final Completion.

 

“Inspections’ shall mean conducting an on site meeting to review the work and identify deficiencies, documenting deficiencies, preparing and issuing the deficiency list, and provide the necessary follow-up site inspections and reports to confirm rectification of deficiencies.  It is expected that the contractor shall perform his warranty obligations at the anniversary of the one and two year warranty periods.

 

“Contract Administration” shall include, but is not limited to, the evaluation of bid submissions, contractor coordination and liaison, site inspections as required, coordination of site meetings, preparation of meeting minutes, preparation and issuance of contemplated change notices, change orders, progress payment certificates, substantial performance certificates, and completion and warranty inspections.

 

“Substantial Performance” shall mean substantial performance as defined in the latest edition of the Construction Lien Act.

 

“As-built Drawings” shall mean documents prepared or redlined by the contractor showing the location of items within the park constructed as part of this contract.

 

“Final Completion” shall mean that park construction is 100% complete without any deficiencies, has been accepted by the Town for maintenance, the warranty period has expired and all warranty work has been completed and accepted by the Town.

 

“Services” shall mean the provision of landscape architectural consulting services as set out under the Scope of Work.

 

 

 

 

 


APPENDIX C:

DEVELOPER OBLIGATIONS: TWO YEAR MAINTENANCE ACTIVITIES

 

Cutting Turf:

  • All turf areas shall be cut at a height of 2 ½”
  • All turf areas shall be cut once every 12 to 14 days, as required. 
  • Naturalized or meadow areas shall be cut once per year in the spring.

 

Fertilizer:

  • All turf areas shall be fertilized with 33-6-6 complete with 50% S.C.U. (sulphur coated urea) at one pound of nitrogen per thousand square feet of turf.
  • General turf areas shall be fertilized twice per year.
  • Naturalized or meadow areas do not need to be fertilized, unless it is determined during the maintenance period, that fertilizer might improve poor growth.

 

Trash/Litter/Recycling:

  • As a minimum, litter is picked up from the ground on the same frequency as turf cutting unless there is a complaint, and then it shall be done within 24 hours.
  • Litter is to be picked up prior to cutting of the turf unless there is a complaint, and then it shall be done within 24 hours.
  • Trash and recycling shall be picked up once per week unless there is a complaint, and then it shall be done within 24 hours.
  • Moloks are to be emptied at least twice per year with frequency depending on the size, location and use unless there is a complaint, and then it shall be done within 24 hours. 

 

Water Systems (Irrigation/Water Play/Turf Valves/Yard Hydrants/etc.)

  • All water systems shall be winterized in the Fall.
  • All water systems shall be started up and programmed (where a programmer exists) each Spring.
  • Repairs to each water system shall be performed as they are discovered.
  • For splash pads, the Town will perform water quality tests in the Spring and periodic testing to ensure chlorine levels are maintained to legislated levels.
  • Water meters and backflow preventors shall be inspected once per year.
  • Backflow preventors shall be tested and certified.

 

 

Snow Ploughing:

  • Not usually performed on park walkways except where park walkways provide the only direct access to the front doors of homes that abut and front onto parks.

 

 


 

Playgrounds:

  • Playgrounds shall be inspected at least once a week with a visual inspection. Inform the contractor and Town of any irregularities or safety concerns.
  • Sand is topped up as required (Hutcheson Sand) by the contractor.
  • Rubberized surfacing shall be swept and repaired as required by the contractor.

 

Planting Beds & Trees:

  • Beds weeded twice per year, unless there is a complaint, and then it shall be done within 24 hours.
  • Tree saucers are weeded twice a year.
  • Mulch is topped up when needed with shredded cedar bark mulch.

 

Aeration/Topdressing/Over-seeding:

  • As required by the contractor and as specified under the contraction contract

 

Payment of Water & Hydro:

  • The Town shall pay for water and hydro once the park reaches substantial completion and it is being used by the public for the purposes intended.