EXHIBIT A |
|
Summary of Closed Capital Project Funding to be
Transferred |
|
at December 31, 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Amount to be Transferred |
|
|
|
|
|
|
|
|
|
$ |
|
$ |
|
|
|
|
|
|
|
Development
Charges |
6,349,766 |
|
6,349,766 |
|
|
|
|
|
|
|
Reserve
Funds |
|
|
|
|
|
Life Cycle Replacement & Capital |
3,187,708 |
|
|
|
|
Road Resurfacing |
18,173 |
|
|
|
|
Gas Tax Revenue |
2,038 |
|
|
|
|
Markham Environmental Sustainability Fund
(MESF) |
14,151 |
|
|
|
|
Pre-DCA |
26,603 |
|
3,248,673 |
|
|
|
|
|
|
|
Reserves: |
|
|
|
Facility Ramp Up Reserve |
23,260 |
|
|
|
|
Waterworks |
1,622,612 |
|
|
|
|
Building Fee Reserve |
83,890 |
|
|
|
|
Development Fee Reserve |
34,535 |
|
|
|
|
Waste |
1,548 |
|
|
|
|
Corporate Rate Stabilization |
17,187 |
|
1,783,032 |
|
|
|
|
|
|
|
|
|
Amount
to be Transferred to Original Source of Funding |
|
|
11,381,471 |
|
|
|
|
|
|
|
|
Transfer
to Capital Contingency Project (top up to $250k) |
|
241,854 [1] |
|
|
|
|
|
|
|
|
Transfer
to Design DC Capital Contingency Project (top up to $100k) |
|
100,000 [2] |
|
|
|
|
|
|
|
|
Transfer
to Planning DC Capital Contingency Project (top up to $50k) |
|
5,000 [3] |
|
|
|
|
|
|
|
|
|
|
|
|
|
Total
to be transferred at December 31, 2008 |
|
11,728,325 |
|
|
|
|
|
|
|
|
|
|
|
|
|