Grant Program:
Project Summary: Emergency
Operations Centre (EOC) & Backup Generators at Strategic Locations
The Town of
In addition we propose to provide back up natural gas generators at the facilities listed below so that these locations can be utilised for Cooling or Warming Centres as well as Reception or Evacuation Centres as required.
Costs:
The project budgets have been confirmed by staff and Power Stream our Hydro provider. None of these upgrades at any of the facilities identified below have been budgeted at this time. At a high level, total costs are as follows:
Facility Name |
Total Upgrade Budget |
Town of |
$1,000,000 |
|
$1,000,000 |
|
$ 600,000 |
|
$1,000,000 |
|
$1,000,000 |
|
$1,000,000 |
|
$1,000,000 |
|
|
|
$ 220,000 |
Sub Total |
$6,820,000 |
10% Consulting / Professional Fees |
$ 682,000 |
TOTAL COSTS |
$7,502,000 |
Timeline: Each project could be completed within 18 months.
Benefits: By making these facility improvements it
will provide the Town of