Report to: General Committee                                                   Report Date: February 5, 2009

 

 

SUBJECT:                          Contract Extension 120-R-06 to The Ventin Group for prime consultant services for the Markham MuseumNew Collections Building

PREPARED BY:               Gary Adamkowski, Project Manager, MHPM Project Managers Inc

                                            Michael Shatil, Manager Facility Assets

 

RECOMMENDATION:

THAT the report entitled “Contract Extension 120-R-06 to The Ventin Group for prime consultant services for the Markham Museum – New Collections Building” be received;

 

AND THAT the contract extension for prime consultant services for the Markham MuseumNew Collections Building be awarded to The Ventin Group (TVG), in the amount of $466,686.00 exclusive of GST and disbursements;

 

AND THAT the tender process be waived in accordance with Purchasing Bylaw 2004-341, Part 11, Section 7(1) c which states “when the extension of an existing contract would prove more cost-effective or beneficial”;

AND THAT the contract extension be funded from account 073-6150-7417-005 Museum Collections Building – Design Fees;

AND THAT Staff be authorized and directed to do all things necessary to give effect to this resolution.

 

EXECUTIVE SUMMARY:

Not applicable.

1. Purpose                     2. Background                      3. Discussion                        4. Financial        

 

5. Others (Environmental, Accessibility, Engage 21st, Affected Units)             6. Attachment(s)

 

PURPOSE:

The purpose of this report is to obtain Council approval to extend the contract for prime consultant services for the Markham MuseumNew Collections Building to TVG.

 

BACKGROUND:

After evaluating the submissions to RFP #120-R-06, Architectural Services – Markham Museum – Ward Building Reconstruction, purchase order D7-49 was issued to TVG in March 2007 (see appendix A). The original award and purchase order covered only the schematic design portion, which was $40,000 of the $215,000 total fee proposed by TVG which in turn was based on total project estimate of $3,325,000.  This translates to 6.5% ($215,000 / $3,325,000) of total project estimate. 

 

On May 13, 2008 Council passed a resolution to restore the Ward Building and separately construct a New Collections Building at a total project estimate of $9,158,000 which included an allocation for internal costs, including the design fees, and instructed staff to negotiate an increased fee for the much larger project scope (see appendix B).  Consequently, after negotiations, TVG submitted the following revised, firm, fee proposal for this project in the amount of $602,175 (equates to 6.57% of the revised project estimate of $9,158,000), summarized by task as follows:

Task

 

Schematic Design

$75,271.88

Design Development

$60,217.50

Contract Documents

$301,087.50

Bidding/Negotiations

$15,054.38

Construction/Contract Administration

150,543.75

Total

$602,175.00

 

On May 23, 2008, PO D7-49 was increased to $135,489 to cover the Schematic Design and Design Development fee portions of the Collections Building project identified above, pending subsequent Council approval to proceed through Design Development.  

 

On November 11, 2008, Council authorized TVG to proceed through Detailed Design, Contract Documents and Tender (see appendix C).  And at the same time, due to TVG’s involvement in project design, Staff requests the Contract Administration service be approved as well.  As a result, a purchase order is requested in the amount of $466,686.63 ($602,175 - $135,489) to cover Contract Documents, Bidding/Negotiations and Contract Administration, which can be funded from budget remaining in project 7417 Museum Collections Building - Design.

 

OPTIONS/ DISCUSSION:

Staff recommends this contract extension be awarded to TVG, based on the May 13, 2008 direction of Council to negotiate a new fee commensurate with the change in project scope and in recognition of the fact this work is an ongoing extension of the original project and consulting services scope.  TVG had provided the low bid in response to the original RFP and their fee for the expanded scope is pro rata to the original.  Further, TVG has completed the Design Development phase and the penalty, in both time and cost, to introduce an alternate design firm at this point would be substantial, hence the recommended approach is easily the most cost effective alternative.

 

BID INFORMATION:

Not applicable.

 

DETAILED PRICING INFORMATION:

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

The following is a summary of the financial considerations for this report:

Budget in 073-6150-7417-005 Museum Collections Building – Design

a

$692,000.00

 

 

Expenditures-to-date

b

$184,262.73

 

 

Commitments outstanding

c

$    7,226.27

 

 

Budget Available

d=a-b-c

 

 

$500,511.00

Award to TVG ($602,175 - $135,489 in D7 49)

e

 

 

$466,686.00

Budget Remaining After Award

f=d-e

 

 

$  33,825.00*

*Budget remaining after final invoices will return to original funding sources

 

 

ENVIRONMENTAL CONSIDERATIONS:

Not applicable.

 

ACCESSIBILITY CONSIDERATIONS:

Not applicable.

 

ENGAGE 21ST CONSIDERATIONS:

Not applicable.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Not applicable.

 

 

 

 

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                      Steve Andrews                                   Brenda Librecz

                                      Director                                              Commissioner,

                                      Asset Management                             Community and Fire Services   

 

ATTACHMENTS:

Appendix A: Council Committee meeting minutes, February 27, 2007, item 005b.

Appendix B: Council Committee meeting minutes, May 13, 2008, item 006a.

Appendix C: Council Committee meeting minutes, November 11, 2008, item 006a.

 

 