Grant Program: Building
Project
Summary:
Project
Components:
·
Erosion
and Flood Protection - $5M
·
Stormwater
Flood Remediation Program - $40M
·
Sanitary Sewer
Replacement (Capacity Improvement) - $5.58M
·
Inflow and
Infiltration Reduction Program - $31.926M
Downspout Disconnection Program $1.86M
Elimination of Manhole Cover Inflow $66K
Relining of Sanitary sewers and laterals $30M
Cost: Total
cost $82.506M
Budget: Town
will provide and advance the budget required for this project upon approval of
the funding.
Timeline: This
project is shovel ready. Studies have been completed and work has been identified.
Some work can be started within 6 weeks of funding approval and will be
completed by
Benefits:
This project will
result in a significant economic impact within the region resulting from an
estimated 924 jobs created and stimulating spending in other sectors. Numerous
environmental social and other benefits are derived from this project namely:
Capacity
improvement of existing sewers
Reduction
of extraneous flows in the sewage system and reduction of sewage treatment
volume resulting in energy savings, etc.
Reduction
and prevention of sewage spills into the environment
Preserve
and protect the natural and sensitive environment
Reduce
damage to property and environment
Reduce
impact to traffic and surface disturbances by utilizing trenchless technology
Reduce
cost and impact to environment utilizing advance no-dig method of
rehabilitation
Reduce
impact to environment and health of workers by utilizing green products in
rehabilitation.
Rehabilitation
of sewers extends its life expectancy by more than 50 years.
Results in
better customer service
PROJECT SUMMARY
Project
Name:
Project
Background
The project has been divided into major components to address both storm
and sanitary sewer flooding. The major components are:
·
Erosion
and Flood Protection - $5M
·
Stormwater
Flood Remediation Program - $40M
·
Sanitary
Sewer Replacement (Capacity Improvement) - $5.58M
·
Inflow and
Infiltration Reduction Program - $31.926M
Surface Erosion and Flood Control project will preserve the natural and
sensitive environment in the Pomona Mills creek,
Stormwater Flood Remediation
Program
The Thornhill area in
Storm flows and volumes during these severe
storms exceeded the current storm drainage infrastructure capacity in the Thornhill
area. In response, the Town of
Significant amount of improvements will be required for Thornhill to raise the level of protection for basement flooding. The following is the description of how this project fits the criteria required by the Canada Build Grant.
1) The stormwater improvements along with other flood remediation identified is $40 million dollars.
2)
This project will be completed
by
3) There is currently no approved budget for the upgrade of the stormwater system in Thornhill.
4)
Large amount of jobs will be
created from the stormwater system upgrades.
Specifically two additional new positions will be created in Town of
Sanitary Sewer Replacement
This project consist of diversion and replacement of 2790 m. of sanitary
sewers that have been found to be under capacity. The total estimated cost to divert
and replace these sewers is $5,580,000. Two additional internal staff will be
hired to manage this project, one project manager and one inspector. Town will
also hire consultant and contractors to deliver this program. Estimated number
of jobs created under this project is 62.
Inflow and Infiltration Reduction
This project consists of 3 components. The first component is the
Downspout Disconnection Program which consists of field investigations, smoke
and dye testing, and flow monitoring for 6400 properties in the area. About 640
homes are estimated to be disconnected in this area. The second component is
the elimination of inflow through the manhole by installation of manhole
covers. There are 1700 manholes that are identified to be sealed. The third and
largest component of this project is the relining of the sanitary sewers and
laterals with is-situ liner. This will reduce infiltration, improve capacity
and structural integrity of the existing pipe and extend the pipe life
expectancy in all critical areas identified in the study. This project will
reduce impact on the environment by using green resins in in-situ lining and
utilizing trenchless technology methods. Reducing inflow and infiltration will
reduce sewage treatment volumes and will therefore reduce energy usage in
sewage treatment. The total cost for this project is $31,926,000. Four
additional staff will be hired for this project namely two project managers,
one inspector and one technician. Town will also hire consultant and
contractors to deliver this program. Estimated number of jobs created under
this project is 355.
Project |
Cost |
Internal
Jobs Created |
External
Jobs Created |
Erosion and Flood Protection |
$ 5
M |
|
55 |
Stormwater Flood Remediation Program |
$ 40
M |
2 |
444 |
Sanitary Sewer Replacement |
$ 5.58 M |
2 |
62 |
Inflow and Infiltration Reduction Program |
$ 31.926M |
4 |
355 |
TOTAL |
$ 82.506M |
8 |
916 |