Report to: General Committee Report
Date:
SUBJECT: Award of Tender 082-T-09 Glenbourne and Glenridge Communities Sanitary Sewer
PREPARED BY: Prathapan Kumar, Ext. 2989
Phoebe Fu, Ext. 3010
Patti Malone, Ext. 2239
1) THAT the report entitled “Award of Tender 082-T-09 Glenbourne and Glenridge Communities Sanitary Sewer” be received;
2)
(a) the contract for 082-T-09 Glenbourne and Glenridge Communities Sanitary Sewer be awarded to the overall lowest priced bidder Digit Excavating Inc. for Part 1 (68 lots) works in the amount of $396,085.00 exclusive of GST;
(b) a separate purchase order for the Part 1 works in the amount of $59,412.75 exclusive of GST be issued for contingency to cover any additional works and that the Director of Asset Management be authorized to approve expenditure of this contingency amount up to the specified limit in accordance with the Expenditure Control Policy;
(c) staff be authorized to retain the highest ranked and lowest priced bidder of RFP 173-R-08, Cole Engineering Group Ltd. for contract administration of Part 1 works for an upset fee limit of $33,831.00 inclusive of disbursements and exclusive of GST;
(d)
a separate
purchase order for a contingency amount of $3,383.10 exclusive of GST be
established to cover any additional contract administration fees and that the
Director of Asset Management be authorized to approve expenditure of this
contingency amount up to the specified limit in accordance with the Expenditure
Control Policy;
(e)
staff be
authorized to retain a qualified geotechnical consulting firm in accordance
with the Town’s purchasing bylaw to provide geotechnical and materials testing
services during construction of Part 1 works to an upset limit of $7,000.00
exclusive of GST;
(f) funds in the amount of $534,176.55 be deposited into capital account 058-5350-8524-005 for construction, engineering and all related administration costs funded from the Waterworks Stabilization/Capital Reserve, to be recovered from the benefiting property owners with appropriate interest;
(g)
actual
construction cost, all the engineering and related administrative and financing
costs front-ended by the Town form part of the total project cost and be
recovered in accordance with the requirements of Section 391 of the Municipal
Act;
(h)
the
necessary By-Law to levy the associated cost against the benefiting properties be
forwarded to Council for adopted when the final cost of the project has been
determined;
(i)
the
residents of Group 2 be permitted the option of payment in the full of their
allocated project cost at the time of the completion of work or in installments
over 10 years with interest payable at the 10 Year Region of York Debenture
Interest Rate in effect on the date the By-Law is enacted, calculated annually
in advance.
3)
(a) Staff be authorized to construct the sewer with one lateral to service #24 Glenbourne Park Drive only, subject to receipt of funding as detailed in recommendation 3(g) below;
(b) the contract for 082-T-09 Glenbourne and Glenridge Communities Sanitary Sewer be awarded to the overall lowest priced bidder Digit Excavating Inc. for Part 2 works only with one lateral in the amount of $38,610.00 exclusive of GST;
(c) a separate purchase order for the Part 2 works in the amount of $5,791.50 exclusive of GST be issued for contingency to cover any additional works and that the Director of Asset Management be authorized to approve expenditure of this contingency amount up to the specified limit in accordance with the Expenditure Control Policy;
(d) staff be authorized to retain the highest ranked and lowest priced bidder of RFP 173-R-08, Cole Engineering Group Ltd. for contract administration for Part 2 works for an upset fee limit of $8,326.50 inclusive of disbursements and exclusive of GST;
(e)
a separate
purchase order for a contingency amount of $832.65 exclusive of GST be
established to cover any additional contract administration fees and that the
Director of Asset Management be authorized to approve expenditure of this
contingency amount up to the specified limit in accordance with the Expenditure
Control Policy;
(f)
staff be
authorized to retain a qualified geotechnical consulting firm in accordance
with the Town’s purchasing bylaw to provide geotechnical and materials testing
services during construction of Part 2 works to an upset limit of $500.00
exclusive of GST;
(g)
the
actual construction cost, all the engineering and related administrative and
financing costs in the total amount of $61,962.04 exclusive of GST be front-ended
by the owner of
(h) a new 2009 Right-Of-Way Assets Capital Budget be established for the construction and all related administrative costs to an upset limit of $57,567.94;
(i)
the
necessary By-Law to levy the associated cost by property be prepared for lots #24,
#26, 29 and
(j)
The Mayor
and Clerk be authorized to enter into an agreement with the owner of No.
4)
AND THAT Staff be authorized and directed to do all things necessary, including the execution of documents, to give effect to this resolution.
Not Applicable
The purpose of this report is to obtain Council approval to award contract 082-T-09 Glenbourne and Glenridge Area Sanitary Sewer in part or in whole subject to receipt of sufficient support from the property owners.
The Glenbourne
and Glenridge Area is located south of Major Mackenzie Drive and east of Warden
Avenue (Appendix “A”), and includes Glenbourne Park Drive, Scandia Court,
Glenhollow Court, Glenmaple Court, Glenridge Drive, and Walnut Glen Place. Residents within this area are currently
served by individual septic system. Staff
reported on the status of the project in “Glenbourne and Glenridge Communities
Sanitary Sewer” on May 26, 2008, and awarded the contract for detailed design of
a sanitary sewer system in “Award of RFP #173-R-08 Glenbourne ad Glenridge
Sanitary Sewer” to Cole
The Glenbourne and Glenridge Area was separated into three groups based on the type of municipal sanitary sewer system:
Group 1 Area (6 properties) North of walkway |
- |
Construction of a gravity sewer system |
Group 2 Area (68 properties) South of walkway |
- |
Construction of a low pressure sewer system (LPS) - forcemain |
Group 3 Area (9 properties) North of walkway |
- |
Gravity service connections to the existing gravity sewer constructed by the Angus Glen Developer |
The owner of
1. The entire Group 2: 68 lots (Part 1 of Tender);
2.
The short section to
accommodate Nos. 24, 26, 39 and 31
3. The balance of the community at a later date if option 2 above is exercised (Part 3 of the Tender); or
4.
Group 1: Six lots at the north
end of
Advertised |
ETN |
Bids closed on |
|
Number picking up bid documents |
13 |
Number responding to bid |
4 |
The tender was broken into four parts to accommodate potential award of the contract in different phases.
Company |
Prices
(excluding GST) |
|||
Part 1 (68 lots) |
Part 2 (4 lots) with one lateral |
Part 3 (64 lots) |
Part 4 (6 lots) |
|
1. Digit Excavating Inc. |
$396,085.00 |
$38,610.00 |
$371,155.00 |
$101,152.00 |
2.
HDC Services Ltd. |
$590,542.00 |
$40,115.00 |
$551,336.50 |
$145,027.00 |
3.
Dig-Con International Ltd. |
$632,040.25 |
$39,815.00 |
$585,432.00 |
$162,100.10 |
4.
North Rock Group Ltd. |
$1,009,268.31 |
$33,100.85 |
$918,875.00 |
$219,205.11 |
Note: Prices are exclusive of GST and have been
verified for accuracy and compliance with the tender terms and conditions.
A public
information meeting with the residents of Glenbourne and Glenridge communities
was held on
B. If sufficient support is received from
the residents of Group 2 (68 lots):
Staff will award the contract according to the proposed resolution as outlined in the report.
o Total Estimated Project Cost (Group 2, 68 Lots – Forcemain, Part 1
of Tender): The total project costs include the cost of construction and engineering
fees. This project cost does not include
the resident’s cost to connect their private property to the sewer.
Construction
Cost for Part 1 Works |
$396,085.00 |
Add:
Construction Contingency |
$59,412.75 |
Sub Total |
$455,497.75 |
Add: Engineering Design Fees (approved
previously under RFP 173-R-08) (A) |
$74,699.84 |
Add: Contract Administration Fees |
$33,831.00 |
Add: Contract Administration Contingency |
$3,383.10 |
Add:
Geotechnical Investigation during construction phase (estimated) |
$7,000.00 |
Total Construction Cost |
$574,411.69 |
Add: Project
Management by Town Staff (6% of total const.) |
$34,464.70 |
Total Project Costs (B) |
$608,876.39 |
Total Additional Funding Required (B)-(A) |
$534,176.55 |
o Funding: If approved by Council, the Town will front-end the
project cost for Part 1 works (68 lots) with funding from the Waterworks
Stabilization/Capital Reserve deposited into capital account 058-5350-8524-005
and
recover the Total Project Costs (B), which includes the design fees, from the
benefiting property owners.
o Method of Cost Sharing: Under Section 391 of the Municipal Act, the project
cost for Part 1 works could be equally shared by the property owners of Group 2
approx. $8,960/lot.
o Method of Payment: If approved by Council, residents of Group 2 will have to pay the Town back for their share of the cost by a one-time lump sum payment or by installments over 10 years, plus accrued interest.
C. If
insufficient support is received from the residents of Group 2 (68 lots) by
The
owner of
In the event that the required community support for the 68
lot sewer is not obtained by April 28th, Staff
is seeking authorization to proceed with the award of contract for Part 2 only
(4 lots) The award will only occur under
the following key conditions:
o All project costs,
including design fees, associated with this contract will be paid for by the
owner of
o Council adopt a
by-law under s. 391 of the Municipal Act, to levy one quarter of the Part 2 (4
lots) project cost (including design fees) against each of Numbers 26, 29 and
o The Town and the
owner of No. 24 Glenbourne Park Drive, who is front ending the cost of the
sewer installation for all 4 lots, enter into an agreement to ensure that, in
the event that the rest of the community (64 lots) proceeds with the sewer
installation, they will incur no additional costs as a result of doing this 4
lot installation in advance, and to provide for reimbursement of costs to the
front ending owner as Nos. 26, 29 and 31 connect to
the sanitary sewer.
o Total Estimated Project Cost (Group 2, 4 Lots – Forcemain with one
lateral only, Part 2 of Tender): The total project costs include the cost of
construction and engineering fees. This
does not include the resident’s cost of connection on their private property.
Construction
Cost for Part 2 Works |
$38,610.00 |
Add:
Construction Contingency |
$5,791.50 |
Sub Total |
$44,401.50 |
Add: Engineering Design Fees (approved
previously under RFP 173-R-08) (C) |
4,394.11 |
Add: Contract Administration Fees |
$8,326.50 |
Add: Contract Administration Contingency |
$832.65 |
Add:
Geotechnical Investigation during construction phase (estimated) |
$500.00 |
Total Construction Cost |
$58,454.76 |
Add: Project
Management by Town Staff (6% of total
const.) |
$3,507.29 |
Total Project Costs (D) |
$61,962.05 |
Total Additional Funding Required (D)-(C) |
$57,567.94 |
If the Town proceeds with the
construction of Glenbourne and Glenridge Communities Sanitary Sewer Part 1 (68
lots) works, the total project cost will be front-ended by the Town and
recovered by imposing an equal fee against each of the benefiting property
owners abutting the works in accordance with Section 391 of the Municipal
Act.
The project can be funded from Waterworks Stabilization/Capital
Reserve deposited into capital account 058-5350-8524-005 and paid back with the
appropriate interest. The s. 391 by-law will provide the residents with the option of paying
the full amount either as one interest free lump sum payment or annually up to
a maximum 10 years with interest payable at the 10 Year Region of York
Debenture Interest Rate in
effect on the date the by-Law is enacted.
Payment in full of the outstanding balance plus
accrued interest would be permitted at anytime.
Eliminating the existing septic system and replacing with the sanitary sewer system will reduce the sulphur loading in soil and water in the nearby areas and enhance the overall environment.
The Finance and
Legal Departments have been consulted, provided input and reviewed this report. The
BY: _____________________ BY: _________________________________
Steve Andrews, P.Eng. Brenda Librecz
Director of Asset Management Commissioner, Community
& Fire Services
Q:\Commission Share\Operations and Asset Management\Reports\2009\Asset
Management\Award of Tender 082-T-09 Glenbroune and Glenridge Communities
Sanitary Sewer_Apr20 09 GC_Final.doc